|
October 29, 1998, E.C.B. Control No.
33/91/163 (65 L.C.R. 99)
| Between: |
Double
Alpha Holdings Corp.
Claimant |
| And: |
Pacific
Coast Energy Corporation
Respondent |
| Before: |
Robert
W. Shorthouse, Chair
Fiona M. St. Clair, Vice Chair*
Michael Grover, AACI, Board Member |
| *
Fiona St. Clair resigned as Vice Chair on August
7, 1998 but continued to participate in the reasons
for decision pursuant to s. 53 (7) of the Expropriation
Act. |
| Appearances: |
Michael
R. Tourigny, Counsel for the Claimant
Robert J. McDonell, Counsel for the Respondent |
REASONS FOR DECISION
1. INTRODUCTION
This case arises from the acquisition
of a 9 metre wide strip of land along the edge of a
650 hectare (1,600 acres) development property in Coquitlam
called Westwood Plateau. The claimant, Double Alpha
Holding Corp., owns the Westwood Plateau, having purchased
it in 1989 from B.C. Enterprise Corporation for the
purpose of developing it as a large residential community.
Double Alpha is a trustee whose majority shareholder
is the land development company, Wesbild Enterprises
Ltd. It is Wesbild that has been developing the property
in accordance with an existing Official Community Plan
and Development Agreement. Double Alpha ultimately intends
Westwood Plateau to comprise about 4,500 homes in a
number of separate subdivisions, along with a golf course
and other recreational and park areas.
In May 1990 the respondent, Centra
Gas British Columbia Inc. (formerly Pacific Coast Energy
Corporation), filed a notice of expropriation against
title to a small portion of the Westwood Plateau. The
notice indicated Centra's intention to expropriate a
9 metre wide 1.6 acre strip of land along the western
boundary, along with two rights of way over other parts
of the Westwood Plateau that are not at issue in this
proceeding. On June 15, 1990, the parties entered into
an agreement under s.3 of the Expropriation Act,
S.B.C. 1987, c.23, now R.S.B.C. 1996, c.125 ("the Act")
to transfer the land in question. Among other things,
the agreement fixed May 25, 1990, as the date of expropriation
for the purpose of determining compensation. In accordance
with the terms of the s.3 agreement, Centra paid the
sum of $342,000 to Double Alpha on June 26, 1990, as
compensation for the transfer of the 9 metre strip.
We will call this transfer in these reasons "the taking",
for ease of reference.
At the compensation hearing, Double
Alpha sought compensation as follows:
| 1. |
under s.29 (now s.30) of the
Act, for the market value of the land taken, based
on its highest and best use at the date of expropriation; |
| 2. |
under s.39 (now s.40) of the
Act, for the reduction in market value to the
remaining land that is directly attributable to
the taking; |
| 3. |
costs under s.44 (now s.45)
of the Act; and |
| 4. |
interest under s.45 (now s.46)
of the Act. |
The current section numbers will
be used in these reasons.
The compensation hearing began in
Vancouver on October 15, 1996, and was adjourned on
October 16, 1996, due to evidentiary problems. Double
Alpha had sought to introduce the expert testimony of
two witnesses without having provided formal notice
or a summary of their evidence to Centra. The panel
decided that notice was required, and rather than force
Double Alpha to close its case without benefit of the
evidence in question, adjourned the hearing to permit
Double Alpha to obtain written reports and provide notice
to Centra. We imposed the condition, pursuant to s.46
of the Act, that Double Alpha would be denied any interest
that might accrue on an eventual award of compensation
from the date of the adjournment to the date the hearing
resumed. The hearing began again on December 16, 1996,
and concluded on December 18, 1996.
The witnesses for Double Alpha were
Paul Young, Director of Planning for Wesbild; Carl Nilsen,
appraiser; Richard Skapski, consulting engineer; and
Daniel Daszkowski, landscape architect and urban planner.
Centra Gas adduced the evidence of Brian Davies, appraiser;
Donald Bowins, engineer; and Slade Dyer, development
consultant.
2. BACKGROUND
When Double Alpha bought Westwood
Plateau, it was subject to a Development Agreement made
between the previous owner and the District of Coquitlam
on August 23, 1988, which was registered against title.
The Development Agreement provides for the development
taking place in phases, and it divides the entire Westwood
Plateau into eight large Development Blocks, identified
as numbers 1 through 8. The Development Agreement also
provides that the phasing and the boundaries of these
Development Blocks may be amended subsequently, subject
to Coquitlam's final approval.
After Double Alpha's purchase of
the site, Wesbild began to work with Coquitlam to refine
the Official Community Plan ("the OCP") for the first
phase of development, "Stage One". The entire area of
the Westwood Plateau is designated in the OCP for residential
development and associated services. The plan is that
Development Blocks will be rezoned as appropriate and
the subdivision and installation of services will then
be undertaken in accordance with that rezoning. Coquitlam
adopted an Amended OCP on March 12, 1990. Zoning was
finalized for Stage One development (for Development
Blocks 2, 3 and part of 4) on April 9, 1990. By this
time, Wesbild had already begun site preparation work
and servicing for the first new subdivisions. These
were registered between September and November 1990,
and Wesbild's sales program for the lots in Stage One
began at the end of November 1990.
Much of the evidence centered on
Development Block 6A, a smaller defined portion of Development
Block 6. Development Block 6A is an area of about 10.3
hectares (25.5 acres) defined by an access road on the
south, the property line of Westwood Plateau on the
north, Noons Creek on the east and the municipal boundary
between Coquitlam and Port Moody on the west. The appraisers
were in agreement that the most likely zoning that will
be approved for this area is single family residential
development. Development Block 6A was scheduled to be
part of the Stage Two development.
The Stage Two development was to
incorporate Development Blocks 5 and 6. Paul Young testified
that Stage One involved approximately one-third of the
overall site and of the number of dwelling units anticipated.
Wesbild projected that Stage One would satisfy approximately
2 to 3 years of market demand. Mr. Young stated that
in 1990 Wesbild was examining the range of alternatives
for Stage Two, looking at such items as a possible golf
course and appropriate densities. Apparently the golf
course and related density problems raised troublesome
issues for the development of Block 5, resulting in
Wesbild's conclusion at the time that Blocks 6E and
6A would probably be the first portions of Stage Two
to be slated for development. This was the situation
at the time of the taking.
3. THE ISSUES
The main issues to be determined
here are:
| 1. |
What area should
be considered "the larger parcel", that is, the
piece of land from which the 9 metre strip was
taken? Should it be the entire Westwood Plateau,
a large development block or a smaller development
block? |
| 2. |
What was the highest
and best use of the larger parcel at the date
of the taking, and was that different from the
then existing use? |
| 3. |
What is the appropriate
approach to the valuation of the land taken and
to the determination of the loss in value to the
remaining land, if any? |
| 4. |
What was the value
of the land taken at the date of the taking? |
| 5. |
What was the loss
in value to the remaining land, if any, as a result
of the taking? |
4. DISCUSSION
4.1 The Larger Parcel
Section 40 of the Act deals with
partial takings. Subsection (1) reads as follows:
| 40. |
(1) |
Subject to section
44, where part of the land of an owner is expropriated,
he or she is entitled to compensation for |
|
|
(a) |
the reduction in market value
to the remaining land, and |
|
|
(b) |
reasonable personal and business
losses that are directly attributable to the taking
or that result from the construction or use of
the works for which the land is acquired. |
In section 40(6), the remaining land
is identified as:
| (a) |
land contiguous
to the expropriated land, or |
| (b) |
land close to
the land that was expropriated, the value of which
was enhanced by unified ownership with the land
expropriated. |
Since compensation under s.40 is
based partly on the reduction in market value to "the
remaining land", it must be clearly defined what constitutes
the area of land before the taking, or what we are referring
to here as the larger parcel. Obviously, where the requirements
of s.40(6) are satisfied, the definition of the larger
parcel will determine the identification of the remaining
land.
In most cases that come before the
board involving partial takings, there is no controversy
as to what property constitutes the larger parcel. In
this case, however, it is a matter of contention and
serious import. There are three possibilities for consideration
as the larger parcel. They are:
- the entire Westwood Plateau (650 hectares/1,600
acres)
- Block A (defined below -- 255 hectares/630 acres)
- Block 6A (10.34 hectares/25.56 acres).
Noting that the overall area of Westwood
Plateau is huge, Double Alpha maintains that the larger
parcel should be viewed as Development Block 6A. Carl
Nilsen, Double Alpha's appraisal expert, states at p.13
of his report, after describing the land taken as "form[ing]
part of a large, on-going development project":
We have considered it most appropriate
to concentrate solely upon the 25.5 acres in our residual
analysis...Thus, although the land taken does form
part of the very much larger development block described
earlier [the 255 hectare Block A, which is defined
below], it is not considered necessary to undertake
a valuation of the entire parcel as the value for
the majority of the area will remain unchanged before
and after the taking.
Nilsen refers to Development Block
6A as "a block of land that would form a logical development
enclave."
Centra, on the other hand, maintains
that the larger parcel should be viewed as being nothing
smaller than a 255 hectare parcel (which represents
just under 40% of the total area of the Westwood Plateau
as a whole), of which Development Block 6A constitutes
a small portion. This parcel is referred to in Centra's
materials as Block A, Sec. 15, which is a shortened
version of a Land Title description. For ease of reference,
we will refer to it simply as Block A. (The various
development blocks were defined with a view to the development
process, and not with any specific reference to Block
A or the other major Land Title block that makes up
the Westwood Plateau.) Block A, Centra argues, is a
very large parcel of land not impacted by the taking
of the 9 metre strip. It says that, given the scale
of the development, any lots that might be said to have
been "lost" as the result of the taking could be "shifted"
to other portions of Block A beyond Parcel 6A. It also
argues that even for Block 6A alone, the density achievable
is roughly equivalent both before and after the taking.
On this basis, Centra maintains that there is no reduction
in value to the remainder -- that is, to Block A minus
the 9 metre strip.
Centra's counsel took this position
in his closing argument, but had earlier put forward
in evidence the expert testimony of Brian Davies, who
prepared two appraisal reports regarding the taking
-- one on April 19, 1990, (upon which the advance payment
was based) and the second on September 13, 1996 (prepared
in anticipation of this hearing). The second of these
reports was entered into evidence by Centra, and the
first by Double Alpha. In both reports Davies finds
a loss in value to the remainder, using essentially
the area of Development Block 6A. Ultimately, Centra
chose not to rely on either of these reports in terms
of loss in value, but offered no other expert appraisal
evidence in their place. In addition, as the Development
Agreement was not entered as evidence, the potential
for density transfer claimed by Centra in its submission
could not be adequately explored.
If, as Centra maintains, the larger
parcel goes beyond the boundaries of Development Block
6A, then it could logically be said to extend to the
four corners of Westwood Plateau. For the valuer, this
would require consideration of over 650 hectares (1,600
acres) in order to estimate the loss arising from the
taking of the 9 metre strip, the area of which is only
about 0.65 hectares (1.6 acres).
If, on the other hand, the larger
parcel is confined by the boundaries of Development
Block 6A, which are Noons Creek, the access road and
the municipal boundary, then the valuer is faced with
the task of accounting for costs associated with extending
roads and services through Westwood Plateau to Development
Block 6A, on the basis that a purchaser of the smaller
Development Block 6A would certainly be required to
reimburse the owner of the larger Westwood Plateau for
having brought such services to it.
Neither party provided us with any
case law on the issue of the identification of the larger
parcel. We have, nonetheless, found some assistance
in the reasons of the former Ontario Land Compensation
Board in Roman Catholic Episcopal Corp. for the Diocese
of Toronto v. Metropolitan Toronto and Region Conservation
Authority (1978), 15 L.C.R. 133. In considering
the issue of valuing the "injurious affection to the
lands remaining" after a partial taking, the Board stated
at p.149:
In our opinion on the before-and-after
approach...it is not always necessary to determine
the market value of all of the owner's lands
both before and after the taking. On the contrary...where
on the before-and-after approach some lands, for example,
on which buildings are located, are not affected by
the expropriation, they may, and in this case, should
be, excluded from the determination of market value,
both before and after.
We agree...that "the whole of the
owner's lands"...has an implicit meaning of "the whole
of the owner's lands necessary to be taken into account
in determining the market value of, and injurious
affection to, the lands affected by the expropriation".
We find this logic compelling, and
equally applicable to our legislation.
In addition, the board has already,
in Mayfair Resources Corp. v. Greater Vancouver Water
District (1997), 61 L.C.R. 183 (B.C.E.C.B.), examined
this type of problem and decided to use a smaller portion
of the owner's entire landholding as the larger parcel
for the purpose of applying s.40 of the Act.
We conclude that it is neither necessary
nor desirable to view the larger parcel here as being
the whole of the Westwood Plateau or the whole of Block
A. In our view, it would make more sense to define the
larger parcel as Development Block 6A. This is because
of the natural boundaries caused by the roads, the creek
and the municipal border and the fact that it is a discrete
parcel intended for development separate from the other
areas of Block A and Westwood Plateau as a whole. In
addition, there was no evidence led that persuaded us
that costs outside of Development Block 6A would have
varied because of the taking. Finally, the only expert
valuation evidence before us was done on the basis that
Development Block 6A should be viewed as the larger
parcel from which the 9 metre strip was taken.
4.2 Highest and Best
Use
Nilsen, on behalf of Double Alpha,
considers the highest and best use of Development Block
6A to be "residential single family development in accordance
with the RS-1 zoning". He considers that the highest
and best use of this area "will be unchanged in a general
sense by the taking," but states that "the acquisition
does have implications for the development capability
of the area."
Davies, for Centra, considers the
issue of highest and best use in both his appraisal
reports. In his 1990 report, in which he defines Block
A as the "subject property", he concludes that its highest
and best use "is for residential development." With
regard to the smaller Development Block 6A, Davies is
of the view that its highest and best use "is a holding
property for development in approximately three years."
In his 1996 report he considers the highest and best
use of the same two parcels. The highest and best use
of Block A, he says, is "for future residential development."
Development Block 6A he views this time as having a
highest and best use as "a holding property for development
in approximately five years."
As far as the probable period of
time between the taking and the eventual development
of the subject is concerned, we have concluded that
three years is appropriate. We note that Davies' first
report, prepared about one month before the valuation
date, fixes three years as the likely time period, as
does Nilsen's report, prepared one year and four months
after the valuation date. The only support for a five
year period is found in Davies' second report, prepared
over six years after the valuation date. In that report,
Davies refers, with reference to Development Block 6A,
to two other nearby development blocks and indicates
that one underwent subdivision in late 1993, with lots
marketed throughout 1994 and into 1995, while the other
was subdivided and developed in 1992. He reasons at
p.28 that
... the 25.56 acres directly impacted
by the taking would have followed these two areas
on the development time table since the impacted lands
are located at the most westerly extreme of the subject
property and would therefore be the last block to
be serviced. As of the effective date, a five year
time frame was the soonest pre-development holding
period that was suggested by the information available
at that time.
Under cross-examination, Davies explained
that in his 1990 report he picked the three year time
frame by choosing the mid-point of a possible range
of time periods indicated by the information available
at that time. In his 1996 report, however, he relied
on events as they had unfolded, which indicated to him
the far end of the range. He attested to his belief
that the use of such information not available at the
date of valuation is appropriate.
We disagree with Davies on this use
of hindsight. The determination of highest and best
use as at a particular date is an exercise in placing
oneself in the shoes of a notional potential purchaser
of the property on that particular date. Such a person
would have no access to actual data from years in the
future, and so would have to undertake the type of reasoned
analysis undertaken by Davies in 1990 and by Nilsen
in 1991. Both these experts thought at that time that
a three year pre-development period was appropriate.
We are persuaded that, with the information available
then, this was the probable conclusion as to development
timing likely to be drawn by a potential purchaser and
thus to be factored into the determination of the market
value.
We conclude, therefore, that the
highest and best use here was for development within
three years. We conclude as well that this was no different
from the actual use of the property at the time of the
taking, as Double Alpha was holding the land for development
and counting on just such a time frame when the expropriation
occurred.
4.3 Appropriate Valuation
Method
Nilsen does not attempt the direct
comparison approach. At p.13 of his report he states:
In view of the fact that this land
forms part of a large, on-going development project
for which there are no direct market comparables,
the most appropriate method of valuation is considered
to be the residual method [referred to in these reasons
as the subdivision development approach].
He then outlines a before and after
analysis using the subdivision development approach,
but only on Development Block 6A, a portion of the "large,
on-going development project." His conclusion as to
the appropriate amount of compensation is found by deducting
his estimate of the value of the land after the taking
from his estimate of the value of the land before the
taking. In the before and after subdivision development
approach, the compensation figure is inclusive of both
the value of the land taken and the loss in value to
the remainder.
In support of the appropriateness
of the subdivision development approach, counsel for
Double Alpha referred us to three reported decisions:
Municipality of Metropolitan Toronto v. Loblaw Groceterias
Co. Ltd. (1971) 1 L.C.R. 118, a Supreme Court of
Canada decision; Ferancik v. Langley (Township)
(1996), 60 L.C.R. 123, a decision of this board; and
Genstar Corp. v. Greater Vancouver Regional District
(1989), 43 L.C.R. 122, a decision by a panel of three
private British Columbia arbitrators. The Toronto
case and the board's Ferancik decision are both
examples of the adoption of the subdivision development
approach, although neither is particularly helpful in
articulating the reasons for its choice. The Genstar
decision refers to the approach as involving "a heavy
measure of speculation -- albeit informed speculation"
and comments that "its conclusions can be greatly affected
by any number of variables encountered in the process."
It also refers to the appropriateness of the approach
in cases where there is an "absence of suitable, comparable
sales data." Double Alpha argues that in the circumstances
of this case the subdivision development approach should
be accepted, and that Nilsen's report and supporting
evidence should be accepted over Davies'.
Davies selectively employs both the
direct comparison and the subdivision development approaches
in his two reports. In his first report he relies exclusively
on the direct comparison approach and finds a loss in
value to the remainder by applying a lot yield formula.
In his second report, he employs the direct comparison
approach only to arrive at a before taking value for
Development Block 6A. He does not attempt to estimate
an after taking value using the same approach, nor does
he use the direct comparison approach to arrive at his
final loss estimate. What he does is determine a slightly
different before taking value through the use of the
subdivision development approach, while nonetheless
stating his preference for the higher direct comparison
before figure. Although he maintains that "the Direct
Comparison Approach is considered the best method due
to the larger number of assumptions that have to be
made with the Development Approach," Davies' ultimate
conclusion as to the total compensation payable is the
difference between his before and after subdivision
development approach values.
Thus, the two appraisal reports that
were put forward in evidence by the parties for whom
they were prepared (that is, the Nilsen report and the
second Davies report) both calculate a loss estimate
based solely on the subdivision development approach.
Curiously, Centra's counsel, Mr. McDonell, in his closing
argument, urged us not to apply the subdivision development
approach. He stated that it was
...inappropriate in the circumstances
of this case because the development was far from
imminent at the time of the taking; the various different
designs are speculative; and the development costs
for Block A are not before the Board.
He urged the panel to award Double
Alpha compensation for the area of the land taken on
an appropriate value per acre using the direct comparison
approach and to deny the claim for loss in value to
the remainder. In support of his opposition to the use
of the subdivision development approach in this case
he cited three case authorities: Maritime Electric
Company Limited v. Thorne and Thorne (1978), 14
Nfld. & P.E.I.R. and 33 A.P.R. 364, a decision of the
Prince Edward Island Court of Appeal; Servold v.
City of Camrose (1982), 25 L.C.R. 342, a decision
of the Land Compensation Board of Alberta; and Christiansen
v. City of Calgary (1987), 37 L.C.R. 320, also a
decision of the Alberta Land Compensation Board. In
the Maritime Electric case the court rejected
the use of the subdivision development approach because
the evidence showed that the proposed subdivision had
not been approved, and might never be granted approval.
They considered the subdivision to be "an uncertain
possibility" that would not warrant damages for injurious
affection under the Prince Edward Island Electric
Power and Telephone Act. The Alberta Board in the
Servold decision refers to case law that sets
out "the difficulties, speculation and uncertainty inherent
in the development approach and the unreliability of
that approach as a method of determining value." In
the particular facts of the Servold case, the
Board also found "further difficulties as the density,
type and timing of development [were] uncertain." Finally,
they were satisfied that two comparable sales existed
that were capable of adjustment and application on a
direct comparison basis. In Christiansen, the
Alberta Board declined to accept the subdivision development
approach because the evidence about the proposed subdivision
itself did not provide a basis for determining the exact
number or configuration of lots, and the evidence regarding
the costs of servicing "varied substantially and of
course are inextricably connected with the yield of
lots achieved."
Professor Todd, in The Law of
Expropriation and Compensation in Canada, 2nd ed.
(Toronto: Carswell, 1992), discusses the subdivision
development approach. He says at p.219:
Courts and tribunals are usually
reluctant to rely on the land development (subdivision)
approach for two reasons. First, unless a proposed
subdivision has actually been officially approved
there is always some degree of uncertainty as to whether,
and under what conditions, the subdivision would ever
have materialized...
Second, it is recognized that the
approach is "volatile" in the sense that a comparatively
minor change, for example in the costing of services,
can produce a figure in the end result which will
significantly affect the residual value.
He goes on to indicate that courts
and tribunals frequently reject this approach on the
basis of the availability of reliable comparable sales
data, the conclusion that the subject property was not
ripe for development at the date of expropriation, or
a determination that the various factors such as servicing,
engineering and other development costs were not based
on solid, factual evidence.
The Appraisal Institute's The
Appraisal of Real Estate, Canadian Edition, (1992)
states at p. 297 that
... bona fide sales data provide
a better indication of value than a subdivision development
prospectus. The reliability of the approach is determined
by the accuracy of the lot yield, absorption rate,
sale prices, servicing costs and soft cost estimates.
Most of the case law on the appropriateness
of the subdivision development approach deals with the
issue of the remoteness in time of the development,
as well as the availability of reliable data with which
to perform a direct comparison valuation. In Lincoln
Village Ltd. v. City of Waterloo (1977), 12 L.C.R.
232 at p.243, the Ontario Land Compensation Board stated
that "...where the state of development of the lands
is such that all the necessary computations can be accurately
forecast, the development cost approach may be appropriate,
provided that suitable comparable sales are not available."
In Oakfield Estate Ltd. v. Halifax (County) (1992),
47 L.C.R. 100 at 105, the Nova Scotia Expropriations
Compensation Board declined to accept valuation conclusions
based on the subdivision development approach because
there was "uncertainty as to the date of commencement,
the number of lots, the costs of development, price
and marketability."
This board, in McKinnon v. School
District No. 36 (Surrey) (1994), 54 L.C.R. 23, referred
to Professor Todd's text, and quoted him as stating
that "it is appropriate to use the method where there
is a paucity of comparable sales...or where the appraisers
for both sides find insufficient comparable sales on
which to base an opinion on the market approach and
both accept that development was imminent as of the
date of expropriation." The board was not persuaded
in that case that the "required degree of imminence
was prevalent", and thus declined to apply the subdivision
development approach.
This board has also recently considered
the use of the subdivision development approach in the
Mayfair Resources decision cited above. The board
included in its reasons a quotation from the appraisal
report of Mr. Douglas Mendel, which in our view is sufficiently
instructive to warrant reproduction in part here as
well:
The Subdivision Development Method
can be a reliable appraisal technique when subdivision
and development are imminent and represent the highest
and best use of the land. The accuracy of the approach
is dependent upon the availability of reliable market
evidence of the value of the subdivided parcels...If
the form of subdivision and achievable densities can
be accurately forecast and costs can be predicted
with some degree of accuracy the method can provide
good results. The reliability of the Subdivision Development
method is dependent on the accuracy of the lot yield
absorption, absorption rate, predictability of lot
prices, servicing costs and soft cost estimates. Where
these elements can be determined with accuracy the
method can be considered reliable for the purpose
of estimating the value of raw land.
In the case of this development,
we have determined that the probable delay period for
completion of the subdivision and sale of the lots would
be 3 years. At the time of the taking, the appropriate
zoning was not in place, the OCP had not been amended
as required, and no subdivision application had yet
been made. Only the main trunk services were in place
(that is, sanitary and storm sewers and water), and
the evidence shows that a pumping station and reservoir
would have had to be constructed because of water pressure
problems created by the topography. The evidence about
the probable number of lots was conflicting, and was
based on plans that were prepared for this hearing and
not for the development itself. In addition, the two
appraisers were separated by the considerable sum of
$1,874,688 in their estimates of the development costs.
As for the availability of suitable
comparable sales, since neither of the proffered appraisal
reports estimated the loss on a direct comparison basis,
we are not in a position to conclude whether or not
such comparables were available. When pressed under
cross-examination, Nilsen said that there were no sales
of property of similar size and location and immediacy
of development, so the comparative approach was not
available. Davies, meanwhile, found eight sales of acreage
from which he concluded that the value of Parcel 6A
was $115,000 per acre, or $2,940,000, before the taking.
He prepared no after taking valuation by direct comparison,
and instead relied for his conclusions on the subdivision
development approach.
We accept that any prospective purchaser
of Development Block 6A in May of 1990 would have viewed
it as being appropriate for development within a three
year period. We are also of the view, however, that
the many variables that must be capable of accurate
estimation in order to permit a reliable subdivision
development valuation are not so in this case. The difficult
situation in which we find ourselves here is that if
we do not accept the subdivision development approach
as put forward by both expert appraisers, we will not
have any appraisal evidence before us other than Davies'
estimate in his 1990 appraisal report, based on a value
per raw lot and a lost lot total based only on the percentage
of the area of the strip taken against the area of the
larger parcel.
Although the preferred method of
valuation here may have been the direct comparison method,
if adequate comparable data were available, what we
have instead are two expert reports using the subdivision
development approach and extensive planning and engineering
evidence in support of those reports. We do not believe
that we would be adequately addressing the valuation
evidence if we looked only to the direct comparison
analysis of Davies in 1990, which was not even entered
into evidence by the party for whom it was prepared.
Doing the best that we can in these circumstances, we
shall proceed to determine this claim based primarily
on a review of the subdivision development valuations.
In addition, by way of comparison, we will consider
the 1990 Davies direct comparison valuation.
5. CALCULATION OF COMPENSATION
5.1 Area of Land Taken
Both parties' appraisal experts calculate
that the area taken constitutes 1.59 acres (0.6421 hectares).
Nilsen calculates the larger parcel before the taking
to have been 25.1 acres, and after the taking to have
been 23.51 acres, for a difference of 1.59 acres. Davies,
while using different figures, arrives at the same conclusion.
He subtracts 23.97 acres in the after taking scenario
from 25.56 acres in the original scenario. We therefore
accept that the area taken was, in fact, 1.59 acres.
5.2 Number of Lots Lost
We have the benefit of two before
and after plans to assist in the determination of the
number of lots lost. Double Alpha's plans were prepared
internally by Paul Young of Wesbild and refined by Daniel
Daszkowski of CIVITAS Urban Design & Planning Inc.,
in consultation with Richard Skapski, a consulting engineer
with InterCAD Services Ltd. Centra Gas' plans were prepared
by Slade Dyer, development consultant, in consultation
with Donald Bowins, engineer. Both sets of plans were
prepared after the taking, as Double Alpha's development
preparation for Development Block 6A had not proceeded
to the point of designing the subdivision at the time
of the taking.
We prefer the Dyer plans for a number
of reasons. First, they were prepared by an objective
outsider to the project, in contrast with Double Alpha's
plans, which were largely prepared internally. In addition,
we find that the Dyer plans are consistent with other
Westwood approved plans in terms of lot widths at the
building set-back line, and that the after plan places
the main road in what the evidence disclosed was the
best location (the west side) for maximum efficiency.
Finally, the Dyer plans achieve virtually
the same density after the taking as before, thereby
mitigating the loss to the remainder:
|
Civitas |
Dyer |
| Before Plan |
25.1 acres |
25.56 acres |
|
104 lots |
107 lots |
|
4.14 units per acre |
4.19 units per acre |
| After Plan |
23.51 acres |
23.97 acres |
|
95 lots |
100 lots |
|
4.04 units per acre |
4.17 units per acre |
Dyer's plans on behalf of Centra
generate more lots and a greater yield, because in Civitas'
plans on behalf of Double Alpha the area is less and
road widths are 17 metres rather than the allowed 16.5
metres under the subdivision bylaw, or 14 metres if
single loaded (i.e. houses on only one side). Moreover,
by placing the road on the west side, full advantage
could be taken of the required 6 metre set back from
the top of the creek bank as required in 1990 by including
this set back in the lot areas.
Dyer's conclusion, which we accept,
is that 7 lots were lost as a result of the taking.
5.3 Summary of Appraisal
Evidence
The two subdivision development valuations
before us differ primarily in three respects: the number
of lots both before and after, the value of the raw
lots, and the development costs. We have summarized
the calculations of both appraisals in comparison charts,
as follows:
| BEFORE TAKING
APPRAISALS |
Nilsen |
Davies
#2 |
| # of lots |
104 |
107 |
| $ per lot |
$108,000 |
$105,000 |
| Total gross revenue |
$11,232,000 |
$11,235,000 |
| Developer's profit |
20%
gross
$2,246,400 |
20%
gross
$2,247,000 |
| Sales commission |
4%
gross
$449,280 |
2%
gross
$224,700 |
| Development costs |
$2,574,000 |
$4,431,852 |
| Financing on development
costs |
15%
for 1.5 ms
$46,312 |
15.75%
for 3 ms
$165,052 |
| Property taxes |
|
$43,886 |
| Discount/deferral
to sales |
15%
for 7.5 ms
$526,525 |
|
| Discount/deferral
to development |
10%
for 3 years
$1,341,981 |
7.35%
for 5 years
$1,230,821 |
| Market Value |
$4,047,502
Rounded to $4,050,000 |
$2,891,689
Rounded to $2,890,000 |
| AFTER TAKING
APPRAISALS |
Nilsen |
Davies
#2 |
| # of lots |
95 |
100 |
| $ per lot |
$108,000 |
$105,000 |
| Total gross revenue |
$10,260,000 |
$10,500,000 |
| Developer's profit |
20%
gross
$2,052,000 |
20%
gross
$2,100,000 |
| Sales commission |
4%
gross
$410,400 |
2%
gross
$210,000 |
| Development costs |
$2,489,000 |
$4,363,688 |
| Financing on development
costs |
15%
for 1.5 ms
$44,887 |
15.75%
for 3 ms
$162,514 |
| Property taxes |
|
$41,156 |
| Discount/deferral
to sales |
15%
for 7.5 ms
$468,470 |
|
| Discount/deferral
to development |
10%
for 3 years
$1,194,106 |
7.35%
for 5 years
$1,081,580 |
| Market Value |
$3,601,227
Rounded to $3,600,000 |
$2,541,061
Rounded to $2,540,000 |
Nilsen's resulting figure for the
overall compensable loss is $450,000, and Davies' is
$350,000 -- a difference of $100,000. Both of these
conclusions exceed Davies' 1990 valuation of $317,289.
One can readily see from these charts
that, although both appraisers made very different assumptions
about the number of lots that the area could generate
both before and after the taking, and although they
assigned different values per lot, their figures for
total gross revenue before the taking are almost identical
because of the way their different figures work together.
Nilsen, however, assumed a 9 lot loss while Davies concluded
that only 7 lots would be lost as a result of the taking.
Both appraisers based their assumptions
on the number of lots available on plans generated by
others. Nilsen relied on Paul Young's plans (as refined
by Civitas), while Davies relied on the plans prepared
by Slade Dyer. Similarly, the particulars of the development
costs put forward by both appraisers were supplied by
the engineers who assisted with the plans, both of whom
filed their own reports and gave evidence in this hearing.
As can be seen from the chart, there is a sizable difference
of $1,857,852 in the two estimates of development costs.
The actual differences between the two before and after
figures is smaller than this, however -- about $1 million
-- which is largely explained by the fact that Nilsen,
who used the lower development cost figure, also factored
in a larger sales commission and a further discount
period between the development and the ultimate sales.
It may be noted that both estimates
based on the subdivision development approach are higher
than Davies' 1990 valuation based on the direct comparison
approach. In that report, Davies estimates a value by
direct comparison of $45,327 per raw lot, noting that
up to seven lots would be lost. The loss in value he
then calculates to be $317,289.
On a before and after test, he values
26.2 acres by direct comparison at $185,000 per acre
or $4,850,000 rounded before the taking. Assuming a
107 lot potential, this is $45,327 per raw lot. After
the taking, he simply reduces the number of potential
lots to 100, applies the same lot value, and finds a
value of $4,532,700. By this method, the loss is $317,300.
Without the rounding to $4,850,000 from $4,847,000,
the raw lot value is $45,299 and the resultant loss
$317,093.
In his second report, he estimates
a before value at $2,940,000 by direct comparison, and
at $2,890,000 by a development approach. With his after
value at $2,540,000 he estimates the value of the part
taken together with the loss in value to the remaining
land at $350,000. Under cross-examination, he defended
this different conclusion from his first report as being
the result of applying a deferment of five years rather
than three years, and more definitive adjustments.
5.4 Market Value Before
the Taking
5.4.1 Lot Value
Using thirteen comparable sales that
took place in May and June of 1990, Nilsen arrives at
a before taking value per serviced lot of $108,000.
Since, in his view, the market had shown movement prior
to the taking, he chooses to focus on sales that occurred
around the time of the taking in order to avoid having
to make time adjustments. Nilsen's comparables range
between $94,000 and $155,000, with the majority falling
between $115,000 and $127,000. Most of the comparables,
however, were better located in that they were in more
established areas or had better views. Nilsen therefore
concludes that the lots would sell for between $105,000
and $110,000, and on that basis settles on an average
lot value of $108,000.
Davies' seventeen comparables were
sold during a broader time range -- March to December
1990. They sold for an average lot value of between
$99,000 and $112,000, after certain adjustments. Davies
concludes that his comparable 11 was the most similar
to the subject, and its value was slightly less than
$105,000 after applying a time adjustment. Based on
this range and this most similar comparable, Davies
concludes that an average price of $105,000 was appropriate
for the subject lots.
We prefer Davies' analysis on this
point, as he has identified both a range of prices and
a best comparable that fits within that range. We therefore
accept his before taking figure of $105,000 per lot.
5.4.2 Developer's Profit
Both appraisers have identified an
expected developer's profit of 20% for a subdivision
such as this. The gross income from a subdivision of
107 lots with a value of $105,000 each would be $11,235,000.
Twenty per cent of that figure comes to $2,247,000,
which we accept as a reasonable amount to have been
expected by a developer of the subject lands.
In a standard scenario, sales commissions
would have to be paid out of the remainder. The two
appraisers differ as to the applicable rate to be applied.
Nilsen estimates that a 4% commission would be applicable,
whereas Davies uses only a 2% commission. Since Nilsen
admitted under cross-examination that his 4% figure
was "a little high," we are prepared to apply a 3% sales
commission to the gross profit. This would result in
a total deduction of $2,584,050 ($2,247,000 + 337,050)
from the gross income figure of $11,235,000, for an
adjusted income of $8,650,950.
5.4.3 Development Costs
Nilsen uses, for the pre-taking cost
of servicing the lots, the figure of $23,750 per lot
provided by Richard Skapski, P.Eng., of InterCAD Services
Ltd. In preparing his cost estimates, Skapski deals
with two basic cost components: an all-inclusive cost
per linear metre of road, complete with typical underground
services; and an all-inclusive cost per linear metre
of rear-yard services, required where gravity sanitary
and storm sewer service cannot be provided directly
to the fronting road because of the steepness of the
land. Skapski concludes that the cost per linear metre
for the road servicing would be $1900 and $400 for the
rear lot servicing. He uses these figures to arrive
at the cost of $23,750 per lot which Nilsen adopts in
his appraisal. Nilsen also factors in the additional
amount of $1,000 per lot for "miscellaneous costs."
His total estimate of pre-taking development costs is
$2,574,000.
Nilsen testified that he included
only on-site costs, since in his view no off-site costs
would apply on the basis that Development Block 6A would
be developed as part of the whole Westwood Plateau.
This would mean that the infrastructure costs would
not change as a result of the taking. Under cross-examination,
Nilsen answered questions about a notional purchaser
of Block 6A. He admitted that such an individual would
have to expect that the cost of such items as creek
crossings and services being provided to the perimeter
of Block 6A would be factored into the cost of buying
that segment of property. He indicated, however, that
he did not factor these assumptions into his report
because his conclusions were based on a notional purchaser
of Block A as a whole rather than of Block 6A in particular.
Davies, on the other hand, applies
both on-site and off-site costs to his analysis. He
adopts the figures provided by Don Bowins, P.Eng., of
D.K. Bowins & Associates, which in turn were prepared
using the layout plans provided by Slade Dyer & Associates.
The on-site figure includes the expense of roads, drainage,
sanitary sewer, water, streetlights, other utilities
and legal surveys. "Double Servicing" of storm and sanitary
utilities is assumed, in light of the steep topography
of the site. Cost figures for work "adjacent to the
site" are also used by Bowins. He does this on the basis
that "even though the extension of services to this
site were done under a previous phase of the development
they are for the benefit of this site and therefore
should be considered as part of the servicing costs
of this parcel." These costs include the crossing of
Noons Creek at two locations and the extension of all
the other utilities. Finally, Bowins calculates the
cost of off-site services, including water, sanitary
and storm sewer, and roads, which are listed in the
Development Agreement and are indirectly required to
service the Westwood Plateau. He also includes an equivalent
amount to the Development Cost Charges that the City
of Coquitlam charges developers, at the 1990 rate of
$955 per lot. This was done despite the fact that the
evidence showed that Coquitlam did not charge Wesbild
any Development Cost Charges for any part of the Westwood
Plateau. Davies' total pre-taking development cost estimate
is $4,431,852, which exceeds Nilsen's estimate by over
$1.8 million. As noted earlier, the primary reason for
this large difference is Nilsen's omission of off-site
costs.
We prefer the approach taken by Davies
and Bowins. In our view, the direct and indirect off-site
costs of developing Development Block 6A cannot be ignored.
A prospective purchaser of this block would reasonably
expect to have to compensate the former owner for providing
creek crossings and for bringing all necessary services
to the perimeter. In addition, we have already stated
that we prefer the Slade Dyer plans to Paul Young's
plans, and since these costs were estimated with the
Dyer plans in mind, we also prefer them for that reason.
We therefore accept Davies' figure
of $3,215,300 for on-site construction costs, $57,000
for legal survey costs, $640,060 for direct off-site
costs and $217,844 for indirect off-site costs. This
gives an overall total for development costs of $4,130,204.
We do not, however, accept the need to include an amount
for Development Cost Charges, as the uncontradicted
evidence of Paul Young was that the municipality had
granted an exemption in this case.
5.4.4 Financing on Development
Costs
To the development cost figure must
be added an amount for interest for the duration of
the development period. Nilsen estimates that a subdivision
of this size would take about three months to service,
and to reflect the fact that not all the financing costs
would be incurred over the whole period, he uses a one
and a half month period in his calculations. He applies
an interest rate of 15%, which he states was appropriate
at the time of the valuation.
Davies' opinion is that there would
be a six month period of construction that would have
to be financed. His calculations apply a 15.75% rate
for a three month period, the latter presumably upon
the same logic as that applied by Nilsen. As for the
interest rate itself, Davies' report indicates that
the prime bank rate at the valuation date was 14.75%
and that, typically, financing is provided to reliable
land developers at 1% or 2% above prime. Within this
range, he employs a rate of 15.75%, although in his
earlier report he employs a deferment rate of 12%.
We accept Nilsen's rate of 15% which
was estimated closer to the valuation date. We prefer
Davies' choice of financing period at one half of six
months, however, which allows for both on-site and off-site
servicing. We therefore will apply a 15% financing rate
to the development costs over a three month period,
which amounts to $154,883.
5.4.5 Parks Allowance
According to Paul Young's testimony,
park dedications -- specified in the Development Agreement
-- are to be taken from individual enclaves. We have
therefore concluded that a 5% parks allowance should
be applied. In this case, it amounts to $204,106 before
the taking.
5.4.6 Holding Costs
Nilsen estimates that the servicing
and sale of the subdivision would take about twelve
months -- three months to service the first phase and
nine months to sell all the lots. On the basis that
the profit from the earlier sales would mitigate to
some extent the holding costs in the later stages, he
applies a 15% discount rate over a deferral period of
seven and a half months. This results, using his figures,
in a further deduction of $526,525 from the net revenue.
Confidence in this technique is diminished by both the
reference to the suggestion that profits will help to
mitigate the holding costs -- without specifying by
how much -- and also by the allowance of interest over
one-half of a fifteen month period, whereas his report
indicates three months to service and none months to
sell, for a total twelve month period. Davies, on the
other hand, merely internalizes this element in calculating
the developer's profit, a simplified approach that was
not challenged and that the board will adopt.
5.4.7 Residual Land
Value
In order to calculate the before
taking land value upon the commencement of development,
one must subtract the on-site and off-site costs, as
well as the interest and park allowance, and a further
amount for property transfer tax. This results in a
figure of $4,082,115. (The property transfer tax is
in the amount of $79,642, calculated on the basis of
1% of the first $200,000 and 2% on the remainder of
the $4,082,115.) This sum would apply if the development
were able to proceed at once, but the land is not ripe
for immediate development.
5.4.8 Development Timing
and Discount Rate
Both appraisers apply a final discount
rate to their raw land values in order to arrive at
a present value for the property as at the valuation
date. Nilsen estimates that the development of the lands
would begin three years after the date of valuation,
and so applies his discount rate over a three year period.
He chooses a discount rate of 10%, which he explains
is based on the 15% current rate used for financing
at the time, less an allowance of around 5% per annum
for anticipated increases in lot values.
Davies uses a deferral period of
five years, as outlined in more detail in the section
of these reasons dealing with highest and best use.
He states that the pertinent financing rate would be
prime plus 1%, which would have amounted at the time
to 15.75%. From this percentage figure he deducts 8.4%
to account for anticipated appreciation of lot values
over the five year period. This calculation results
in the 7.35% effective rate which he applies.
We have already concluded that the
appropriate deferral period is three rather than five
years, in part because Davies arrives at his five year
conclusion by applying historical facts to his analysis
that were unavailable to anyone looking at the situation
at the valuation date. In determining the appropriate
discount rate Davies takes the same flawed approach.
He examines what actually happened to lot prices historically
after the valuation date, and uses this information
to arrive at the 8.4% which he deducts for appreciation
of lot values. He states in his report that "the actual
lot value changes calculate to approximately 8.4% per
annum..." We disagree with this approach for the same
reasons we disagreed with it in Davies' opinion regarding
the deferral period, and prefer Mr. Nilsen's deferral
period and discount rate which were arrived at without
the benefit of hindsight.
Before applying this discount, an
allowance must be made for property taxes during the
holding period, plus six months construction and one
year marketing. Davies makes such an allowance, whereas
Nilsen does not. At $381.44 per acre according to Davies,
property taxes over 4.5 years of $9,750 per acre at
15% represents an allowance of $30,345. The net value
before discount is therefore $4,051,771.
5.4.9 Present Value
Before Taking
Applying the 10% discount rate over
a three year period to the $4,051,771 net value results
in a present value before the taking, as at the valuation
date, of $3,042,879.
5.5 Market Value After
the Taking
The after taking values flow from
the before taking determinations, since all of the assumptions
remain the same. Merely the mathematical calculations
differ, as the result of the loss of the seven lots.
The following chart shows both the before and after
figures, as well as our determination of the loss figure
based on these calculations. We have arrived at a before
taking value of $3,042,879, and an after taking value
of $2,673,873, which results in a loss of $368,906.
| BOARD CONCLUSIONS |
Before |
After |
| # of lots |
107 |
100 |
| Times: $ per lot |
$105,000 |
$105,000 |
| Equals: total gross revenue |
$11,235,000 |
$10,500,000 |
| Less: developer's profit
(20% gross) |
$2,247,000 |
$2,100,000 |
| Less: sales commission
(3% gross) |
$337,050 |
$315,050 |
| Equals: remaining revenue |
$8,650,950 |
$8,085,000 |
| Less: development costs |
$4,130,204 |
$4,093,269 |
| Less: financing on development
costs (3 months @ 15%) |
$154,883 |
$154,496 |
| Less: park allowance @
5% |
$204,106 |
$179,450 |
| Less: property transfer
tax |
$79,642 |
$69,780 |
| Equals: residual land value upon
commencement of development |
$4,082,115 |
$3,589,005 |
Less: property taxes during holding period (15% for
4.5 years) |
$30,345 |
$28,455 |
| Equals: net value |
$4,051,771 |
$3,560,550 |
| Less: discount/deferral
(10% -- x .751) |
$1,008,892 |
$886,577 |
| Market Value |
$3,042,879 |
$2,673,973 |
|
Loss = Before less
After: $368,906 |
6. INTEREST
Interest flows on the board's award
of $368,906 under s.46(1) of the Act from May 25, 1990.
The advance payment of $342,000 constitutes about 92.7%
of the board's award of compensation, so additional
interest under s.46(4) may not be awarded. In accordance
with our earlier ruling regarding interest, set out
in the first part of these reasons, no interest will
run on the compensation award between October 16 and
December 16, 1996.
7. COSTS
The compensation award is approximately
108% of the advance payment. Under s.45(5) of the Act,
if the compensation awarded is 115% or less of the amount
of the advance payment, the board may award the owner
all or part of their costs. In this case, in light of
the substantial amounts being contested and the relative
complexity of the issues put forth, we award Double
Alpha its actual reasonable legal, appraisal and other
costs necessarily incurred for the purpose of asserting
its claim for compensation.
THEREFORE IT IS ORDERED THAT
Centra shall pay to Double Alpha:
| (1) |
Compensation pursuant
to s. 30 and s.40 for the market value of the land
expropriated and the loss in value to the remaining
land of $368,906; |
| (2) |
Interest pursuant to
s.46(1) of the Act from May 25, 1990, until paid,
with appropriate adjustments to take into account
moneys paid from time to time by Centra to Double
Alpha, and excluding the period between October
16 and December 16, 1996. Pursuant to s.45(2) of
the Act, interest shall be calculated at the following
rates: |
|
(a) |
Thirteen and one-quarter per
cent (13.25%) from May 25, 1990 to June 30, 1990; |
|
(b) |
Fourteen and three-quarters per
cent (14.75%) from July 1, 1990 to December 31,
1990; |
|
(c) |
Twelve and three-quarters per
cent (12.75%) from January 1, 1991 to June 30, 1991; |
|
(d) |
Nine and three-quarters per cent
(9.75%) from July 1, 1991 to December 31, 1991; |
|
(e) |
Eight per cent (8.00%) from January
1, 1992 to June 30, 1992; |
|
(f) |
Seven per cent (7.00%) from July
1, 1992 to December 31, 1992; |
|
(g) |
Seven and one-quarter per cent
(7.25%) from January 1, 1993 to June 30, 1993; |
|
(h) |
Six per cent (6.00%) from July
1, 1993 to December 31, 1993; |
|
(i) |
Five and one-half per cent (5.50%)
from January 1, 1994 to June 30, 1994; |
|
(j) |
Eight per cent (8.00%) from July
1, 1994, to June 30, 1995; |
|
(k) |
Eight and three-quarters per
cent (8.75%) from July 1, 1995, to December 31,
1995; |
|
(l) |
Seven and one-half per cent (7.5%)
from January 1, 1996, to June 30, 1996; and |
|
(m) |
Six and one-half per cent (6.5%)
from July 1, 1996, to October 16, 1996 and from
December 16, 1996, to December 31, 1996; |
|
(n) |
Four and three-quarters per cent
(4.75%) from January 1, 1997 to December 31, 1997; |
|
(o) |
Six per cent (6.00%) from January
1, 1998 to June 30, 1998. |
|
(p) |
Six and one-half per cent (6.5%)
from July 1, 1998 to December 31, 1998. |
| (3) |
The actual reasonable
legal, appraisal and other costs necessarily incurred
by Double Alpha for the purpose of asserting its
claims in these proceedings in such amount as may
be agreed upon, and failing such agreement, in such
amount as may, upon application to the board, subsequently
be determined and allowed by the chair. |
|