|
November 26, 2001, ECB Control No.:
24/95/215, 04/99/215
| Between: |
Heinz
Eckervogt and T.D. Oilfield Services Ltd.
and Walter Yates
Claimants |
| And: |
Her Majesty the Queen in Right
of the Province Of British Columbia
as represented by the Minister of Employment And Investment
Respondent |
| Before: |
Sharon
I. Walls,Vice Chair
Lesley Eames, AACI, P.App. Board Member
Julian K. Greenwood*, Board Member |
| Appearances: |
Timothy
S. Preston Q.C. Counsel for Heinz. Eckervogt
Andrew P. Schuck Counsel for T.D. Oilfield Services
Stephen B. Jackson Counsel for Walter Yates
Alan V.W. Hincks, Counsel for the Respondent |
* Julian Greenwood
was a member of the panel that heard this matter. He
has not
participated in the final deliberations
leading to these reasons for decision.
REASONS FOR DECISION
1. INTRODUCTION
[1] The claimants had interests
in three placer gold mining leases on a tributary of
the Tatshenshini River, in the north-west corner of
British Columbia, close to the Yukon border. The claimant,
Heinz Eckervogt, was the owner of all three leases.
They were referred to in the hearing as the Upper Lease,
Middle Lease and Lower Lease. Eckervogt operates a highway
lodge in Haines Junction in the Yukon, about 115 kilometres
(72 miles) from the leases. Eckervogt had granted a
right to mine over one lease and a portion of a second
lease to D. & B. Oilfield Contracting Ltd. This
agreement was set out in writing. The principal of this
company was Douglas Busat who had extensive experience
with his company in the oilfield and heavy equipment
business, as well as some prior placer mine experience.
This claimant is based in Fort Nelson, British Columbia,
very approximately 1,600 kilometres (1,000 miles) from
the leases. D. & B. Oilfield Contracting Ltd mined
part of the Middle Lease during the summer of 1993.
Subsequent to the events leading to this hearing, D
& B Oilfield Contracting Ltd. was amalgamated into
the present claimant T.D. Oilfield Services Ltd. ("TD").
Thus any right to compensation earned by D & B Oilfield
Contracting Ltd is now properly directed to TD, and
for simplicity, both companies will be referred to in
this decision as TD. Eckervogt had also granted a similar
right to mine over the third lease to the claimant Walter
Yates. Yates is a real estate developer and equipment
operator who lives in Cedar Park, Texas. He had spent
a number of summers mining in northern British Columbia,
including mining on the Upper Lease in 1982, as well
as the mining on the Lower Lease in the summers of 1992
and 1993.
[2] On October 15, 1993 the
respondent (the "Crown") established the Tatshenshini-Alsek
Provincial Park as a Class A park. The new park included
the area of the three mining leases. Since no mining
is permitted in a Class A park, the Crown eventually
admitted that it had, by this action, expropriated the
claimants' interests in land. Compensation to be paid
is under the Expropriation Act, R.S.B.C. 1996,
c. 125 ("the Act").
[3] The question of compensation
for the claimants Eckervogt and TD was at first taken
by agreement to a private arbitrator, Douglas Campbell.
Mr. Campbell issued a decision in which he awarded some
compensation to Eckervogt and TD. The Crown applied
for a judicial review of that decision and succeeded
in having the decision quashed by the Supreme Court
for arbitral error. The claimants subsequently came
to this board for determination of compensation. Yates'
application, although separate from that of Eckervogt
and TD, was heard at the same time by consent. At the
commencement of the hearing, Yates' lawyer indicated
that, other than leading evidence from Yates himself,
he would take little part in the hearing and rely simply
on the evidence presented by Eckervogt and TD.
[4] The three claimants say that as a result
of the expropriation they have together lost property
in excess of $2,000,000. They have valued the three
leases using the discounted cash flow ("DCF")
approach. A mining engineer has mapped the leases and,
extrapolating from TD's mining experience on the Middle
Lease in the summer of 1993, has estimated the volume
of gold that could have been extracted from all three
lease areas. Based on TD's records from 1993, the mining
engineer has estimated that it would have taken some
seven seasons to mine that amount. Mining or operating
costs, again derived from TD, were deducted from the
price obtainable for the estimated gold in each season
and the resulting income was discounted back to the
date of taking and reduced for taxes. The total compensation
sought was allocated between the claimants based on
the amount of gold that was estimated on each claimant's
interest in the relevant lease(s) plus Eckervogt's royalty
payments, less each claimant's share of the mining costs,
each discounted to present value separately. There were
some minor differences in how the claimants' experts
apportioned the compensation between the three claimants
but both attributed between 30 and 40% of the total
valuation of approximately $2,000,000 to each of Eckervogt
and TD and a somewhat smaller percentage to Yates.
[5] It took some time before the Crown made any
advance payment but finally on September 26, 1997 the
following payments and allocations were made:
| Heinz Eckervogt |
|
|
market value for PL 1762 - the Lower Lease: |
$ 25,000 |
|
market value for PL 1271 - the Middle Lease: |
$ 70,000 |
|
market value for PL 1287 - the Upper Lease: |
$ 5,000 |
| TD Oilfield Services |
|
|
market value for PL 1271 and 1287: |
$200,000 |
|
disturbance damages: |
$ 50,000 |
| TOTAL |
$350,000 |
The Crown made no advance payment to Yates, perhaps
because it understood that Yates had given up mining
on the Lower Lease before the expropriation in October,
1993. On November 3, 1997, the claimant Eckervogt returned
the advance payment of $25,000 made to him for the market
value of the Lower Lease to the Crown because he and
Yates could not agree on the disposition of the funds.
The overall advance payments are considerably higher
than the amounts that the Crown now argues should be
paid as compensation.
[6] The Crown submits that in the circumstances
of this case the DCF method of valuing the three leases
is not appropriate. Instead it says that the Direct
Comparison Approach should be used to value each claimant's
interest independently. There are no examples of placer
mining leases changing hands at anything close to a
sum within the range of $500,000 to $900,000. The Crown
points to the actual terms on which the leases themselves,
or interests in the leases, had been acquired, and at
market evidence of the transfer of other placer leases,
and it argues for a total market value for the three
leases of $13,500. This, it says, is the value of Eckervogt's
interest as the owner of the three leases. The Crown
states that neither of the agreements granting a right
to mine to TD and Yates have any market value.
[7] Both TD and Yates also claim disturbance
damages. As a result of the expropriation TD incurred
prospecting expenses to find a new mining property earlier
than it otherwise would have done. If there had been
no expropriation and TD had continued to mine on the
subject leases, assuming that it mined all three, TD
says that it would have been mining on the subject leases
for another six years. Therefore, TD claims damages
for incurring the prospecting expenses six years prematurely.
The present value of the claimed prospecting expenses
discounted for six years is approximately $97,000. In
the alternative, assuming TD mined only that area of
the leases set out in its written agreement to mine,
it says that the mining would have been for another
three years. The present value discounted for three
years is approximately $53,000. The Crown concedes that
TD is entitled to some disturbance damages, but says
that since TD only had the right to mine the Upper Lease
and a portion of the Middle Lease, it is restricted
to a maximum claim based on the discount for only three
years or $53,000. Further, the Crown says that TD would
in fact have only mined one further year on the subject
leases and therefore the exploration costs were only
advanced by one year. Finally, according to the Crown,
the costs include some items that are inappropriate
and need to be reduced accordingly.
[8] Yates makes alternative claims for disturbance
damages. If the DCF approach for market valuation of
Yates interest is accepted then Yates claims $30,000
for early demobilization of his mining operation including
losses on some of the equipment. If the DCF approach
is not accepted then Yates claims either:
| i |
the loss of the cash flow projected by the
DCF approach as disturbance damages, or, at
a minimum, |
| ii |
all of his expenses spent on the mining operation
in 1992 and 1993 since the expropriation truncated
the mining operation before any income was received.
The expenses claimed totalled approximately
$87,000 after allowing a set off for the sale
of some of the equipment. |
The Crown denies all of these claims for disturbance
damages on a number of grounds including the fact that
Yates had not actually incurred any losses that arose
out of the expropriation.
[9] Thus the main issue in this hearing was the
appropriate approach to market valuation, as well as
the actual valuation, of the three claimant's interests
in the expropriated leases given the circumstances that
existed at the date of expropriation. A secondary issue
was the amount of disturbance damages to which TD and
Yates were entitled.
2. BACKGROUND
2.1 Leases and Agreements to Mine
[10] Two of the leases, the Lower, or most downstream
lease, and the Middle Lease were on Squaw Creek which
is a tributary of the Tatshenshini River. These two
leases on Squaw Creek were contiguous. The Upper Lease
was on the North Fork or Paddy Creek, which was a tributary
of Squaw Creek. The Upper Lease was contiguous with
the side boundary of the Middle Lease just above where
the North Fork flowed into Squaw Creek. The Middle Lease
extended further up Squaw Creek above the junction or
confluence with the North Fork. There was some uncertainty
as to the exact size and location of the three leases
as they are defined by staking under the Mineral
Tenure Act, S.B.C. 1988, c. 5 (and the predecessor
legislation) and some of the original posts have disappeared.
According to the original placer leases filed with the
Gold Commissioner, the Lower and Upper Lease were approximately
805 metres (2,640 feet) long with 201 metres (660 feet)
on either bank of the creek for a total of width of
402 metres (1,320 feet). This means that the leases
appear to be very approximately 32.36 hectares (80 acres)
in size.
[11] The claimant Eckervogt staked the Upper
Lease on the North Fork and the Crown granted the placer
lease PL 1287 on December 29, 1978 for a term of ten
years. On December 9, 1987 Eckervogt applied to extend
the lease for five years until December 29, 1993. On
September 23, 1992, as a result of legislative changes
to the provisions governing placer leases, the Crown
rescinded and replaced the five-year extension of the
lease with a ten-year extension to December 29, 1998.
[12] The Middle Lease, PL 1271, was originally
granted in December 29, 1978 for a ten-year term. On
July 27, 1980 Kevin Schropfer sold the lease to Eckervogt
for $32,000. On December 9, 1987 Eckervogt applied to
extend the lease for five years until December 29, 1993.
On September 23, 1992, as a result of legislative changes
to the provisions governing placer leases, the Crown
rescinded and replaced the five-year extension of the
lease with a ten-year extension to December 29, 1998.
[13] The most downstream or Lower Lease, PL 1762,
was originally granted for a term of 20 years commencing
on December 15, 1972. On December 12, 1977, records
in the Gold Commissioner's office indicated that the
lease was sold from Phyllis Ross of Vancouver to Karl
Gruber of Whitehorse for $2,500. On July 21, 1987 Karl
Gruber sold this lease to the claimant Eckervogt for
$30,000. On December 15, 1992 the Crown extended the
term for 10 years until December 15, 2002.
[14] On June 1, 1992, the claimant Eckervogt
entered into a written mining lease agreement with the
claimant Yates. We note that Yates was born in 1924
and thus was 68 in 1992. This agreement, which was drafted
and typed by Yates, replaced a hand written agreement
made in 1991. Under this 1992 agreement, Yates could
mine the Lower Lease in return for a royalty of 15%
of the gold recovered, payable at the end of each mining
season. The agreement was for five years to June 1,
1997 with an option to renew for an additional three
years to June 1, 2000. Yates paid no monies up front
for this right to mine the Lower Lease; his only obligation
was to start testing in the 1992 season and to have
a wash plant and related equipment on the claim in the
1993 season, provided the test results were positive.
There was some suggestion that Yates had in fact given
up mining on this lease in July 1993 prior to the expropriation,
but Yates denied this. There was evidence that supported
Yates' testimony that he intended to keep mining during
the summer of 1993 and we accept that his agreement
to mine was in place in October 1993. But for the expropriation
he may have attempted further mining in 1994.
[15] The claimant Eckervogt and the principal
of the claimant TD, Douglas Busat, began discussion
in 1992 with respect to TD mining the Upper Lease and
part of the Middle Lease. TD did some testing on the
claims in 1992 and in May 1993. On June 9, 1993, Eckervogt
and TD recorded their oral agreement in writing. TD
was given the right to mine the Upper Lease and the
portion of the Middle Lease downstream from the mouth
of the North Fork (approximately two thirds of the Middle
Lease), on payment of a royalty to Eckervogt. TD would
pay Eckervogt 10% of the first 15 ounces of gold recovered
on each "clean-up", or recovery of gold from
the wash plant, and 20% of any gold over that amount.
The agreement was for three years to June 9, 1996 with
an option for a further three years to June 9, 1999.
Payment was actually to be made in gold. As with the
Yates agreement, TD paid nothing to enter into this
agreement. TD was not obligated to do any mining unless
it decided after testing to do so. If it did decide
to mine it agreed to mine a minimum of 25,000 cubic
yards per year. TD also agreed to comply with all regulations
including the restoration of the mining area to the
state required and to keep the property free from any
liens. Failure to comply with any of these provision
rendered the lease agreement void.
[16] Thus at the time of expropriation in October
1993 there were agreements in place to mine the three
leases. The only area that was not subject to an agreement
to mine was the upper end of the Middle Lease on Squaw
Creek above the confluence with the North Fork. Eckervogt
had retained the right to mine this area thinking that
he or his family might want to do some more mining in
the future.
[17] The three leases were difficult to reach.
Access was from the Haines Road, which runs from Haines
Junction on the Alaska Highway in the Yukon to Haines,
Alaska. Some 90 kilometres south of Haines Junction,
a rough dirt road approximately 25 kilometres long ran
from the highway to the leases. Four wheel drive vehicles
were required to access the claims. Various streams
had to be forded, including at one point the Tatshenshini
River. The route crossed the Yukon-British Columbia
border a short distance before the most downstream or
Lower Lease. The trip in from Haines Junction (the nearest
community of any size) took an average of six hours.
Depending on the conditions and what was being carried
or towed, it could take anywhere between three and twelve
hours.
2.2 Geology
[18] The board received extensive geological
evidence from a number of witnesses. Michael Milner
and Stephen Morison testified for the claimants; Dr.
Victor Levson appeared for the Crown.
[19] Placers are formed when eroding rivers cut
through gold-bearing rocks. Lighter materials get washed
downstream, while gold, being heavy, tends to fall downward
and to become concentrated in the bottom gravels at
the bedrock layer. Placer gold therefore refers to gold
that has been washed from its original bedrock sources
to find its way into river gravels. Because rivers and
streams are not static, but can take a variety of routes
over the centuries, placer gold can be found, not simply
in the present-day creek bottom gravels, but also in
older stream channels which may lie elsewhere in the
valley, including under terraces or benches some distance
above the valley floor. The experts differed sharply
as to how much evidence there was for gold bearing older
stream channels in Squaw Creek.
[20] Placers are also affected by glaciation.
Glaciers can be quite erosive and may erode older placer
deposits. Also, glaciers leave behind material known
as till as they retreat, and the till can bury older
placers and make them harder to find. Finally there
was some evidence that glaciers sometimes may concentrate
the gold. The Squaw Creek area was once entirely glaciated,
although again there were differing views among the
experts on how much effect the glaciation may have had
on the placer deposits in Squaw Creek.
[21] There were differences of opinion between
the geologists on the likelihood of placer gold being
found on the North Fork in the Upper Lease. This creek
passed through a narrow gorge with a waterfall not far
above its confluence with Squaw Creek. Above that point
it lay in a different geological zone or terrain than
did Squaw Creek. Levson, who testified for the Crown,
theorized that the North Fork, lying generally in a
different terrain, and in a wider valley above the falls,
was less promising as a bedrock source for gold than
Squaw Creek. The claimants' witnesses thought otherwise,
but there was little evidence of gold, or the lack of
it, from the Upper Lease to support either opinion.
We did have evidence from the claimant Walter Yates
as to the gold that he recovered on the Upper Lease
(see section 2.3.2 below). There was also evidence from
the miner Alan Dendys as to poor results from his testing
further up the North Fork. Finally, TD's test done on
the North Fork near the confluence with Squaw Creek
recovered the lowest concentration or grade of gold
of the six tests that were done.
[22] The claimants also suggested that gold might
be found in the glacial till deposits and glaciofluvial
deposits found further up the hillsides. In practice,
the only mining history on Squaw Creek had been in the
valley bottom. But since the leases were wide enough,
at approximately 400 metres, to include a substantial
amount of the valley benches and hillsides, the possibility
of placer gold in these unexplored areas was of some
importance to the claimants. Morison, a geologist for
the claimants, gave some support for gold being found
in the glacial tills; however he appeared to be speaking
largely theoretically. There was a British Columbia
Minister of Mines Report with respect to Squaw Creek
that Morison interpreted as supportive as well as publications
that indicated gold had been found in these types of
deposits elsewhere in British Columbia. The only actual
evidence of gold in Squaw Valley tills was a single
grain of gold found several kilometres downstream in
what were assumed by Morison to be similar material.
At this location the miner, Jerry Reid, had reportedly
found some gold in tills present as overburden (the
soil overlying the gravels that is normally stripped
before the gravels are put through the wash plant) as
well as in the stream bed gravels underneath, but we
were not given any detailed evidence. By contrast, the
likelihood of till containing any economic quantity
of gold was strongly contested by the Crown's expert
Levson. The board learned that Morison had co-authored,
with Levson, a chapter in a geological text on placer
deposits in areas of glaciation which stated that "gold
concentrates in till … are too low to mine … but may
locally be worth processing with improved recovery systems"
and "economic gold concentrations are also rare
in glaciofluvial deposits and are usually restricted
to areas where meltwaters have reworked older placers".
[23] It appeared that the only issue on which
the geologists (and miners) were in agreement was that
the concentration of gold in placer deposits tends to
be very variable. The gold is not fixed in the rock
but has been carried by water flowing in streams and
rivers and then by gravity migrated down through layers
of gravel. As a result it is unwise to assume that a
grade (weight of gold per unit volume of gravel) found
at one test site will be repeated at other places. This
is to be contrasted with hard rock mining of gold where
the deposits or reserves that have intruded into the
rock can be mapped in all three dimensions with sufficient
drilling.
2.3 Mining History on Squaw Creek
2.3.1 Generally
[24] We heard evidence from a number of people
who had mined on Squaw Creek including the claimant,
Heinz Eckervogt; his son, Martin Eckervogt; the principal
of the claimant TD, Douglas Busat; the claimant, Walter
Yates; and two other miners, Daniel Johnson and Alan
Dendys. There were also a number of reports referring
to the history of mining on Squaw Creek.
[25] Placer gold has been recovered from Squaw
Creek for many years, with the first staking in 1927.
By 1928 the entire creek was staked, although mining
was initially haphazard and only on a few claims. However,
mining activity increased, and during the 1930's there
were up to 45 miners at a time. Mining dwindled with
the beginning of the war in 1939. A British Columbia
Department of Mines Bulletin in 1948 reported that although
the records showed 3,500 ounces of gold had been removed,
it was likely that up to 5,000 ounces of gold had already
been recovered from Squaw Creek.
[26] In these early years access was by wagon
road and pack trails. The mining would have been hand
mining with relatively crude wash plants. Gravel would
have been shovelled into pans or sluice boxes through
which water from the creek was run, washing away the
gravel and leaving the heavier gold behind. In 1943
the Haines Road was built so that there was better access
to within approximately 25 kilometres of the claims.
[27] In the 1960's the Minister of Mines' reports
indicate that a mining company carried out some mining
on Squaw Creek using a bulldozer and a hydraulic sluicing
system. In the 1970's a rise in the price of gold led
to renewed interest, and the area was restaked. Although
some hand mining continued, more miners brought in equipment
such as excavators, backhoes, and loaders to excavate
and move the gravel. Since placer gold concentrates
at the bedrock level, the ability of the equipment to
dig down to bedrock is important. We heard evidence
of variable depths of gravel encountered on Squaw Creek:
from as low as three feet, to a high of 60 feet, with
an average of about 12 feet. The wash plants also became
more sophisticated with pumps and more efficient recovery
systems, although from the evidence we heard there was
considerable variation in the wash plants used on Squaw
Creek, most of which were self-designed.
[28] We heard considerable evidence from Daniel
Johnson with respect to his mining of the two claims
on Squaw Creek that were immediately downstream of the
Lower Lease. This mining occurred in 1988 and 1989 as
a joint venture between Johnson, Black Cliff Mines,
and Menora Resources. It was a relatively large-scale
operation with $700,000 of equipment and machinery and
a work force that for a short time near the end of the
1989 season employed 12 people, running two shifts.
The area was extensively tested in 1988, and the valley
floor was completely mined over that year and the next.
Johnson told the board that there had been many miners
on these two claims, the most recent of whom, Terry
Thompson, had mined the area for several years in the
1980's. As a result Johnson thought that less than 5%
of this area was truly virgin ground. He reported that
the average grade on these two leases, expressed in
value, was $5.50 per cubic yard (measured by bucket
volumes). A total of 1,130 ounces of gold was recovered.
At the reported grade this suggests something over 100,000
cubic yards mined in the two years, although Johnson
reported mining more than twice that.
[29] It is of some significance to note that
the Black Cliff-Menora-Johnson venture never reported
a profit. There was no further mining after 1989, and
the corporate partners took their equipment out in 1990.
Johnson stayed for a while, trying to mine other leases
upstream of the Middle Lease on Squaw Creek, but gave
up when he experienced greater depths of overburden
which made the operation too risky. He eventually moved
to carry on placer mining in an area near Atlin.
2.3.2 PL 1287 - the Upper Lease
[30] This lease on the North
Fork was the one that was originally staked by the claimant
Eckervogt. The lease extended from the side of the Middle
Lease to a point on the North Fork above the waterfall.
The falls presented a barrier to mining. This lease
had more boulders than the other two leases. Boulders
generally cannot be processed in the sluice box with
the gravel. If they are large the equipment has to mine
around them. If they are smaller the loaders may move
them aside. Aside from these practical difficulties,
the presence of boulders affects the recovery rate or
grade for the gold since they are part of the ground
that is not mined.
[31] Eckervogt carried out some
testing and mining on this lease shortly after acquiring
it. Records filed in the Gold Commissioner's office
by Eckervogt describe his gold recovery as "poor"
and "very poor".
[32] In 1982 the claimant Yates entered into
an agreement to mine this lease with Eckervogt. The
payment to Eckervogt was in the form of a royalty or
percentage of the gold that was found, although we were
not provided with evidence on the amount of the royalty.
Yates worked the lower end of this lease, near the confluence
with Squaw Creek. Given the uncertainty of the exact
location of the leases, it appears that some of this
mining on the North Fork near the confluence may have
been in fact on the Middle Lease since the Middle Lease
extended on both banks of Squaw Creek including the
lower reaches of the North Fork. Yates, who at the time
had no placer experience, worked with two partners.
They had an old loader and bulldozer. Using a collection
of ideas obtained from other miners, they built a single-run
wash plant of their own design at the site. Working
upstream toward the falls they fairly soon found themselves
facing a number of difficulties: excessively deep gravels,
water seepage from the creek, and, near the base of
the falls, very large boulders making up about half
the total volume of gravel in places. Yates found that
the size and quantity of the boulders in this location,
some of them reportedly as large as a small car, made
any mining very difficult, especially given the calibre
of equipment they were using. They kept no records.
Yates estimated, in hindsight, that his operation was
probably less than 50% efficient (in other words it
would have only caught about half of the gold). Over
the 1982 summer he and his partners recovered some 90
to 100 ounces of gold, including one 13-ounce nugget.
Yates did not continue to mine the Upper Lease in 1983,
considering that the conditions were too difficult for
his methods and equipment. He agreed that it was easier
to mine the gravels on Squaw Creek than the conditions
he encountered on the North Fork on the Upper Lease.
[33] We heard some evidence about further testing
on the North Fork by the miner, Alan Dendys. He testified
that the concentration of gold decreased the further
he went up the North Fork. As mentioned above, the right
to mine this Upper Lease was later assigned to TD's
predecessor in 1993. However it appears that no further
mining took place after 1982 on the Upper Lease before
the right to do so was foreclosed by the creation of
the park.
2.3.3 PL 1762 - the Lower Lease
[34] This lease was the last one acquired by
Eckervogt in 1987. Records in the Gold Commissioner's
office indicate that in 1981 there was an application
to record work on the lease by Karl Gruber, the cost
of which work was well over $150,000. In 1983 Gruber
filed an application to record work which indicated
that some hand sluicing had occurred over two weeks
in August of 1982. The miner, Daniel Johnson, also testified
that in 1982 he did some hand mining on the Lower Lease.
It appears from records in the Gold Commissioner's office
that in 1983 and 1984 the miner, Terry Thompson, mined
this lease, or a portion of it, at the same time that
he mined the two leases immediately below the Lower
Lease. However, the mining of this lease was apparently
not authorised by Gruber.
[35] In 1987 Eckervogt entered into an agreement
with Dendys to supervise mining of the Lower Lease in
return for a percentage of 6% of the gold recovered.
Eckervogt was in the process of acquiring the lease
from Gruber during that season. The gold price in 1987
was $592 an ounce; it was significantly higher than
the price of $511 per ounce in 1986 or the price of
$484 per ounce on October 15, 1993, the date of expropriation.
There was some talk of a partnership involving Dendys
but in the end Dendys did not sign the documents and
he left Squaw Creek with his equipment after the 1987
season. Dendys told the board that he and his four person
team (which included Martin Eckervogt, the son of the
owner) worked the Lower Lease from May 30 to October
14, 1987, during which time he estimated they sluiced
for about 108 days. They used a simple single-run wash
plant. Dendys estimated (without records) that they
sluiced on average about 1,200 cubic yards a day, in
two shifts, for a seasonal total of some 130,000 cubic
yards (loose volume). His records indicated that 1,395
ounces of gold were recovered, including the largest
nugget ever found in North America (74.5 ounces.). Some
of the wages for the six employees, including the cook,
were paid as a percentage in gold. Martin Eckervogt
stated that the operating costs were high in that year
and company records indicate that $206,469 was paid
in total wages (including those paid in gold) while
the cost of mining, including wages, was $321,173. Mining
revenue was reported at $486,224 but after deduction
of mining expenses, exploration expenses, administration
expenses, and taxes the net income was reported to be
$60,190. The valley bottom was completely mined over
that summer, although Dendys agreed that they had bypassed
some portions when the results were poor. By the end
of the 1987 mining season, Dendys felt there was little
gold left, unless there was more under the hillsides
themselves.
[36] Little happened on the Lower Lease between
1987 and 1991 when Walter Yates did some testing on
the lease and entered into a right to mine with Eckervogt.
Yates testified that in 1991 he met Daniel Johnson,
who had been mining immediately downstream of the Lower
Lease with the Black Cliff-Menora venture. Yates had
been encouraged by Johnson's results and he approached
Eckervogt for the right to mine the Lower Lease. Early
in the 1992 season Yates spent considerable time repairing
the road, creating settlement ponds, and building a
wash plant of his own design on site. He experienced
difficulties with the equipment and only mined 100 -120
cubic yards of material in 1992, recovering about three
ounces of gold. Then in the spring of 1993 he injured
himself while repairing his backhoe. By the time he
returned to the lease, it was general knowledge that
the park would be established and his mining would have
to stop. He did not do any further mining in 1993.
2.3.4 PL 1271 - the Middle Lease
[37] The Middle Lease was the second lease to
be acquired by Eckervogt in 1980. The gold price in
1980 was at an all time high at over $US600 per ounce.
(The price for gold is traditionally quoted in US dollars
per Troy ounce, as set in the London Metal Exchange
PM fix and converted at London closing exchange rates.
The expert witnesses provided us with the price in Canadian
dollars in most circumstances using an appropriate exchange
rate for the time in question. We were not given the
conversion rate for 1980.) There were two cabins on
the Middle Lease, situated on the right side of the
creek facing downstream, which showed up in some photographs
and were sometimes used as geographical references.
Above the cabins, the North Fork entered the creek from
the right side, approximately two thirds of the distance
upstream from the lower boundary of the Middle Lease.
[38] Eckervogt testified that he had sold his
first highway lodge on the Haines Road in 1980. In 1981
and 1982 he brought some equipment onto the Middle Lease
and with his sons mined what he estimated was 6,000
cubic yards in the first season and some 4,000 cubic
yards in the second season. He was using two loaders
and a sluice box of his own design to do the mining.
There were no records of the amount of gold recovered
nor were there any records of the number of days that
were mined or the amount of material mined per day.
Eckervogt suffered a heart attack in the spring of 1983
that forestalled any mining for 1983 and he also bought
another motel that year. He did not return to Squaw
Creek until 1989, when he and his sons mined an alluvial
fan that descended into the valley bottom of the lease
area, keeping no records and again getting relatively
poor recoveries.
[39] Then in 1992 Douglas Busat, the principal
of TD, did some testing on a number of leases on Squaw
Creek. Busat had been an oilfield contractor and heavy
equipment operator for many years, and had considerable
expertise in designing, maintaining, and operating machinery.
He had started some placer mining in the early 1980's,
first at Fourth of July Creek, north of Haines Junction
in 1981 and second at McDame Creek, near Cassiar, in
1987 and 1988. In 1992 Busat did some testing on the
Middle Lease, and, acting through the predecessor of
his company TD, made an oral agreement with Eckervogt
for the right to mine. Over the winter of 1993 Busat
built what was described to the board as a "state
of the art" wash plant, which cost him about $150,000
in materials. Near the end of May 1993 he went into
the leases with his equipment to set up camp, and to
dig test holes and choose the best mining location.
This was a fairly major undertaking involving a number
of trips to bring in equipment, some of it from Haines
Junction and some of it from his base in Fort Nelson,
about 1,600 kilometres (1,000 miles) away. The initial
testing involved digging six trenches in various locations
on the Middle Lease down to bedrock at an average of
12 feet below the surface. Busat recorded the results
as price of gold per cubic yard based on a price of
gold of $500 per ounce. The six holes tested between
$7.50 per yard and $18.00 per yard. After he had carried
out the tests, Busat, on behalf of TD, prepared the
written agreement to mine that he and Eckervogt signed.
Eckervogt inserted the exclusion clause for the area
of the Middle Lease on Squaw Creek above the confluence
with the North Fork. During the remainder of June, TD
carried out preliminary work such as repairs to the
road, construction of settling ponds, setting up the
wash plant, and stripping the ground of overlying soil
and vegetation. There were five workers in total: Douglas
Busat, his wife Carol Busat, Martin Eckervogt, son of
Heinz Eckervogt, and two other men who had worked for
TD intermittently for eight years. Martin Eckervogt
and the other two men operated the equipment, Carol
Busat did the cooking and some of the record keeping,
and Douglas Busat filled in on the equipment during
meal breaks, serviced the equipment, and carried out
the gold clean-ups.
2.3.5 The 1993 Mining Season on the Middle
Lease
[40] TD began some preliminary sluicing of gravel
towards the end of June and, after taking a break for
four or five days, began actual mining of the Middle
Lease on July 3, 1993. TD kept daily time sheets for
the hours worked by each employee and each piece of
equipment. These time sheets also recorded a brief description
of what was done each day including the number of cubic
yards that were put through the wash plant, maintenance
of the equipment, and trips out to Haines Junction and
Fort Nelson. The number of cubic yards was estimated
from the bucket counts on the back hoe used to feed
the wash plant (the backhoe had a counter that could
be clicked for each bucket). There were also records
of the gold recovered at each clean-up and the amount
paid to Martin Eckervogt as royalty payments for his
father.
[41] According to Martin Eckervogt, mining began
near the bottom of the Middle Lease, just below the
lower cabin, and followed a path upstream more or less
to the level of the upper cabin, near the confluence
of Squaw Creek with the North Fork. This first cut was
close to the right edge of the valley looking downstream.
The width of the cut was essentially the reach of the
excavator used to excavate the gravel on either side,
although it varied somewhat with the topography. The
average depth of gravel to bed rock was reported to
be 12 feet. The records show that on the first cut an
average of about 340 cubic yards of gravel was put through
the wash plant each day, except for another five or
six day break around August 1. The gold recovered in
each clean up during this cut varied between 250 and
700 grams. (While prices for gold are traditionally
quoted per Troy ounce, TD recorded its gold recovery
in grams and the claimants' mining valuation was expressed
in metric units. One Troy ounce is equivalent to 31.10
grams.) The grades obtained in each clean up ranged
between 0.24 and 3.09 grams per cubic metre, showing
significant variation in the gold concentration. The
average grade was 1.31 grams per cubic metre. The stream
was then diverted to the area that had been mined and
a second cut was made beside the first, more toward
the centre. This second cut started about 20 metres
further upstream than the first cut, and continued upstream
until eventually fall weather made further work impossible.
This second cut was similar in overall length to the
first cut, but with the 20 metres offset. The records
showed that on the second cut until September 16, an
average of about 420 cubic yards of gravel was put through
the wash plant every day but for a three-day break just
before September 1. The gold recovered during this period
on the second swath was higher than on the first cut
with clean ups ranging between 303 and 914 grams. The
grades obtained in this second cut again showed variation,
ranging between 0.75 and 3.66 grams per cubic metre
with an average grade of 2.13 grams per cubic metre.
On September 17, Busat made a number of modifications
to the wash plant that allowed him to increase the number
of yards of gravel sluiced per day. From September 18
to September 24, the last day of mining, about 925 cubic
yards of gravel were mined per day. Thus, in the last
week more than twice as much gravel was processed per
day as had been processed per day throughout the rest
of the season. However, the gold recovery dropped significantly
during this period, with individual clean ups varying
between 167 and 557 grams. The average grade was only
0.45 grams per cubic metre for this final week. TD's
financial statement for the year ended February 28,
1994 shows an income of $313,939 with expenses of $428,746
for a net loss of $115,000 which was reported on TD's
income tax return. Not all of this income and expenses
were related to the mining operation.
[42] In summary, the time sheets record that
a total of 22,976 cubic metres (30,050 cubic yards)
by bucket count were sluiced on 72 sluicing days and
26,023 grams (837 ounces) of gold were recovered. Busat
reported a different volume mined, namely 50,000 cubic
metres, on a Notice of Completion of Work filed with
the Ministry of Energy, Mines and Petroleum Resources
on October 26, 1993. He estimated the mined area to
be 11,000 square metres. The gold price in October 1993
was about $484 per ounce ($15.57 per gram) and the average
for 1993 at $464 per ounce was 12% higher than the price
in 1991 and 1992 at $415 per ounce.
[43] During July the news came that the park
would be established, and that mining would not be able
to continue the following year. TD did some required
reclamation in the spring of 1994 and took its equipment
out of Squaw Creek.
3. MARKET VALUE
3.1 Approaches to Valuation
[44] The claimants take the position that as
a result of TD's mining in the summer of 1993, the three
subject leases made up an operating mine which, if it
had been allowed to continue, would have produced 394
kilograms of gold, worth about $6,700,000, over the
following seven years. The claimants then subtracted
estimated mining costs each year, based on TD's experience,
to get a net annual income, and discounted those net
incomes back to the date of expropriation in October
1993 at a discount rate of 15%. This produced a present
value in October 1993 by the DCF approach of about $2,000,000,
after deducting an amount for income tax. That is what
the claimants say has been taken from them, and that
therefore is what they ask for, as a group, in compensation
for the loss of the property.
[45] The Crown says, in essence, that this estimate
of future income was and is wildly optimistic. It is
based on a number of assumptions taken from the 1993
mining season that are extremely unlikely, including
the gold grade, the volume of mineable material, the
rate of mining, and the mining costs. The discount rate
is too low to adequately reflect the major risks involved
in the analysis. In addition, there are several errors
in the claimants' analysis, all of them favouring the
claimants.
[46] However the Crown objects to the use of
a DCF approach for more fundamental reasons. Under section
32 of the Act, compensation for the market value of
the interest in the property is based on what a willing
purchaser and seller would agree as the sale price on
the relevant date. In the market, buyers simply do not
buy placer leases, or the rights to mine placer leases,
on the basis of a DCF approach. They pay much smaller
amounts. The Crown says that the Direct Comparison Approach
using the prices actually paid for transfers of gold
placer leases is a better method to estimate the market
value of the claimant Eckervogt's interest. It also
used the Income Approach on Eckervogt's royalty income
assuming two different estimates of gold recovery and
found that this approach supported the valuation by
the Direct Comparison Approach when the relatively conservative
estimate of gold was used.
3.2 Claimants' case
[47] The claimants relied on two experts for
valuation evidence. Randy Clarkson, a mining engineer,
with New Era Engineering Corporation in Whitehorse was
qualified by the board as an expert in placer mining,
capable of expressing opinions on the average grade
of the placer leases, the costs of this placer mining
operation, the life expectancy of this mining operation,
and the efficiency of placer mining operations. Toby
Symes is an accountant and business valuator, operating
Symes Valuation Services Ltd. in Vancouver. In addition,
Michael McGillivray, a chartered accountant, provided
evidence on TD's financial statements. Both Clarkson
and Symes took the same approach to value, namely the
DCF method. Symes adopted Clarkson's assumptions and
estimates of volumes of mineable material, gold grades,
mining rates and mining costs. The only difference between
the two valuers was in the choice of gold prices to
apply during the seven-year mining period. As a result,
their final estimates of value were very similar. They
also made somewhat different allocations of their final
estimates of value between the three claimants.
3.2.1 Estimate of Amount of Gold
- Volume of mineable material
[48] Clarkson had produced an initial report
in 1995 based on a brief site visit in 1994. In 1998
he carried out extensive field work on the three subject
leases that led him to revise his conclusions on the
amount of mineable material. He determined as best he
could the location of the claims, since some of the
original claim posts were missing. He made 30 transects
or cross-sections across the valley in order to map
the valley in some detail and to estimate the area of
mineable material. He described 17 different areas on
the three claims in which he had formed the opinion
that gold bearing material could be found and mined.
Relying in part on the two geologists, Michael Milner
and Stephen Morison, he decided that some of these areas
of mineable material were not simply in valley-bottom
alluvial gravels, but also in old stream beds and glacial
tills extending 10 to 20 metres up the hillside on either
side. He excluded the glacial tills that were further
up the hillside. He applied a uniform depth of 3.3 metres
(10.8 feet) to all the areas to which he attributed
gold and estimated the volume of mineable material for
each of the 17 areas that he had identified, which totalled
together came to 688,375 cubic metres.
- Probability factor on volume of mineable
material
[49] Clarkson then assigned a "probability
factor" of between 50% and 90% to each of the 17
areas that he had identified, with 50% probability being
applied to those areas further up the hillsides that
had not been tested or mined and 90% probability being
applied to the gravels in the central channel. He multiplied
the volume of material in each of the 17 areas by the
assigned probability factor, which had the effect of
reducing the volumes for each area, so that the overall
total of estimated mineable material was now 504,156
cubic metres.
[50] Clarkson used two grades of gold for the
17 different areas he had described. For areas that
Clarkson decided were previously unworked, he used the
grade that he estimated TD had encountered in its mining
on the Middle Lease in 1993. The one certainty on which
everyone agreed was that TD had recovered 26,023 grams
(approximately 837 ounces) of gold. Clarkson reviewed
the assays for this gold from Engelhard Canada Ltd.
where most of the gold had been refined. These assays
showed that the fineness or purity of the gold was an
average of 84.4% and that the payout by the refinery
was 98.5% of the gold. TD reported that this gold had
been recovered in 22,975 cubic metres (30,050 cubic
yards) of gravel measured by bucket count. However,
bucket counts record a larger volume than material in
the ground because the loose material swells. Clarkson
applied a "swell" factor of 20% to the "loose"
volume recorded in bucket counts. In addition, he recognized
that some boulders would be too large to be included
in the buckets transferred to the wash plant. He estimated
that this would have the effect of reducing the volume
in the ground by 10%. Taking these two factors together,
he calculated the bucket counts at a volume 8% higher
than in ground or "bank" volume (1.2 x 0.9
= 1.08). Clarkson calculated the average grade encountered
by TD as the grams of gold recovered per bank or in
ground volume of gravel multiplied by 84.4% for fineness
and by 98.5% for the percentage payout or 1.02 grams
per cubic metre. This grade was applied to all those
areas that Clarkson concluded had not been mined recently.
[51] Clarkson compared this grade with the grade
found by TD on the six test holes carried out in late
May and early June 1993. He converted Busat's grades
measured by value to grams per cubic metre at a price
for gold that Busat used of $500.00 per ounce. Using
this price he obtained an average grade of 0.95 grams
per cubic metre which he concluded was relatively close
to TD's average grade encountered in mining of 1.02
grams per cubic metre.
[52] Clarkson visited the site after it had been
reclaimed and smoothed over; therefore he could not
tell directly how much area had been mined. He relied
on the advice of Martin Eckervogt, who pointed out an
area about 200 metres long by 39 metres wide. When Clarkson
multiplied this by what he reports being told was an
average depth of 3.3 metres (10.8 feet), and subtracted
the old stream bed, he stated that the resulting volume
of in place gravels of 22,700 cubic metres, was fairly
consistent with the 22,975 cubic metres that TD had
recorded by bucket count (or 21,273 cubic metres bank
or in ground volume).
[53] Clarkson decided that much of the previous
mining of the leases was likely to have been inefficient,
and that there should still be significant gold quantities
in what were in effect tailings, or residual gravels,
from those operations. For those areas that he thought
had been previously mined he assigned a grade that the
miner Daniel Johnson told him he had encountered on
the two leases below the Lower Lease that he had mined
with Black Cliff-Menora in 1988 and 1989. These two
leases had been mined by Terry Thompson, amongst others.
Johnson reported average results of $5.50 per cubic
yard of gravels washed. Clarkson converted this figure,
using gold prices of the period ($494.76 per ounce)
and an assumption of 80% recovery, into an estimate
that grades of 0.57 grams per cubic metre could be recovered
even from tailings.
[54] In estimating the total volume of pay materials,
Clarkson included certain areas of glacial till. He
justified this on the basis of a test on till materials
at a mine several kilometres further down the river
(the Jerry Reid mine). Clarkson's tests found one fleck
of gold 0.3 millimetres in diameter from this material,
which he assumed would be similar to the areas of till
he identified on the subject leases.
[55] Clarkson applied what he thought was the
appropriate grade, either 1.02 grams per cubic metre
for relatively undisturbed material, or 0.57 grams per
cubic metre for previously mined material, to the estimated
volumes of mineable material (bank or in ground volume)
in each of the 17 areas. After adjusting for the probability
factor, he estimated that a total of 394 kilograms of
gold could be recovered in the three claims.
[56] For gold prices, Clarkson chose to use US
dollar gold future contract prices as at the date of
taking (when the gold price was $C484 per ounce) for
the amount of gold that he estimated would be mined
each year, converted to Canadian dollars at the October
1993 exchange rate. This resulted in the price per ounce
rising from $484 per ounce in 1994 to $567 per ounce
for 1998 through 2000. Symes also used US dollar gold
future contract prices, but he converted them to Canadian
currency based on currency future contract rate. His
estimates for the gold price ranged from $491 per ounce
in 1994 to $611 per ounce for 1999 and 2000. Clarkson
estimated a gross value of $6,730,000 while Symes estimated
a gross value of $7,026,000.
3.2.2 Mining Rate
[57] Once Clarkson had decided on the locations
and volumes of pay gravel he would use, and the grades
of gold he would assume to be present, he then inserted
these numbers into a DCF model. He imagined a mining
plan that would see all the practically mineable gravels
being mined over the following seven annual seasons.
This was based on an assumption that mining would have
continued throughout the leases at a rate of 88,000
cubic metres (loose volume) or 81,450 cubic metres (bank
or in ground volume) per year.
[58] The source for the estimate was TD's 1993
mining records. However it was based on a daily volume
of 710 cubic metres (about 925 cubic yards) of loose
material that was only achieved by TD in the last seven
days of mining that year. Prior to that date TD had
mined a much smaller amount - an average of 340 cubic
yards of gravel per day on the first cut and 425 cubic
yards of gravel per day on the second cut. In his most
recent report Clarkson accepted Busat's evidence that
this increase was due to a change in the screening mechanism
of the wash plant and that any future mining on any
of the three leases would be able to maintain this high
rate. Clarkson also assumed that these 710 cubic metres
of loose material would be sluiced on every one of 124
sluicing dates per season, although in 1993 TD had only
sluiced a total of 72 days.
3.2.3 Mining Costs
[59] Mining costs were calculated by Clarkson
on the basis of TD's records, which had been classified
into various headings. First Clarkson identified $312,147
of mining expenses. He then attempted to isolate the
operating costs by deducting what he regarded as capital
costs ($121,734) and one-time mobilization costs ($28,622)
primarily related to the transportation of equipment.
This left him with operating costs of $161,793. He decided
that because TD spent the month of June on such items
as camp set-up, road repair, and settling ponds then
the costs of that month should not be regarded as ongoing
operating costs for following years. As a result he
reduced the operating expenses 25% on the basis of one
month's costs out of four. This gave him $121,343 for
what he regarded as recurring operating costs, to which
he added an allowance for five days of annual start
up costs ($9,975) and an allowance for equipment depreciation
during the three month mining period ($36,265). He converted
this total mining cost of $167,583 into a unit cost
of $3.50 per cubic metre of bank or in ground volume
mined, assuming that all ongoing mining would be on
the basis of 710 cubic metres of mining material per
day (657 cubic metres bank or in ground volume), the
high rate achieved in the final week of mining. He did
not think that any allowance was necessary for any extra
operating expenses to maintain this high rate of mining
for 124 sluicing days. He calculated the mining costs
for each season by applying his relatively low unit
cost assumption to the estimated volumes to be mined
each year with a 2% annual increase in the costs for
inflation.
3.2.4 Discount Rate and Taxes
[60] Both Clarkson and Symes then discounted
the net cash flows to 1993 at a discount rate of 15%.
They explained this choice of discount factor somewhat
differently. Clarkson expressed the rate in one report
as being "8.5% plus a 6.5% risk factor", and
in another as "10% plus a 5% risk factor".
Symes preferred to say it was a matter of valuer's judgement,
based on a variety of positive and negative factors
that he identified, but did not attempt to quantify.
[61] Symes provided the combined income and mining
tax rate of 34%. Both Clarkson and Symes deducted 34%
for taxes from the present value for each year.
3.2.5 Estimates of Market Value for each
Claimant
[62] Clarkson and Symes produced fairly similar
valuations by the DCF approach. After corrections made
during the hearing, Symes proposed approximately $2,150,000,
with a range of $100,000 either way, and Clarkson proposed
just over $2,000,000. Both Symes and Clarkson gave the
opinion that a purchaser would pay these sums for the
right to acquire this income stream at the end of 1993.
[63] Clarkson allocated the total value among
the three claimants by allocating the amount of mineable
material and the associated mining costs on each claimant's
interest in the relevant lease. The appropriate royalties
are also attributed to Eckervogt. The income flow from
each claimant's leasehold interest is discounted to
the present value and reduced for taxes. This resulted
in an approximate allocation of present value as follows:
| Eckervogt |
|
$ 732,000 (36%) |
| TD |
|
$ 711,000 (35%) |
| Yates |
|
$ 589,000 (29%) |
| Total |
|
$2,032,000 |
Symes allocated the values similarly except that, instead
of assuming all three interests were mined simultaneously,
he assumed TD's interest was mined first, followed by
Eckervogt's interest, and then Yates'. As a result of
this assumption, discounting had an effect on the allocation
of value as follows:
| Eckervogt |
|
$ 669,000 (31%) |
| TD |
|
$ 891,000 (42%) |
| Yates |
|
$ 586,000 (27%) |
| Total |
|
$2,146,000 |
3.3 Crown's case
[64] Valuation evidence for the Crown was provided
by Ellen Hodos and James Hodos, both of Onstream Resource
Managers, Inc. ("ORM") located in Carson City,
Nevada. Ellen Hodos is a geologist and mining engineer,
specializing in placer mines. In addition she has training
and experience in mining appraisal, including placer
mines. She contributed most of the technical opinion
in the ORM report. James Hodos is also a geologist,
with training and experience in mining appraisal. He
was responsible for the collection and analysis of some
comparable sales data used in the report. ORM has done
a number of placer evaluations in Alaska for the National
Parks Service. Richard Crosson, an accountant and business
valuer, of Blair Crosson Voyer in Vancouver, provided
rebuttal evidence with respect to the DCF analysis advanced
by the claimants.
[65] ORM provided some background information
on the gold market and its inter-relation with gold
mining. Gold is bought for both investment and industrial
purposes. The price of gold is volatile, influenced
by a large number of factors, including various investment
factors such as the rate of inflation, interest rates,
the strength of various currencies in relation to the
US dollar, central bank sales, as well as such factors
as mining costs (and the events that affect these in
various parts of the world), and industrial demand.
The timing of the fluctuations in the gold price cannot
be predicted and thus anticipating gold prices creates
a significant risk for gold miners. There is a general
correlation between the price of gold and the number
of placer mines held. The number of claims in British
Columbia declined between 1990 and 1993 with the decrease
in price of gold to $415 an ounce in 1991 and 1992,
the lowest price in the period between 1986 and 1993.
If gold prices fall below production costs, placer miners
stop mining, or operate on a reduced scale.
[66] Ellen Hodos considered a number of approaches
to market value for the placer leases. The cost approach
to value is not applicable as there is no mine plant
to which it could be applied. In her opinion, the DCF
approach or mine valuation approach, attempting to value
future mine production, is not appropriate in this case
because there are too many unknowns, including unknown
reserves, to make a reasonably accurate forecast of
income.
3.3.1 Income Approach
[67] The Hodos attempted to value Heinz Eckervogt's
interest in the leases with respect to his anticipated
income stream from royalty. The income stream from royalty
is somewhat less volatile than an income stream from
mining since it is paid off the top whether the miner
makes a profit or not.
[68] The Hodos used two sets of assumptions.
First (Case I) they used the assumptions for volume
to be mined, grade, and price for gold that Clarkson
had used in his first report in 1995, based on TD's
experience. Secondly (Case II), they made the significantly
more conservative assumption that the leases had only
one more season of economic production, and that a similar
volume and grade would have been achieved in that season
as in 1993.
Case I
[69] The Hodos started with Clarkson's estimate
of volume of mineable material in his first report in
1995: 181,200 cubic metres. This was, of course, much
lower than Clarkson's current estimate of volume of
over 504,000 cubic metres. Using the grade that Clarkson
reported in his 1995 report as to what TD had in fact
obtained, a total production of 5,673.46 ounces of gold
was estimated over the next five years. Assuming Clarkson's
average gold price of $500 per ounce and an average
royalty to the owner (from 1993 experience) of 11.62%,
Ellen Hodos calculated the annual value of the royalty
to the owner Eckervogt from TD at $65,926 per year.
[70] The Hodos then calculated the net present
value of Eckervogt's royalty income using their own
customized Income Approach. This involved discounting
the calculated royalty by 15% as well as assigning a
declining probability to the income stream for each
of the five years, reflecting the view that mining might
stop any year. This calculation produced a net present
value of the royalty income to Eckervogt of $144,905.
[71] The Hodos then used the same assumptions
and valued Eckervogt's interest in the royalty income
by an income capitalization method that they said was
found in the industry. Buyers of placer mines expect
to recover the price within three years and will thus
pay an amount based on a capitalization rate on net
royalty income of one third or 33.3%. This yielded an
estimate of market value of the royalty income to Eckervogt
of $197,798.
[72] The Hodos used the same assumptions and
valued Eckervogt's interest as a percentage of the gross
income from the estimated gold production by another
method called the "Schmidt" valuation: an
approach that was described to them by Stuart Schmidt,
a Yukon miner with long experience in trading leases.
Schmidt reported valuing leases at between 3 and 5%
of the total estimated recoverable gold. Using the mid-point
of 4% and assuming the same gold price of $500 an ounce,
this yielded an estimate of market value to the owner
based on the income from the estimated gold production
of $113,469.
Case II.
[73] The second set of assumptions was based
on one more production year on the leases. The amount
of mineable material was assumed to be 25,000 cubic
yards (19,114 cubic metres) which is somewhat less than
what TD reported that he mined in 1993, at 30,050 cubic
yards (measured by bucket count). The same grade was
used as in Case I and the gold price was now assumed
to be $483.61 per ounce, which is what it was on October
15, 1993. These assumptions yielded a gold recovery
of 581 ounces, worth $280,977. The value of the royalty
to the owner Eckervogt, assuming the same average royalty
of 11.62% as was achieved in 1993, would be $32,650.
[74] The Hodos then calculated the net present
value of this royalty income, this time using a discount
rate of 30% and a probability factor of 50%, again reflecting
the view that mining might not occur. This produced
a present value of the royalty income to Eckervogt of
$12,554.
[75] The Hodos applied the Schmidt method to
these new factual assumptions and obtained a market
value to Eckervogt based on the income from the estimated
gold production of $11,239. The income capitalization
method was not used, apparently because only one year
of mining was anticipated in this model.
3.3.2 Direct Comparison Approach
[76] The Hodos also examined a number of transfers
of placer leases, including the subject leases, and
used the Direct Comparison Approach to estimate the
value of the three leases owned by Eckervogt. The Lower
Lease had been sold in 1978 for $2,500. In 1987 it had
been sold to the claimant Eckervogt for $30,000. The
Middle Lease had been sold to the claimant Eckervogt
in 1980 for $32,000.
[77] James Hodos provided details of nine other
sales of placer mines in the Cariboo area of British
Columbia between 1991 and 1993. These ranged from $250
to $70,000, with these two prices at either end of the
range being for a half interest in a placer claim. He
chose four lease sales that he thought were most similar
to the subject leases. The sale prices for these four
leases ranged from $2,500 to $6,895 for one placer lease,
with what he regarded as the most similar lease, selling
for $5,000. After consideration of these four sales
he concluded a value of $4,500 per lease or $13,500
for the three placer leases.
[78] The Hodos also estimated a market value
from Alaskan sales information. The sale prices of Alaskan
properties were provided in summary form per acre and
per ounce of anecdotal or proven reserve gold. The average
sale price derived from 11 sales in 1992-1993 was $US115,000
for a generally larger lease than the subject leases.
Since the size of the subject leases was somewhat uncertain
and there was only information on the average size of
the Alaskan sales, the Hodos used the average price
of $US1.59 per anecdotal ounce of gold recorded for
11 sales in 1992 - 1993, averaging 457 acres per sale.
This price was some 50% lower than what had been reported
for 11 sales in 1990 - 1991. Converting this price to
Canadian dollars as of October 15, 1993, a market value
for the three placer leases of $11,965 was derived,
assuming the 5,673.46 ounces of gold in the Case I situation
described above, or $1,125, assuming the 581 ounces
of gold in the Case II situation.
3.3.3 Critique of the Claimants' DCF Approach
[79] The Crown did not favour the DCF approach
and introduced expert evidence from Richard Crosson,
an accountant and business valuer, to rebut the claimants'
evidence advanced by Clarkson and Symes. Crosson questioned
the use of the DCF approach as a means of measuring
the market value of the subject leases on two main bases:
| i |
the DCF approach is only a valid measure of
market value where it is an approach that is
used by real buyers in a real market. Clarkson
and Symes did not provide any evidence that
this was the case. |
| ii |
the DCF approach can only be used where the
risk attached to the projected cash flow is
measurable. Crosson casts doubt on a number
of the assumptions made by Clarkson and Symes
in their DCF analyses and as a result says the
assumptions are subject to significant estimation
error. There are also a number of mistakes in
their analyses, all of them increasing the claimants'
final valuation. |
Those assumptions which Crosson questioned are set
out below. Not being himself a mining engineer or geologist,
Crosson did not attempt his own estimate of the volume
or grades of mineable material.
[80] Crosson noted that Clarkson's original calculation
of grade in his 1999 report contained an error in the
average fineness factor obtained from the Englehard
refinery receipts, which when corrected reduced the
grade obtained by TD. Clarkson acknowledged this error
and the grade advanced by him at the hearing contained
this correction.
[81] Crosson criticized the use, by both Symes
and Clarkson, of gold future contract prices. He described
this as being wrong in principle, in that gold future
prices at any date are not predictions of the price
of gold at future dates, but rather reflect the investment
interest rates over the time period of the contract
or the time value of money. Thus, the use of future
contract prices will improperly inflate the apparent
value of the income flow. In Crosson's opinion the appropriate
gold prices to use in a DCF calculation are the current
spot market or cash values at the valuation date of
October 15, 1993.
[82] Crosson felt that Clarkson was too optimistic
using an assumption of 124 sluicing days per year and
a daily volume of 710 cubic metres of gravel processed,
for a total of 88,000 cubic metres (loose volume) per
year. Crosson thought that an analysis of TD's time
sheets only justified an assumption of 95 sluicing days
per year out of a total of 106 operating days. He pointed
out that while Clarkson had measured mineable volumes
and gold recoveries on bank or in ground volume, he
measured daily production on loose volume. This means
that the daily production volume of 710 cubic metres
was overstated by approximately 8%. He also considered
that it was more representative for mining rates to
be based on an average rate for the season, rather than
solely on the final seven days, especially when those
days resulted in a low recovery grade of gold. This
resulted in a figure of 339 cubic metres (bank or in
ground volume) per sluicing day, for a total of 32,000
cubic metres (bank or in ground volume) per year. Crosson
noted that these were reasonable estimates for TD to
achieve, based on its 1993 experience, but would not
necessarily be rates that Yates or Eckervogt or a prospective
purchaser might have been able to achieve.
[83] In Crosson's opinion the analysis of unit
operating costs as presented by Clarkson (and adopted
by Symes) was flawed. He disagreed with the reduction
of the operating costs by 25% on the basis that all
of the costs incurred in June were "one-time"
costs. The time sheets for June recorded activities
such as stripping, road-work, and settling ponds some
of which would recur with respect to further mining
on the other leases in future years. In addition the
costs included nothing for the labour of Douglas and
Carol Busat when the time sheets indicated that they
had worked on site for 109 and 98 days respectively.
Crosson also thought that it was unreasonable to expect
operating costs (that were largely labour and machine
operating costs) to remain fixed, while the volumes
increased substantially. He had also noted that the
unit costs were calculated on the basis of the 710 cubic
metres of loose volume per day rather than on bank or
in ground volume, a point that Clarkson conceded. Crosson
calculated what was, in his opinion, a more reasonable
unit operating cost by taking the midway point between
the operating costs for a low range based on three months
and for a high range based on four months. He added
the costs of Douglas Busat and Carol Busat at $400 and
$200 per day respectively for the appropriate number
of days to the operating costs for three months or for
four months and then divided by the appropriate volume
of material mined in each period. This resulted in a
figure of $8.85 per cubic metre excluding all consideration
of capital costs, start up costs, exploration costs
and mobilization costs.
[84] Crosson observed that Clarkson had incorrectly
included an allowance for capital depreciation in the
DCF analysis. Both Clarkson and Symes had also ignored
the up front capital costs of $647,000 for equipment,
presumably in part because of the implicit assumption
that TD would continue to do the mining. He agreed with
Symes that the allowance for capital depreciation could
be treated as a sustaining capital reinvestment; but
if this was done it should be treated as a somewhat
higher annual cost rather than as part of the unit mining
cost.
[85] Crosson reserved some of his strongest criticism
for Clarkson's and Symes' choice of a 15% discount rate.
He observed that there was no attempt by either witness
to demonstrate any market evidence for this percentage.
Neither was there any analysis to support a built up
rate consisting of a risk free rate for the time value
of money (for the fact that the income stream would
be received in the future) and a risk premium based
on an assessment of the risk inherent in the projected
cash flow. While Symes listed a number of positive and
negative factors that he considered in arriving at his
opinion that a 15% discount rate was appropriate, Crosson
undermined a number of the alleged positive factors.
In Crosson's opinion the prospective cash flows in the
situation envisaged by the claimants had to be treated
as speculative, in which case discount rates considerably
higher than 15% would apply. He went further and said
that, in his opinion, the risk in these cash flows was
not determinable with sufficient certainty to develop
any useful discount rate. Under such circumstances,
one should not use the DCF approach at all.
[86] Finally, Crosson criticized the way that
Clarkson and Symes proposed to allocate the resulting
value between the three claimants. He pointed out that
the analyses treat the three leases as if they were
under a single operator, TD, with costs based on the
use of TD's equipment and Busat's experience. Neither
Yates nor Eckervogt are assumed to have any costs in
exploration, start-up costs, or equipment to mine their
share of the leases. This, he argues, necessarily results
in those interests being overstated.
- Alternative DCF valuation
[87] On instructions from counsel, Crosson then
presented what he called a "sensitivity" calculation,
in which he used the same DCF model as the claimants,
but inserted more pessimistic input assumptions for
a few items such as annual volume mined and mining costs
which he felt were better justified by the evidence.
He maintained most of the other assumptions used by
Clarkson including the total volume of mineable material,
gold grade and even the 15% discount rate. Crosson also
used the same model and showed the effect on the valuation
by varying the discount rate and/or the amount of material
to be mined per season.
3.3.4 Estimate of Market Value for each
of the Claimants
[88] There was a range of value by the Income
Approach of $113,469 to $197,798 under the assumptions
for Case I, and $11,239 to $12,554 under the assumptions
for Case II. Using the Direct Comparison Approach, the
four closest transactions provided a value of $4,500
for each lease or $13,500 for the three leases. Prior
sales of the subject suggested a maximum market value
of $96,000 for the three leases. Alaskan sales of placer
leases suggested $11,965 based on 5,673.46 ounces of
gold in Case I and $1,125 based on 581 ounces of gold
in Case II.
[89] The Hodos rejected the high values obtained
using the Income Approach based on the assumptions in
Case I on the basis that there was no market support
for this range of values. In their survey of nine transfers
of British Columbia placer leases, the highest price
paid was $70,000 per lease, where exploration supported
significant quantities of gold. The subject leases had
not been similarly explored and, in their opinion, the
market heavily discounts speculative projections of
gold. Relying solely on the Direct Comparison Approach,
they concluded a market value for Eckervogt's interest
in the three leases as $13,500, a figure which was supported
by the Income Approach based on the more pessimistic
assumptions in Case II.
[90] The Hodos stated that TD's interest as lessee
of part of the Middle Lease and the Upper Lease had
no market value. The contract rent averaged 11.5% royalty
in 1993. In the Hodos opinion, the market rent for the
right to mine was 10% royalty based on a survey of British
Columbia and Yukon lease holders, operators, and publicly
traded companies. If the contract rent was greater than
market rent, then the lessee's interest in the agreement
to mine had no market value. In any event, TD's financial
statements and income tax returns for 1993 show that
no profit was made. Although the Hodos did not value
Yates' interest, the Crown took the position that for
the same reasons Yates interest as lessee of the Lower
Lease had no market value.
3.4 Discussion
3.4.1 Interests to be Valued
[91] Sections 31 and 32 of the Act require us
to value interests in land as follows:
31 (1) The board must award as compensation
to an owner the market value of the owner's estate
or interest in the expropriated land plus reasonable
damages for disturbance …
…
(3) If there is more than one separate interest
in the land expropriated, the value of each interest
must, if practical, be established separately.
32 The market value of an estate or interest
in land is the amount that would have been paid
for it if it had been sold at the date of expropriation
in the open market by a willing seller to a willing
buyer.
[92] The first question to be addressed in this
valuation is the claimants' interests that are to be
valued. The Act requires us to attempt to value the
three claimant's legal interests in the subject leases
separately. Eckervogt is the owner of the placer leases,
subject to their expiry in 1998 and 2002. However, but
for the expropriation, we assume Eckervogt's interest,
or any purchaser of one or more of those interests,
would have been successful in applying for the continued
extension of the lease(s) as had been done in the past.
Eckervogt had an unencumbered right to the upper portion
of the Middle Lease. He also had the right to receive
royalties under the two agreements to mine he had signed
with Yates and TD as long as Yates and TD continued
to mine. Yates and TD's interests were only through
their respective agreements to mine, for five years
and three years respectively, with options to renew
for a further three years in each case. These legal
interests must be valued under section 32 on the basis
of what a willing and prudent purchaser and seller of
the interest would agree on as a transfer price. While
Eckervogt did own all three placer leases and might
sell his interest in the three leases collectively or
separately, the two agreements to mine were with different
claimants and were for separate leases and should not
be treated collectively. We agree with the Crown that,
given these circumstances, the claimants' implied assumption
in the DCF approach that the three leases would all
be mined by the same miner is inappropriate.
3.4.2 DCF approach
3.4.2.1 Legal Authorities
[93] The claimants referred us to two British
Columbia cases where the DCF approach to valuation had
been upheld by the courts. In Shell Canada Resources
Ltd. v. British Columbia (Assessor of Area No. 22 East
Kootenay) (1987), 21 B.C.L.R. (2d) 22 (B.C.S.C.)
Spencer J. stated that the DCF approach is an acceptable
way of valuing an industrial undertaking such as the
subject coal mining operation where there was appropriate
evidence. However, we note that Spencer J. went on to
hold that since the requisite information to apply this
approach was not available to the assessor (or the hypothetical
purchaser) at the valuation date, the DCF approach could
not, as a matter of law, be used as the valuation method
in that case. In Re MacMillan Bloedel Ltd. and the
Queen in Right of British Columbia (1995), 56 L.C.R.
81 (B.C.C.A.) the Court of Appeal upheld the arbitration
board's decision to value the timber licenses that had
been expropriated by the DCF method. In that case both
valuators had valued the timber licenses on the DCF
approach. What was being valued was the income that
would be derived from the harvesting of the timber on
the expropriated license. In our opinion, the valuation
of an income stream from harvesting timber is a very
different exercise than the one presented for this placer
gold mining operation, because there is so much more
certainty in the evidence on such factors as the amount
of the resource, the rate of harvesting, and the costs
of harvesting.
[94] The use of the DCF approach to valuation
of properties with mineral resources has been thoroughly
canvassed in two decisions of this board: Casamiro
Resource Corp v British Columbia (1993), 50 L.C.R.
99; affd 70 L.C.R. 81 (B.C.C.A.) and Premanco Industries
Ltd. v. British Columbia (Ministry of Environment, Lands
and Parks) (2000), 71 L.C.R. 6; leave to appeal
to B.C.C.A. refused, (2001), 72 L.C.R. 1 (B.C.C.A.).
We adopt the analyses in these two cases as to the requirements
for the appropriate use of the DCF approach and provide
only a brief summary of the relevant principles. As
stated in the board decision in Casamiro, the
DCF approach is grounded on there being proven or probable
mineral reserves. While there are a number of factors
that feed into the DCF approach for which there must
be some level of certainty, the amount of known mineral
resource is the starting point. Casamiro also
referred to comments on the volatility in market value
in the DCF approach as a result of relatively minor
variations in assumptions for such items as mineral
price, mining costs, or discount rates. This board's
decision to reject the DCF approach in Casamiro
on the grounds that the evidence on mineral resources
was too speculative was upheld by the Court of Appeal
since argument in the present case concluded.
[95] Similarly, in Premanco this board
followed Casamiro and decided that the DCF approach
was not suitable for valuing the mineral resource in
that case. Again the primary problem was a lack of established
mineral reserves. In addition, a number of authorities
were cited that discussed the problem of volatility
in the DCF approach. In Sequoia Springs West Development
Corp. v. British Columbia (Minister of Transportation
and Highways) (2000), 69 L.C.R. 1 (B.C.E.C.B.),
for example, this board commented at para 53 that because
of the volatility inherent in the discounting method
in the Development Approach, a methodology in the appraisal
of land that is similar to the DCF approach, "the
Direct Comparison Approach is to be preferred except
where there is insufficient evidence to support a comparative
approach". The board in Premanco went on
to note that the volatility associated with the DCF
Approach was magnified in an arbitration setting such
as this, where the constraints provided by the real
market place are lacking. In such situations, valuers
have a natural tendency to put forward opinions undependably
high or undependably low. See the reference to Clinker
& Ash v. Southern Gas Board (1967), Digest of
Cases 533, (English Lands Tribunal). As indicated above
the Court of Appeal has refused leave to appeal the
board's decision in Premanco, one of the grounds
for appeal being the board's rejection of the DCF approach.
[96] The claimants in this case sought to distinguish
their case from Casamiro on the basis that at
the time of expropriation TD was engaged in an operating
mine with recorded gold production and mining costs.
It is true that TD was operating a placer mining operation
on the Middle Lease in 1993 that recovered 26 kilograms
(about 837 ounces) of gold. We accept that, but for
the expropriation, TD would in all probability have
returned to continue mining on the Middle and Upper
Lease for some further period. TD's time sheets do provide
some basis for estimating assumptions such as the mining
costs used in the DCF approach. In this respect, the
subject leases present a somewhat different factual
situation than that in Casamiro and Premanco
where there was no operating mine in effect at the date
of the expropriation.
[97] However, despite TD's mining operation,
there continues to be considerable uncertainty with
respect to the income stream that might be generated
from any of the leases. As indicated in Shell Canada
Resources, the DCF approach can only be used where
there is appropriate evidence available to the hypothetical
purchaser on the valuation date. Casamiro and
Premanco make clear that the amount of established
mineral reserve is a key evidentiary requirement for
use of the DCF approach. In addition, the DCF approach
can only be justified if it is an approach that is used
in the market place as set out in section 32; the valuation
must be one that a hypothetical willing purchaser and
vendor of the interest would agree to pay.
3.4.2.2 Estimate of Amount of Gold
[98] All of the miners and experts agreed that
placer mining was inherently variable with patches where
little or no gold was found and others where the gold
recovery was high. TD's records of gold recovery for
1993 showed variable grades of gold at different times,
and Busat attributed this to hot spots and cold spots
in the gravels he was mining. Because of this variability,
testing in one area is not necessarily indicative of
grades to be found elsewhere on the leases. As we indicated
above, placer mining is different from hard rock mining
in this respect.
[99] In placer mining, the amount of gold is
estimated from the grade of gold and the volumes of
mineable material. In this case the only actual testing
we have is TD's six test holes done on the Middle Lease
in May/June 1993. These tests showed a variation between
$7.50 and $18.00 per cubic yard that Clarkson translated
into grades that fell between 0.61 and 1.47 grams per
cubic metre, with the lowest grade of 0.61 being for
the test on the North Fork. The average grade was 0.95
grams per cubic metre. TD presumably used the tests
when it decided where to mine in 1993 and although it
is not clear exactly where TD did mine, it would appear
that the locations around at least three of those test
holes have now been mined over.
[100] The only other evidence of gold grade that
we have is from TD's mining experience on the Middle
Lease in 1993. Clarkson's revised estimate of TD's average
grade based on the amount of gold recovered from the
volume of gravel as measured by bucket counts recorded
on TD's time sheets, adjusted for bank or in ground
volume and boulders as set out above, was 1.02 grams
per cubic metre. However, there was considerable controversy
in the evidence as to whether the total volume of gravel
mined by TD to recover the agreed amount of gold was
in fact much larger. If the volume of gravel in place
was actually larger than Clarkson assumed, as some of
the evidence suggests, then the average grade of gold
estimated by Clarkson would be lower.
[101] While the bucket counts recorded a total
of 22,975 cubic metres of loose material (21,273 cubic
metres of bank or in ground volume) that were sluiced,
TD completed a Notice of Completion of Work, filed with
the Ministry of Energy, Mines and Petroleum Resources
on October 26, 1993, shortly after quitting the subject
leases, indicating more than twice this, at 50,000 cubic
metres of material, were mined. After reclamation, both
the claimant's witness, Clarkson, and the Crown's witness,
Levson, visited the site separately and relied on Martin
Eckervogt and Douglas Busat, respectively, to point
out to them the area of mining in 1993. Clarkson's measurements
resulted in a strip approximately 200 metres long while
Levson measured a strip approximately 330 metres long.
Both agreed to a width of about 39 metres and a depth
somewhat over 3 metres. The volume of in place gravels
that were mined as calculated by Clarkson was 22,700
cubic metres (after subtracting a volume for the stream
bed), while Levson's volume was twice as much, at 45,000
cubic metres. (In fact, using Clarkson's stated measurements
we calculate the in place volume to be 25,700 cubic
metres minus 2,000 cubic metres for the stream channel
or 23,700 cubic metres).
[102] The testimony of Martin Eckervogt and Douglas
Busat as to their recollections of where the mining
had occurred, tends to support a volume of approximately
30,000 cubic metres. Martin Eckervogt stated that the
excavations started below the lower cabin, in an area
where the two roads intersected. The first cut ended
at a point near the upper cabin, perhaps a little upstream.
The second cut started about 20 metres further upstream
and continued past the upper cabin to close to the confluence
with the North Fork. Douglas Busat said that the first
cut started downstream from the lower cabin near where
an area of bedrock was exposed and ended near the upper
cabin. The second cut started upstream from the first
and continued approximately 91 metres (300 feet) past
the upper cabin. On her site visit, the Crown's witness,
Ellen Hodos, measured the distance from the lower cabin
to the upper cabin as 145 metres and the distance from
the upper cabin to the confluence with the North Fork
as 105 metres. Assuming the mining started some 50 metres
downstream of the lower cabin, using the evidence of
these three witnesses, the two swathes appear to average
about 210 metres in length. Assuming the width was 39
metres and the average depth was 12 feet or 3.7 metres,
as reported by Busat and Martin Eckervogt, an approximate
volume of mined material is about 30,000 cubic metres.
Again, TD filed a Notice of Completion of Work in October
1993 saying that the area mined (not including testing,
settling ponds, or the campsite) was 11,000 square metres.
At an average depth of 12 feet or 3.7 metres this calculates
into a volume mined of 40,700 cubic metres.
[103] Although Busat stated that, in his view,
the most accurate measure of volume mined was bucket
count, we heard evidence from the Crown's witness Levson
that miners are commonly imprecise about bucket counts.
Even if TD's operators were methodical in recording
the bucket counts, bucket loads are in practice very
variable in size, and they necessarily have to exclude
all boulders that are too large for the machinery, a
fact that may not be accurately reflected in Clarkson's
10% allowance for boulders.
[104] Reviewing all of this evidence suggests
to the board that Clarkson's volume estimate of the
in place gravels that were mined in 1993 at 21,273 cubic
metres based on adjusted bucket count was likely too
low. There is evidence from Levson, Busat, and Eckervogt
that supports volumes that are higher than this. This
volume was the basis for Clarkson's estimate of the
grade of 1.02 grams per cubic metre and therefore, in
our opinion, the actual grade achieved by TD in 1993
was probably lower.
- Volumes of mineable material
[105] Clarkson ascribed his estimate of TD's
grade of 1.02 grams per cubic metre to all areas of
the leases that he assumed were unmined, approximately
48% of the total estimated volume of mineable material.
He then used 0.57 grams per cubic metre, the grade reported
by the miner, Daniel Johnson, on the two leases below
the subject leases in 1988 and 1989, for all the areas
that Clarkson assumed were tailings, approximately 52%
of the total estimated volume. As set out above, the
volumes of mineable material in the different areas
estimated and described by Clarkson had been reduced
by a probability factor, with the greater reduction
for those areas further up the hillside where there
had been no testing or mining to date. However, this
was a factor to adjust for overestimates of volume rather
than grades. These two grades, one derived from TD and
one from Johnson, were applied to large volumes of material
estimated by Clarkson from his field work. Some of these
areas of mineable material that were assigned a grade
of 1.02 grams per cubic metre included areas that had
traditionally never been mined in Squaw Creek: benches
and limits of the channel some 15 or 20 metres up the
hillside from the valley bottom. This grade of 1.02
grams per cubic metre was also applied to areas of the
Upper Lease on the North Fork, both above and below
the falls, where mining conditions were reported to
be relatively difficult.
[106] Thus the total of 394 kilograms of gold
that Clarkson estimated would be recovered has been
estimated from the application of two grades, one from
an area of the valley floor in the Middle Lease already
mined by TD and one from the two leases downstream of
the subject leases. There is virtually no testing providing
any basis for this uniform application of the two grades
to the large estimations of mineable material, although
everyone agrees that placer mining is very variable.
We note that this total gold recovery of 394 kilograms
has more than doubled from a total of 176 kilograms
that Clarkson estimated in his first report in 1995.
This significant increase in the amount of projected
gold was justified by Clarkson on his more detailed
mapping of the site in 1998 with the resulting increase
in volume of mineable material from 181,247 to 504,156
cubic metres, an increase that is close to three times.
The claimants submitted that if they had been allowed
to carry out testing on the subject leases after the
expropriation they could have been more certain in their
projections of mineable gold. Any uncertainty in the
projections for the amount of gold, they argued, should
be interpreted to the benefit of the claimants since
the Crown had denied them the opportunity to do any
further testing.
[107] However, under section 32 of the Act we
must estimate the market value that would have been
paid by a purchaser, not the potential gold that might
have been mined. A purchaser in October 1993 would not
have had the benefit of Clarkson's information. A purchaser
of one or more of the leases may have done some testing
on the site, as Busat did. While testing of the subject
leases was precluded after expropriation for a park,
it is unlikely, in our view, that a prospective purchaser
would have carried out much more extensive testing than
the type of testing already done by TD on the Middle
Lease. There was considerable evidence at the hearing
about how thorough and business-like Busat and TD were
in their testing and mining on the Middle Lease. It
is very unlikely that a prospective purchaser would
have hired a mining engineer or a geologist to do five
or six days of field work on the site to prepare detailed
mapping. The prudent purchaser would have bought one
or more of the leases on the basis of information ascertainable
at the time; namely, the gold mining history as recorded
in the Gold Commissioners office and government reports,
any information that could be obtained from Eckervogt
and/or TD and Yates, together with any further testing
carried out by the purchaser, similar to what TD had
done in early 1993. We also note that since argument
in this case concluded, the Court of Appeal in Casamiro
and this board in Premanco have rejected claims
for an adverse inference on the Crown's refusal to allow
further testing.
[108] Given the considerable uncertainty in the
evidence on both the grade obtained by TD and on the
volume of mineable material, together with the inherent
variability of placer mining, the evidence is far short
of showing established reserves of gold on the subject
leases in 1993.
3.4.2.3 Use in the Market Place
[109] The evidence established that prices paid
for placer leases in Squaw Creek and in the Cariboo
appeared to range between zero or a relatively nominal
$250 and $140,000. Many of the prices were under $50,000.
Between 1990 and 1993 the statistical information on
the sale of Alaska placer mines indicated an average
sale price between $US70,000 and $US115,000 ($C92,800
and $C152,500). The board recognizes that placer mines
are variable and that each turns on its own characteristics,
such as accessibility, mining history, both on the lease
and more generally in the surrounding area, and what
gold testing on the site might reveal. However, in our
opinion, these prices, some of them for leases on Squaw
Creek, including the subject leases, indicate that actual
buyers in the market place are prepared to pay only
relatively modest amounts for placer leases. We can
only conclude that buyers of placer leases place little
or no faith in DCF projections such as those made by
the claimants.
3.4.2.4 Volatility
[110] In any event, we note Crosson's demonstration
of volatility in the DCF approach. Crosson used the
same DCF model as Clarkson and for this exercise used
Clarkson's total estimate of the amount of mineral resource
by using Clarkson's estimates on the volume of mineable
material and the grade of gold. He also used Clarkson's
discount rate. However, Crosson changed the assumptions
on the amount of material that would be mined each season
and an aspect of the mining costs, to amounts that he
felt were better justified by the evidence as set out
in section 3.3.3 above. He also factored in Clarkson's
estimate of the value of TD's equipment. Changes on
these factors alone, even at the low discount rate of
15%, caused a change in the market valuation from over
$2,000,000 to a negative value of minus $405,000,
before tax. Crosson used the same model and showed the
effect on the present market valuation of changes in
the discount rate and/or the amount of material that
would be mined per season. A single change in the discount
rate from 15% to 20% assuming that the amount mined
per season was 88,000 cubic metres, as claimed by the
claimants, caused the pretax present valuation to fall
from $403,000 to $259,000 or 36%. A change only in the
amount mined per season from 88,000 cubic metres as
claimed by the claimants to 80,000 cubic metres, keeping
the discount rate of 15%, resulted in a drop in the
pretax present valuation from $403,000 to $302,000 or
25%. These significant changes in value by the substitution
of a small change in a single factor or in a few factors
makes obvious the unreliability of the DCF approach.
3.4.2.5 Conclusion on DCF Approach
[111] Although there was a gold placer mining
operation in place on the Middle Lease in 1993, there
was no established reserve on the rest of the subject
leases in 1993 from which a stream of income was reasonably
predictable. In any event, we agree with the Crown that
the DCF approach is not one that appears to be used
by actual buyers of placer leases in the market place.
It is also an approach that Crosson has demonstrated
to be very vulnerable to major oscillations in the final
value by relatively small changes in a few factors.
As a result, we conclude that the DCF approach is inappropriate
for the valuation of these placer leases. We are further
supported in this conclusion by a detailed analysis
of a number of the other assumptions and estimates which
underlie the claimants' use of the DCF approach as set
out below.
3.4.2.6 Other Assumptions and Estimates
in the DCF Approach
[112] We find the Crown's evidence on gold price
for the seven years following expropriation persuasive.
Gold future contract prices reflect the time value of
money and therefore will tend to overstate the price
that gold is actually expected to fetch at the specified
date in the future. As a result, we agree that the gold
future contract price should not have been used in the
calculation.
[113] In a DCF calculation, the rate of production
of income is an important assumption, as a longer mining
period will reduce the present value, potentially to
uneconomic levels. Crosson demonstrated this in his
sensitivity calculation, when substitution of Clarkson's
mining rate to one that Crosson thought was more reasonable
given the evidence (as well as changes in mining costs)
produced a negative present value.
[114] Clarkson's assumption was that a daily
volume of 710 cubic metres of gravel would be mined
on 124 sluicing days each season, even though TD had
averaged only 366 cubic metres per day in 72 sluicing
days in 1993. Clarkson's assumptions resulted in an
annual mining rate of 88,000 cubic metres of gravel,
an increase close to three times the annual volume estimated
in his 1995 report of 32,200 cubic metres. Crosson correctly
pointed out that the mining rate should be expressed
in bank or in ground volume rather than loose volume.
[115] We agree with Crosson that an analysis
of the work detailed on the time sheets suggests that
time was spent on non-operating activities such as hauling
in equipment and repairing the road and on operating
activities such as building settling ponds and stripping
the ground, as well as actual sluicing of gravels. Although
the amount of non-operating start-up work for TD would
be less in succeeding years, a number of activities
in the time sheets such as further road work, constructing
settling ponds, and reclamation work would continue.
Further TD took a few days off site at the end of every
month in 1993 and did not even work 124 days between
May 18 and September 30, a season that is limited by
weather conditions.
[116] We are also reluctant to accept the daily
volume of 710 cubic metres of gravel when this rate
was only achieved for the final seven days of mining
in 1993, at the same time as the gold grade dropped
dramatically. Although TD may have improved its screening
process, we also heard evidence that the presence of
large boulders on Squaw Creek slowed the rate of mining.
The conditions on the North Fork were worse in this
respect than Squaw Creek. Busat attempted to support
this high volume by suggesting that production rates
could have been improved by adding a conveyer belt or
operating double shifts. However, we note that TD did
not, in fact, purchase a conveyer belt until 1999 and
has not yet used double shifting in its new mining operations.
[117] In the end, we conclude that Clarkson's
mining rate assumptions were too optimistic.
[118] Clarkson's estimate of unit mining costs
after adjustment for bank or in ground volume was $3.50,
a decrease of 58% from the unit cost in his 1995 report
of $6.05. Crosson again was able to show how sensitive
the DCF approach was to mining costs since changes in
Clarkson's assumption (together with a change in mining
rate) produced a negative present value.
[119] Clarkson reduced TD's mining costs 25%
on the grounds that June was spent on start up costs
that would not be needed in subsequent years. As we
have already indicated a review of the time sheets shows
that some of the activities that were done in June would
continue in subsequent years. After reviewing the financial
statements we also note that over $100,000 of expenses
that were initially treated as repair and maintenance
expenses were reallocated by Clarkson to capital expenses.
There were also some general expenses that were likely
at least partly attributable to the mining operation
that were omitted. While we did not have detailed evidence
on individual expenses, in our opinion, Clarkson appears
to have minimized the operating expenses to some degree.
At the same time Clarkson made no allowance for any
increase in costs, which were primarily labour and equipment
operating costs, although he assumed that the mining
rate would more than double. In our view this is unrealistic.
Finally, we agree with Crosson that the capital cost
of the equipment estimated at $647,000 should be properly
considered, as should the labour of Carol Busat and
Douglas Busat. We note that in TD's claim for accelerated
prospecting expenses, Douglas Busat's time is charged
and yet it was omitted from the mining costs for the
DCF analysis.
[120] In our view, Clarkson's mining costs were
significantly underestimated.
[121] The board agrees with the Crown's observation
that the discount rate of 15% used by the claimants'
experts is simply unsupported by any market evidence
and that this choice appears to contribute to a significant
overvaluation of the property. Given the uncertainties
involved in the price for gold, as well as the estimates
for the grade of gold, volume of mineable material,
mining rate, and mining costs, the risks to the income
stream support a significantly higher discount rate
than 15%. Indeed, we are persuaded by Crosson's opinion
that the cash flows are so speculative that a determination
of the risk factors is uncertain enough that the DCF
approach should not be used.
[122] Thus, the board finds that none of the
factors inputted into the DCF model used by Clarkson
or Symes stands up to scrutiny. We also note that the
assumptions of mining rate and mining costs are estimated
as if TD would continue mining all three leases. As
already indicated this is an inappropriate assumption.
We are further confirmed in our conclusion that the
DCF approach should not be used to value the subject
leases.
3.4.3. Income Approach
[123] Having rejected the DCF approach, we must
value Eckervogt's interests in the leases from other
evidence that we received. Eckervogt's interests in
the leases were partly encumbered by the agreements
to mine from which he had the right to be paid royalties.
During 1993 Eckervogt received 3,025 grams of gold from
the Middle Lease which, at $484 per ounce ($15.57 per
gram) in October 1993, was worth approximately $47,100.
We accept the evidence from the Hodos that a valuation
based on royalty income was more stable than a valuation
based on a stream of income from gold production because
the royalty income is paid off first and is not affected
by the miners' costs.
[124] The Hodos used the Income Approach to value
Eckervogt's interest in the leases through his projected
income stream from royalties. They used two sets of
assumptions:
| Case I |
181,200 cubic metres (about 237,000 cubic
yards) of mineable material with a gold grade
of 0.99 grams per cubic metre (0.028 ounces
per cubic yard) mined over five years, discounted
at 15%, as well as a declining probability in
each year, yielded a value of $144,905. |
| Case II |
19,114 cubic metres (25,000 cubic yards) with
the same gold grade mined over one year discounted
at 30%, as well as a probability factor of 50%,
yielded a value of $12,554. |
[125] The Hodos concluded that the present valuation
in Case II of $12,554 supported their valuation based
on the Direct Comparison Approach. In the board's opinion,
the assumptions in Case II are overly pessimistic. The
volume mined is assumed to be 20% smaller than the volume
actually mined by TD in 1993; the other assumptions
include a discount rate of 30% as well as a 50% probability
factor that the mining would not occur. Based on the
mining agreements actually in place in October 1993,
we think that it is reasonable for a potential purchaser
to assume that TD would have returned to mine on the
Middle Lease as it had in 1993, with somewhat increased
annual volumes. We note that Busat did not do any testing
on the benches further up the hillside nor in any areas
of till in 1993 and we do not think that a reasonable
purchaser would have relied on TD mining those areas,
despite Busat's testimony to the contrary. Busat testified
that in order to finish mining "rim to rim"
on the valley floor there was room for two more cuts
or swathes with one of them being wider than the two
done in 1993. There was also the area where the settling
ponds were located. Assuming that TD had mined approximately
30,000 cubic metres in 1993, in our opinion a purchaser
of Eckervogt's interest might make a conservative estimate
that approximately two thirds of the valley bottom gravels,
or 60,000 cubic metres in the area covered by the agreement
to mine, remained to be mined. Although we have indicated
above that a purchaser would be unlikely to have the
information on volumes derived from Clarkson, we do
note that his estimate of a total of approximately 95,000
cubic metres in the valley bottom on this section of
the Middle Lease is relatively consistent with the estimate
of 60,000 cubic metres remaining to be mined. Assuming
the same average grade found by TD on its six test holes
on the Middle Lease, 0.95 grams per cubic metre, gold
recovery would be approximately 57,000 grams. Assuming
again conservatively that this volume would be mined
over two years with the same 11.62% royalty, the annual
royalty income to the owner of the leases in each of
the two years would be $51,563 at the gold price in
October 1993 of $484 per ounce ($15.57 per gram).
[126] Using the Hodos' assumptions for their
Income Approach (as described for Case I), the net present
value of the two years of royalty income to the owner
of the leases in this situation would be $76,045, rounded
to $76,000. We note that this valuation of the royalty
income includes valuation for the Upper Lease but does
not include any valuation for approximately one third
of the Middle Lease that had been excluded from the
right to mine agreement. Nor does it include any income
for the Lower Lease, since there is no basis for projecting
any royalty income from Yates. If TD's mining agreement
was not in place, there would be considerable risk to
this estimate from royalty income for parts of the Middle
and Upper Lease. We also note that this valuation depends
on an estimate of both volume to be mined and grade
for the Middle Lease, when the evidence that we (and
the prospective purchaser) have on both of these factors
is limited.
[127] The income capitalization method used by
the Hodos to value Eckervogt's interest in the royalty
income cannot be used because there are only two further
years of mining assumed.
[128] The Hodos also used the "Schmidt"
method that valued leases at a percentage of the gross
income from the estimated gold production. Using 4%
total estimated recoverable gold and assuming a gold
production of 57,000 grams as estimated above, together
with a gold price in October 1993 of $484 an ounce ($15.57
per gram), for the part of the Middle Lease covered
by the right to mine agreement we obtain a valuation
of $35,500. Since we are now valuing the gold production
rather than the royalty income from TD we can extend
this method to the unencumbered part of the Middle Lease.
One of TD's test holes in early 1993 was in this area
and the grade produced was slightly over the average
of the six test holes on the Middle Lease. Thus we have
some basis for assuming the same average grade as used
in the lower part of the Middle Lease of 0.95 grams
per cubic metre. Clarkson's map indicated that the upper
part of the Middle Lease constitutes approximately one
third of the Middle Lease. We have assumed that the
total volume of valley bottom gravels on the lower two
thirds of the lease was approximately 90,000 cubic metres.
Thus an approximate volume of valley bottom gravels
on the upper part of the Middle Lease is 45,000 cubic
metres. Again we note that although a purchaser is unlikely
to have had this information, Clarkson estimated approximately
59,000 cubic metres of valley bottom gravels on this
part of the Middle Lease. In our opinion, a purchaser's
conservative estimate for the volume of valley bottom
gravels on this part of the Middle Lease would be 50,000
cubic metres. On this basis the valuation for this portion
of the lease would be $29,823. This would give a total
value for the Middle Lease of $65,083, rounded to $65,000.
Once more we note that this valuation depends on an
estimate of both volume to be mined and grade for the
Middle Lease, and that the evidence on both of these
factors is limited. Moreover, we have difficulty in
applying this method to the Upper and Lower Lease when
we have no testing from these leases to permit us to
predict gold recovery.
3.4.4 Direct Comparison Approach
[129] The Hodos provided information about recent
sales of nine placer leases in the Cariboo region, ranging
from $250 to $70,000 for a 50% interest in a placer
lease. James Hodos explained that he had obtained approximately
120 bills of sale for leases that had sold in British
Columbia between 1991 and 1993 from the Ministry of
Energy, Mines and Petroleum Resources. However, approximately
75% of these bills of sale did not provide a sale price.
The sales of the nine placer leases were those in which
a sale price was listed and James Hodos had been successful
in locating the purchaser and/or seller by telephone
and persuading them to provide him with further details
about what was in the mind of the purchaser at the time
such as testing, access and mining history. With respect
to the four sales on which he relied, James Hodos indicated
that there had been some sampling or testing by the
purchasers prior to the sales in each case. We note,
however, that although gold was found and in some cases
gold nuggets were found, there is only one report on
one of these four leases of a reported test grade. This
one reported grade was lower than any of the grades
on the six test holes dug by Busat on the Middle Lease.
The lease that was said to be most comparable to the
subject leases showed some similar characteristics such
as a prior mining history and the presence of benches
where some gold nuggets had been found. In addition,
the purchaser's sampling had been carried out with a
small wash plant and back hoe rather than by panning.
Two of the four sales that were said to be similar had
comparable depths of gravel to portions of the subject
leases at 10 to 15 feet. Three of the leases were said
to have better access than the subject leases. However,
most of these factors are very general and are not in
our view determinative of what a potential purchaser
of a placer lease would be prepared to pay. We note
that we do not know whether these Cariboo leases were
the same size as the subject leases. In the absence
of test results it is difficult to know whether these
leases that sold between $2,500 and $6,895 are in any
way comparable to the Middle Lease.
[130] Two of the other sales were for $250 and
$500 and were eliminated by the Hodos because they did
not seem to be arms length sales. A third sale for $14,000
for two leases was also discarded because it appeared
that the presence of the cabin on the lease might be
transforming this sale into a recreational property,
rather than a mining property. James Hodos commented
that a fourth sale for $27,000 had a very high grade
of six grams per cubic yard. However, because this sale
was for a total of five leases and claims, it appears
that the price per lease is just over $5,000. Finally,
the highest priced sale at $140,000 for the whole lease
was to be paid in three installments: $18,000 each from
the two purchasers in November 1992 and $17,000 each
in November 1993 with the remaining $35,000 each still
outstanding. Thus the price of $140,000 should be discounted
to reflect the fact that payments were to be spread
over three years. In any event, this sale was not used
because James Hodos stated that it was very positive
in relation to the subject leases. This lease was reported
to contain an auriferous seam; test results were reported
at 0.3 ounces per cubic yard, which is greater than
the average grade found on the Middle Lease through
Busat's testing and mining. However, we note that there
were 40 to 70 feet of overburden to remove to access
the gravel that contained the gold.
[131] In summary, the Hodos provided us with
a range of sales of nine placer properties in the Cariboo
region from which they concluded a value for the subject
leases of $4,500 per lease. The Cariboo is a considerable
distance from Squaw Creek and we do not have any evidence
as to how placer mines in the Cariboo compare to those
on Squaw Creek. A number of the arms length sales in
the Cariboo were in the range of very approximately
$5,000 per lease but in our opinion it is difficult
to know how similar these leases are to the subject
leases. We accept that detailed information on the sales
of placer mines is more difficult to obtain than conventional
land transactions. However, in our view, it is problematic
that these nine sales were originally chosen because
they were the only ones on which information was available
rather than on their comparability with the subject
leases. The one sale that should be discounted from
$140,000 does appear to be superior to the Middle Lease.
[132] We did not find the evidence derived from
the sales of Alaskan placer leases of much assistance.
The only information was that 11 sales of placer leases
in private hands in the two-year period 1992 - 1993,
with an average size of 457 acres per sale, sold for
an overall average of $2.109 per estimated ounce of
anecdotal gold or $152,500 per sale (based on a conversion
to Canadian dollars in October 1993). We note that the
subject leases appear to be very approximately 323,600
square metres (80 acres) in size. We do not have any
other details with respect to the Alaskan leases: we
do not know where they are located, we know nothing
about their mining history or any testing that might
have been carried out, and we know nothing about the
purchasers or sellers. We do not know on what basis
the ounces of gold were estimated.
[133] Nonetheless, although there were problems
with the comparable sales in the Cariboo region of British
Columbia and with the statistical information from Alaska,
there was information about the sale prices for a number
of placer leases on Squaw Creek that came out in the
evidence. First of all there were the two sales of the
subject leases: the Middle Lease was bought by Eckervogt
in 1980 for $32,000 and the Lower Lease was bought by
Eckervogt in 1987 for $30,000. Documents showed a declared
price of $2,500 for the Lower Lease when it was bought
by Gruber in 1977. Other sales of leases on Squaw Creek
included a transfer of a lease upstream from the Middle
Lease from Art Papineau to Daniel Johnson for nominal
financial consideration in 1987. Papineau and Johnson
had been partners briefly and had mined together in
1982, Johnson's first year of mining. Papineau was an
older and more experienced miner at that time. They
staked two adjacent leases on upper Squaw Creek together,
but Papineau, who was in his mid 50's, later gave up
active mining and assigned his lease to Johnson for
what Johnson described as a moose, perhaps, and some
favours. This acquisition by Johnson from his partner
Papineau is a non-arms length transaction and should
be ignored. Johnson also testified that he was told
by Black Cliff-Menora that they had paid $90,000 or
$110,000 for the two leases immediately below the Lower
Lease in 1987. Johnson reported that the company had
based their purchase on a 1982 report by a geologist,
Joseph Wise, on testing on these placer leases on Squaw
Creek that had cautiously predicted that an economic
placer mine on Squaw Creek was feasible. Johnson reported
that the companies did not know that Terry Thompson
had been mining the two relevant leases for the six
years since Joseph Wise's report. While we did not see
any documentation on the sale of these two leases, Johnson
had no interest in these proceedings and we accept Johnson's
testimony as to his understanding of the price paid.
Yates sold another lease on Squaw Creek a short distance
downstream over the Yukon border for $US70,000 (approximately
$C92,800 at $1.326 rate in October 1993) including his
equipment from the Lower Lease in October 1993. There
was no allocation of the price between the lease and
the equipment, although the evidence suggested that
Yates attributed approximately $US20,000 to the equipment.
The purchase price was paid in three installments: $5,000
in October 1993, $30,000 in December 1993 and $35,000
in June 1994. Yates testified that he had paid $US15,000
for this lease in 1982 although it was possible that
he had made a further payment at some later date. We
note that Yukon placer leases are somewhat smaller than
the subject leases. Finally there was anecdotal evidence
from Alan Dendys, who had mined on the Lower Lease in
1987, that in the negotiations with respect to the company
that Dendys proposed joining, Heinz Eckervogt valued
the three subject leases altogether at $150,000. However,
this alleged valuation by Eckervogt was not for the
purpose of selling the leases.
[134] Given this evidence of prices paid for
leases on Squaw Creek we find the Hodos' price of $4,500
per lease based on the sale of leases in the Cariboo
too low. We recognize that gold has been removed from
the subject leases since the prices of $30,000 and $32,000
was paid in the 1980's. The price for gold was also
less in 1993 than when these prices were paid in 1980
and 1987. On the other hand, we do have evidence of
higher prices on two of the more recent sales of placer
leases on Squaw Creek in which there had also been prior
mining. It may be that the Black Cliff-Menora purchase
for the two adjacent leases in 1987 at $90,000 - $110,000
was made as a result of some misapprehension of how
much mining had occurred since the test results on which
the purchasers relied. However, the most recent placer
lease sale on Squaw Creek appears to be for $66,000,
assuming an allocation of $26,500 ($20,000 US) to the
equipment, for a somewhat smaller lease. This sale price
should be discounted somewhat to allow for the purchaser
paying in installments. There appears to be a market
for placer leases amongst individuals who are attracted
to the life style of placer mining in the north, even
if as set out by the Hodos, they sometimes underestimate
the overall capital costs of a placer mining operation.
3.5 Final Conclusion on Market Value of
Eckervogt's Interest
[135] Thus with respect to the Middle Lease we
have several estimates of value ranging from $4,500
based on the ORM report of four leases in the Cariboo
region to $76,000 for approximately two thirds of the
Middle Lease based on the royalty income from TD. We
also have an estimate of value of $65,000 based on the
"Schmidt" method (a percentage of the gross
income for estimated gold production). We note that
both the estimate based on royalty income and the estimate
based on the "Schmidt" method rely on average
grades and volumes for the Middle Lease, factors on
which we have limited information (and on which a potential
purchaser may have even less information). Finally we
have evidence of two comparable sales for near-by leases
on Squaw Creek at $50,000 per lease, (assuming a $100,000
purchase price by Black Cliff-Menora for the two leases
immediately below the Lower Lease) and $66,000 (before
discounting) for a somewhat smaller lease, (assuming
the amount allocated for equipment was $US20,000) for
the purchase of Yates' lease further downstream on the
Yukon side. Relying particularly on the comparable sales
on Squaw Creek, but with some support from the royalty
Income Approach and the "Schmidt" approach,
we conclude $70,000 for the market value of the Middle
Lease. Given that royalty income from the mining agreement
with TD provides a high estimate, we assume that this
lease has similar value with or without this mining
agreement in place.
[136] We have less information about the Lower
Lease. There is no evidence to support any value based
on royalty income from Yates. There are also no test
results to support any value based on the "Schmidt"
method. There is also the presence of a relatively loosely
worded mining agreement from which no royalty income
is likely. In the circumstances of the mining history
on this lease, and based primarily on the sale of other
leases we conclude a market value of $35,000.
[137] We have the least information on the Upper
Lease. In our opinion there is no basis for any value
based on royalty income from TD for this lease. Not
only are there no test results for this lease, but the
mining history is much more sketchy, with only the evidence
of Yates' efforts in 1982 and we are not certain how
much of his mining may in fact have been on the Middle
Lease. It is true that some geologists thought the geology
supported gold occurring on the Upper Lease, but other
geologists disagreed, and in our view a purchaser would
not likely have this information. The presence of many
large boulders, the canyons and the lack of existing
access to the area above the falls means that the market
value for this lease would be significantly less than
for other leases on Squaw Creek. Relying on the minimal
evidence presented to us we attribute a value of $5,000
to the Upper Lease.
3.6 Market value of TD's and Yates' Interests
[138] With respect to the right to mine agreements,
the interests of the miners, TD and Yates, are solely
through their agreements. The agreements require TD
and Yates to pay an agreed royalty or rent. This aspect
means that both TD's and Yates' interests resemble a
lessee's interest. The market value of a lease is:
the present value of the difference between the
rental paid by the tenant, and the rental that the
property is worth, for the unexpired portion of
the lease.
See E.C.E. Todd, The Law of Expropriation and Compensation
in Canada, 2nd ed. (Carswell Co. Ltd., Toronto,
1992) p. 413. Professor Todd goes on to say at p. 414
that if the economic rent (which is the amount
the property could have been rented for at the date
of valuation, assuming it had been available for renting
to a new tenant) is not greater than the contract
rent in the lease then "the leasehold interest
has no market value and the lessee will not be entitled
to compensation".
[139] ORM surveyed 10 owners or miners of placer
leases in British Columbia and the Yukon as to the royalty
that they paid or were paid for the right to mine. The
royalties reported ranged from 3 to 30% with 10% reported
as the typical rate by most, although two reported 10-15%
as typical. Higher rates were sometimes reported for
leases with higher grades. The Hodos determined from
this information that the market royalty or rent for
the right to mine was 10%. Their report also indicated
that 10% royalty generally costs the mining operator
approximately 40% of the profits. Since TD's net royalty
in 1993 was 11.6% and this was more than the market
rent, the Hodos concluded that TD's interest had a market
value of nil. We accept ORM's evidence on this point
and conclude that TD's interest had no market value.
Although Yates interest was not valued by ORM, since
Yates' royalty under his agreement to mine was 15%,
then the same conclusion would apply; namely Yates'
interest had nil market value.
4. DISTURBANCE DAMAGES
4.1 T.D. Oilfield Services Ltd.
[140] TD claims disturbance damages for the accelerated
costs of exploration for a new mining property. The
Crown accepts that TD is entitled to some of these costs
as disturbance damages. However, it says that TD's claim
for $53,000 is excessive for two reasons. First, while
TD's claim assumes that mining over the remainder of
the Upper and Middle Leases covered in the right to
mine agreement would take three years (1994-1996) the
Crown's position is that any further mining would be
completed in only one more season. Second, TD's claim
includes a significant portion of expenses for work
on Hunker Creek in 1996 and 1997, when TD was actually
in operation on Hunker Creek in 1997, and was generating
income. As a result the Crown says that the claim for
these expenses is inappropriate.
[141] We agree that the disturbance damages in
this case include the acceleration of moving expenses
and prospecting expenses. We have found above that but
for the expropriation that TD would have returned to
mine for a further two years before having to move on
and prospect for a new mine. Therefore, the discount
to present value of the moving and exploration costs
should be for a two-year period rather than the three-year
period as suggested by the accountant McGillivray. With
respect to the expenses for Hunker Creek, TD initially
stated that exploration there continued from 1996 through
1997 and that mining did not begin until 1998. However
some of the invoices for 1997 stated on their face that
they were for mining. There was also reference in a
Yukon Government Report as to TD being in full operation
on Hunker Creek in 1997. Faced with this evidence Busat
conceded that TD was in production on Hunker Creek in
1997. As a result the 1997 costs should be excluded.
[142] Given that TD had a right to mine the gold
on the Middle and Upper Lease, it could have claimed
for its loss of profits, as long as there was no overlap
with any award for market value. We have already set
out that the mining costs for the continued operation
of the mine in the DCF model advanced by the claimants
are significantly underestimated. With respect to the
1993 mining year, although McGillivray attempted to
show that TD made a profit we are not necessarily convinced.
The relevant financial statement showed a loss of $115,000
and McGillivray reallocated over $200,000 of expenses
to non-mining operations and to capital items before
he arrived at a net profit of about $77,000 on the pro
forma statement. While we accept McGillivray's evidence
that certain items had been wrongly allocated by Busat
or TD's own accountant, we are not satisfied that all
his reallocations are appropriate. As we said above
there are certain general expenses that are omitted
which appear to be at least partly attributable to the
mining operation. Again we note that wages to Douglas
and Carol Busat were omitted. In our opinion McGillivray's
mining expenses are likely undervalued. Despite TD not
satisfying us that a profit was made in 1993, we have
found that TD would have returned to mine the subject
leases for two further years and in these circumstances
TD would likely have made nominal profits. After consideration
of all of the evidence we award a round figure of $75,000
for TD's disturbance damages for acceleration of moving
and prospecting expenses and nominal loss of profits.
4.2 Walter Yates
[143] Yates claims disturbance damages for either
his loss of cash flow based on the DCF calculations
or, in the alternative, his net expenses expended on
his mining operation that he says were thrown away because
the expropriation ended the mining before any income
was received. Yates did not carry on mining on another
lease and thus has no acceleration of moving and prospecting
costs like those claimed by TD. The Crown says that
the primary expense has been for equipment (approximately
$51,000 of $87,000) and that Yates sold this equipment
with his lease on Squaw Creek. Losses on this equipment
are not a result of the expropriation and should not
be charged to the Crown. More fundamentally, the Crown
says that the Lower Lease was mined out by Dendys and
that Yates with no history of successful mining was
unreasonable in incurring the claimed expenses for this
mining operation.
[144] First, with respect to the claim for loss
of cash flow, we have already rejected the claim based
on the DCF analysis. In any event Yates has not demonstrated
any profitable mining in the past. We do not accept
Yates' claim for loss of cash flow as disturbance damages.
[145] The second claim is for approximately $87,000
in costs thrown away as a result of the expropriation.
Because Yates experienced difficulties with his equipment
and then injured his back trying to repair his equipment,
he had recovered only three ounces of gold in his two
years on the Lower Lease. There is some uncertainty
in the details of his expenses as Yates did not always
record whether they were in US dollars or Canadian dollars.
However, the expenses include the net cost of machinery
and equipment including the wash plant (very approximately
$35,000), repairs on the equipment (very approximately
$7,000), mining supplies and fuel (very approximately
$8,000), and travel expenses between Texas and Alaska
(very approximately $10,000). Some of the travel expenses
include trips after the expropriation to move his equipment
to the Yukon lease on Squaw Creek.
[146] We agree that as a result of the expropriation
Yates' opportunity to recoup some of his expenses on
the Lower Lease were foreclosed but for the sale of
his equipment. However, we also agree with the Crown
that Yates did not have a history of successful mining.
The Crown is not responsible for Yates' losses due to
this factor. We award $20,000 to Yates for costs thrown
away as a result of the expropriation.
5. SUMMARY
5.1 Heinz Eckervogt
[147] We have awarded Heinz Eckervogt compensation
for the market value of his interest in each of the
leases as follows:
| Market Value of Middle Lease |
$ 70,000 |
| Market value of Lower Lease |
$ 35,000 |
| Market Value of Upper Lease |
$
5,000 |
| Total |
$110,000 |
5.2 T.D. Oilfield Services Ltd.
[148] We have awarded T.D. Oilfield Services
Ltd. $75,000 compensation for disturbance damages. TD
is not entitled to any compensation for the market value
of its interest in the mining agreement for the Middle
and Upper Leases.
[149] Since the advance payment to TD of $250,000
is more than the compensation awarded, pursuant to section
30(2) of the Act we certify the difference of $175,000
as a debt due by TD to the Crown as represented by the
Minister of Employment and Investment.
5.3 Walter Yates
[150] We have awarded Walter Yates $20,000 compensation
for disturbance damages for costs thrown away. Yates
is not entitled to any compensation for the market value
of its interest in the mining agreement for the Lower
Lease.
6. INTEREST and COSTS
[151] Eckervogt submitted that the issues of
interest and costs should be adjourned until the release
of our decision. The Crown agreed with this submission
and thus we make no awards for interest or costs at
this time. However, we will make a few observations
that may facilitate the parties in settling these issues
in whole or in part without further submissions. We
note that since the conclusion of the argument, this
board has rendered its decision in Premanco
where the issue of the commencement date for interest
under section 46(1) and additional interest under section
46(4) in similar circumstances to those in this case
have been considered. We would also note that although
Eckervogt returned the advance payment cheque for $25,000
for the Lower Lease, section 20(2) of the Act provides
that an advance payment under section 20(1) is deemed
to be made when the expropriating authority tenders
the cheque. Thus, for the purposes of sections 45 and
46, section 20(2) means that Eckervogt is deemed to
have received the full $100,000 as an advance payment
on September 26, 1997. With respect to costs, we note
that the claims were difficult to characterize and to
value. The advance payment made by the Crown and the
expert evidence relied on by the Crown from geology
engineers based in Nevada are some evidence of the difficulties.
At the time that this hearing was held, the decision
by the Court of Appeal in Casamiro and this
board's decision in Premanco (as well as the
Court of Appeal's refusal of leave to appeal) had not
been rendered and therefore there was less authority
that the DCF method was inappropriate.
[152] We request that if one or more of the parties
wish to schedule a hearing or make written submissions
on the issues of interest and/or costs, that they so
advise the registrar within 60 days from the issuance
of these reasons.
THEREFORE IT IS ORDERED THAT the Crown as represented
by the Minister of Employment and Investment shall pay:
| 1. |
Compensation to Heinz Eckervogt in the amount
of $110,000 for the market value of his interest
in the expropriated property pursuant to section
31(1) of the Act. |
| 2. |
Compensation to Walter Yates in the amount of
$20,000 for disturbance damages pursuant to section
31(1) of the Act. |
|