| October 2, 1998, E.C.B. No. 54/91/162
(65 L.C.R. 139)
| Between: | Seaside
Acres Ltd. Claimant | | And: | Centra
Gas British Columbia Inc. (Formerly Pacific Coast Energy Corporation) Respondent |
| Before: | Julian
K. Greenwood, Panel Chair Suzanne K. Wiltshire, Board Member Art Guthrie,
Board Member | | Appearances: | William
A. Scott, For the Claimant Robert J. McDonell, For the Respondent |
REASONS FOR DECISION
1. INTRODUCTION On September 19,
1990, the respondent took a statutory right of way ("SRW") over the claimant's
property, for the purpose of a buried natural gas pipeline. The SRW was in total
about 2,600 feet (790 m.) long, and for most of its length 40 feet (12.2 m) wide.
It comprised 2.47 acres (just under 1 ha.). The claimant's
property was a vacant land parcel of some 55 acres, rising up the side of a fairly
steep hill on the south side of Ladysmith, Vancouver Island. It was described
as a "hooked" parcel, divided into two parts by a B.C. Hydro transmission line
right of way, owned in fee by B.C. Hydro. A 46.05 acre portion of the property
lay to the southwest (uphill side) of this Hydro strip. It was approximately triangular
in shape, with the Hydro strip forming the long side of the triangle. It rose
fairly steeply from the Hydro strip to the top of the hill, and was "flattest"
in the area of the Hydro strip. The respondent's SRW was taken from the edge of
this 46.05 acre portion, alongside the Hydro strip. The zoning on this portion
of the property, both at the time of taking and at the time of hearing 8 years
later, was an "urban rural residential" zone permitting single family lots of
a minimum size of 7,190 square feet or 668 square metres.
The balance of the claimant's property, on the northeast (downhill side) of the
Hydro strip, was unaffected. That part of the property was subsequently developed
as a residential subdivision backing onto the Hydro transmission lines and adjoining
other residential developments. Views from these developed lots to the east and
north-east could be spectacular, looking over the Strait of Juan de Fuca, Texada
Island, and beyond. The Hydro right of way formed a barrier
which had, up to the time in question, effectively prevented further development
of the 46.05 acre portion "behind" the transmission lines. Nevertheless the claimant
put to the board a theory of value which presumed the property would be further
developed with single-family residential lots. A claim that it should be valued
as a multi-family site was abandoned at the hearing. Only a 15 acre area alongside
the Hydro right of way was said to be economic for development in the near term,
because the rest of the property was so steep. The respondent's SRW lay in that
developable area. The claim was that the SRW reduced the number of lots which
could be developed, and hence caused a loss in value. The
respondent, by contrast, argued that its SRW had no significant effect on the
development potential of the 46.05 acre portion. It submitted firstly that the
property was not ripe for development in any event, given the very high development
costs for this site and modest market of 1990-91. Even if one did attempt a development
analysis, the SRW would lie over "back yards" in any future subdivision, and would
not seriously impair the ability to build on lots, nor would it affect the number
of lots which could be reasonably obtained. Much of the hearing time was occupied
with discussions of the development potential of the property.
Because the respondent doubted that development of the 46.05 acre portion was
realistic in the early 1990's, it argued that the property could be more realistically
valued by comparison with sales of other acreage parcels with a low development
potential. The difference of opinion presented to the board
was striking. The respondent said the market value of the SRW taken was nominal
-- $1,000, and that there was no reduction in market value to the remainder. Since
the claimant had already received an advance payment of $4,590, nothing more could
be owing. The claimant, on the other hand, said that the real loss was to the
remainder of its land. It argued it had lost development potential worth about
$183,000. In addition, the claimant sought extra costs of access, which it said
would be incurred in building special crossings over the respondent's right of
way. It also sought compensation for "executive time" spent dealing with the expropriation;
and of course it sought interest and costs. A claim for special economic advantage,
although discussed in the materials, was not pursued at the hearing.
2. CLAIMANT'S EVIDENCE The evidence
presented to the board to support the claims was regrettably weak in places. No
evidence at all was presented to support the claims for executive time and for
crossing costs, with the result that the board has had to reject those claims.
The claims for market value of the land taken, and for reduction
in market value to the remainder, were supported first by the evidence of Mr.
Hugh Ney, one of the principals of the claimant. Mr. Ney had a background in engineering
and development, but was not presented as an expert witness. He testified first
as to the history of the property. It had been in his family (through holding
companies) for many years. In 1988 the owner was under some financial pressure,
and was persuaded by its banker to reduce its debt. In response to this pressure,
Mr. Ney found some other investors, and with their help arranged for the present
claimant to purchase the entire 55 acre parcel for $42,000. Mr. Ney was a principal
of the companies on both sides of the transaction. Given these circumstances,
the claimant argued that the 1988 sale should not be considered an arms' length
market sale, and should be ignored in a valuation of the property.
Mr. Ney also testified as to the development of the property. The 9 acres below
the Hydro transmission lines were developed in two stages in the 1990's. Mr. Ney
had been responsible for development layouts. A preliminary layout approval ("PLA")
supporting the 9 acre development had been received in June 1991 (a year after
the taking). The plan underlying this PLA included a conceptual layout for a large
number of lots (well over 100) for both single-family and multi-family residences
on the rear 46.05 acres; however there was no suggestion in the evidence that
these rear lots were to be developed at the time, or that the sketched layout
was anything more than a concept. Much would have to be done, including possible
rezoning, engineering and cost feasibility studies, and the obtaining of regulatory
approvals for the detailed designs. The only work actually proceeded with was
the development of the lower 9 acres below the Hydro lines.
Nevertheless, Mr. Ney testified that the claimant's longer term plans included
continuing development up the hill, as circumstances permitted. Thus, to support
the claimant's contention that development behind the Hydro lines was impaired
by the respondent's pipeline and SRW, he submitted various conceptual plans for
such further development. Again, Mr. Ney had been responsible for the key development
layouts presented to the board. He had worked with an engineer (Rodney Smith)
to determine the boundaries of practical development by reference to the topography,
and had sketched conceptual layouts for single family lots and roads within that
boundary. He had retained a B.C. Land Surveyor (Thomas Hoyt) to draw the lots,
but Mr. Hoyt did little more than apply the concepts supplied to him by Mr. Ney,
ensuring that the zoning requirements for minimum dimensions and areas were satisfied.
The result of this work was presented to the board as two
plans -- one for 77 lots which assumed that the SRW was not a factor (a "before"
layout), and another for 71 lots which took into account the presence of the SRW
and a gas pipeline (an "after" layout). Thus, the claimant argued that the gas
pipeline SRW had the effect of removing 6 potential development lots.
The engineer Rodney Smith also testified. He had estimated some of the costs of
development of these two hypothetical subdivisions. Unfortunately it became clear
that his work did not include all the development costs. Potentially substantial
amounts for off-site development, survey, legal and management costs, taxes, the
costs of providing double services (something he considered a necessary consequence
of the steep topography), and the cost of land preparation, were omitted entirely.
Mr. Smith's additional contribution was to explain to the
board in a general way why the gas pipeline SRW might reduce the development yield.
Since the development would be on a hillside, with a road running across the hill
parallel with the Hydro and gas rights of way, there would be housing both below
and above the development road. Water and sewer services to the houses below the
road would, in Mr. Smith's view, most likely be run through the back yards of
those downhill lots, while services to the uphill lots would run in the road allowance.
The alternative of placing all services in the road allowance would require a
very deep trench if it were to be able to handle runoff from the lower lots.
Mr. Smith observed that backyard servicing to the lower lots would have been placed
alongside the Hydro property, except that the gas SRW was now occupying that area.
The result, he argued, was that the hypothetical development would have to be
shifted uphill by the width of the gas SRW (mostly 12 metres). He also assumed
that fill to cover these utility lines and to flatten the lower lots could not
be placed on the gas SRW. These factors reduced the land practically available
for development, and hence the number of lots which could be created.
In making these comments Mr. Smith conceded he was speaking generically, and that
his comments did not relate specifically to the two plans put forward by Mr. Ney.
Mr. Smith had not been asked to provide his engineering expertise to prove the
feasibility of Mr. Ney's layouts and their likelihood of compliance with all local
requirements. Also, it appeared from his evidence that there were various ways
of servicing lots, and the exact choice would depend on a number of factors which
had not been determined for the subject property. Mr. Hans
Heringa, another principal of the claimant and a contractor and developer by occupation,
provided his own "ballpark" estimates, done in the fall of 1991, of what a development
of the entire 46.05 acres might have cost assuming yet other layouts. Like Mr.
Ney, Mr. Heringa did not testify as an expert, nor were the 129 lot or 140 lot
plans on which he had based his costing ever shown to have been feasible from
an engineering viewpoint. In view of the evidence in the hearing as to the very
steep topography prevailing over much of the site, the board concluded that Mr.
Heringa's development assumptions were never more than speculative.
Overall, the claimant's evidence for loss in market value to the remainder was
weak. As mentioned above, it was based on the difference between anticipated developments
of the land behind the Hydro strip "before" and "after" the SRW. However the board
could not place much faith in the layouts suggested by Mr. Ney. Proposed development
plans which are not proven through proper experts to be both feasible and optimal
are of little use to the board. Without such support they are just speculations
as to what might be possible. In this case there was no professional planning
opinion presented by the claimant to support Mr. Ney's plans. Mr. Smith and Mr.
Hoyt may together have had the necessary expertise, but they were not asked to
be responsible for the layouts chosen. Their assignments were limited to other
matters. The board also observed that all of the claimant's
various predictions as to the development prospects and costs were made after
the SRW was an accomplished fact and the expropriation claim was under way. There
was some evidence that the development plans may have been chosen more to advance
the compensation claim than to support actual development in the near future.
This factor, together with the apparent multiplicity of different conceptual layouts,
none of which had been studied in detail, made the board somewhat cautious about
accepting the claimant's development predictions. In addition,
the cost information presented by the claimants was either incomplete or was not
related to Mr. Ney's plans except in a general way. Thus, the foundation evidence
for a claim of loss in market value to the remainder was lacking.
Unfortunately, this evidence was then fed to the claimant's appraiser, Mr. Vic
Sweett, who adopted it without change. Mr. Sweett presented an appraisal report
which assumed the number of development lots would decline, because of the SRW,
from 77 to 71, and that the costs of development would be simply those estimated
by Mr. Smith. He did not do any independent verification of these base assumptions.
In general his report lacked the kind of objective, skilled and independent testing
of the evidence which one hopes to receive from an expert witness. These are the
factors which make opinion evidence useful; without such objectivity, so-called
"expert" evidence can become mere advocacy. Mr. Sweett calculated a "value of
compensation due" of about $183,000 based largely on the claimant's assumptions;
but the board could not give his valuation any weight, when its inherent frailties
were understood. Although Mr. Sweett also developed some
market value evidence based on acreage parcels, his use of this evidence seemed
somewhat cavalier. For example, having given the opinion that only 15 acres of
the "back" portion of the property were currently developable, he nevertheless
proposed that the remaining (undevelopable) acreage be valued at $7,500 per acre,
a figure which was drawn from properties with access and some current development
potential. The more appropriate data from his own report indicated a value of
$3,000 per acre or less, as he conceded in cross-examination.
3. RESPONDENT'S EVIDENCE The first
witness for the respondent was James Fraser, a pipeline technician, who advised
the board that in practice the respondent did not prevent surface owners from
placing fill over its pipeline rights of way. This evidence removed an important
assumption inherent in some of Mr. Smith's testimony that because one could not
place fill over the SRW any practical development would have to be shifted uphill
by the full width of the SRW. Claimant's counsel conceded that Mr. Fraser's evidence
eliminated that particular argument. The respondent's value
evidence rested primarily on an appraisal report by Brian K. Davies of Interwest
Property Services (1991) Ltd. Like the claimant, Mr. Davies concentrated on the
"rear" 46.05 acres and valued this as if it were a separate parcel, to see whether
the SRW had affected that value. He presented both a market comparison approach
based on acreage parcels and also a subdivision development approach. However
he concluded that subdivision was not economic in 1990/91, and hence that any
value had to be found from the market evidence. Mr. Davies'
development approach was in turn based on the evidence of two other witnesses,
both of whom were qualified before the board as experts in their areas.
Mr. Slade Dyer, a qualified planner, presented his view of the most likely development.
He showed that except for some 15 acres nearest the Hydro lines, the balance of
the property was too steep for practical development. (It is interesting that
although the claimant did not concede this point, the actual development layouts
presented by the claimant for this hearing occupied much the same 15 acres.) Mr.
Dyer then presented his layouts of the 15 acre "developable" portion nearest the
Hydro lines. He thought that one could create either 62 fee simple lots, or 69
bare land strata lots, and that the number of lots would be the same whether or
not the SRW was considered. In other words he did not see the SRW as having any
effect on the development potential of the property. It would lie within "back
yards" of the affected lots. Although it would theoretically affect the amount
of available building land on those lots, they were in general large enough that
no lot would be rendered unusable. Donald Bowins, a civil
engineer, provided the board with his opinion as to the costs of development of
Mr. Dyer's 62 or 69 lot layouts. He concluded almost $1.5 million for the 69 lot
strata subdivision, and about $1.9 million for the fee simple layout. Although
these figures were necessarily preliminary (no detailed engineering study having
been done by any party), the same criticism was equally applicable to the claimant's
cost figures. On balance it appeared to the board that Mr. Bowins' cost estimates
were more thoroughly considered and more inclusive, and should be given greater
weight. The appraiser Mr. Davies then applied these cost
estimates in looking at the viability of either of these two subdivisions. It
was his view, based on market data, that lots would have been worth $26,000 each
at the relevant time, whether fee simple lots or strata lots. (The board noted
that this was similar to Mr. Sweett's estimate of $27,000 per lot). Mr. Davies
anticipated a development time frame of about 11 years, consisting of a four-year
holding period, one year for initial construction and rezoning, and about 6 years
to sell the resulting lots at a rate of about 10 per year. With this background
he prepared discounted cash flow spreadsheets from which he concluded that the
net present value of development, seen from the beginning of the marketing period,
was negative in each of the scenarios. In short, it was his view that the property
was simply not "ripe" for development, and would not become so until lot values
had risen considerably. That being his opinion, Mr. Davies
valued the land using comparative data from the sales of large acreages in the
area. His data, after adjustments for time to the relevant date of September 1990,
showed values from other properties ranging from about $1,600 per acre to about
$7,500 per acre. Generally the higher values were achieved by properties with
more imminent development prospects. The particular sale that resulted in almost
$7,500 per acre was a 14.5 acre parcel immediately south of the subject, on the
downhill "developable" side of the Hydro lines. Mr. Davies therefore saw this
as the best comparable to the equivalent portion of the subject - namely the 9
acre developable (and now developed) portion below the Hydro strip, which was
unaffected by the SRW. Mr. Davies also included in his comparisons
the 1988 sale of the subject parcel at $42,000. Even after adjustment for time
this comparison gave the lowest acreage rate of all his comparisons at $1,116
per acre. He argued that this could be considered an "arms' length" sale and hence
a valid indicator. It essentially showed that very little money was paid for the
property up the hill behind the Hydro transmission lines; all the value was in
the 9 acres below. Mr. Davies' final use of the data was
unusual. He chose not to use the $7,500 figure, and instead selected a mid-range
$5,500 per acre which he applied to the lower 9 acres. He then took his time-adjusted
figure from the 1988 sale of the subject, and subtracted the value he had arrived
at for the developable 9 acres, to conclude that the entire 46.05 acres behind
the Hydro lines was worth only the residual of $12,000. This approach therefore
relied crucially on the actual sale of the subject in 1988.
Finally, Mr. Davies came to value the SRW itself. He surmised that the entire
value of the back 46.05 acres in fact lay in the lower 15 acres which the planner
had seen as the only practical area for development. The right of way itself was
2.47 acres, or about 1/6 of that area. By simple proportion, he concluded $2,000
for the fee simple value of the land in the SRW. Finally,
Mr. Davies suggested that since all that was taken was a right-of-way, the actual
value of what was lost should be no greater than half of the fee simple value.
He assigned a nominal value of $1,000 to the market value of the interest in land
taken, and found no loss of value to the remainder. 4.
DISCUSSION The substantial issue before the board was
whether there was a loss in value to the remainder of the land, after the partial
taking of the SRW. The actual value of the interest in land taken was comparatively
small. The parties diverged widely, however, on whether the taking affected the
development potential of the remainder of the property. The
claimant attempted to show a substantial loss by a "before and after" approach,
comparing the development possibilities with and without the SRW and gas pipeline
in place. This would give a combined number for the market value of the land taken
and the loss in market value to the remainder. However, the board has not been
persuaded that in this case the taking of the SRW and the placing of a gas pipeline
alongside the Hydro property would make any difference to the development potential
of the remainder of the property. The board also concluded (see below) that the
development approach was not appropriate in this case. Therefore the board concludes
there was no effect on the market value of the remainder.
The board agrees with the respondent that the prospects for development of any
part of this property behind (uphill from) the B.C. Hydro property were speculative
and remote in late 1990. The most reliable evidence from both parties has convinced
the board that the time was not right. Lot values would have had to rise considerably
from the then prevailing levels of some $26,000 or $27,000 before development
would be feasible on that difficult terrain. In addition there was the unknown
cost of obtaining access across the Hydro property. Two entrances were needed
before development would happen. Although witnesses assumed Hydro would grant
access, the price was simply unknown. Orally, B.C. Hydro personnel had suggested
various negotiating positions from which Mr. Bowins, for example, had concluded
that the cost might be as high as $75,000. Boards have held
in the past that the development approach is to be avoided if development was
too remote a prospect or if there were too many unknowns. An example is Eddy
v. Minister of Transportation and Communications [1974] 7 L.C.R. 120 (Ont.
L.C.B.). The board agrees that this is sensible advice, and therefore prefers
to arrive at a value for the interest in land taken from the market comparison
data. However in the present case the market data itself
is difficult to use, because the subject property is unlike any of the other comparables,
having the combined difficulties (for most of its area) of very steep topography
and no enforceable access. The only "comparable" which has the same difficulties
is the 1988 sale of the subject itself, but that sale has problems of its own.
Not only was it somewhat old requiring a two-year time adjustment, but the particular
circumstances of the sale raise doubts. The fact that there was some financial
pressure and that at least one party appeared on both "sides" of the transaction,
suggest to the board that the transaction is an unreliable guide to the value
of the subject land in September 1990. The board is in the
position of having to do the best that it can with the market data available from
both parties. Although most of Mr. Sweett's comparables were smaller multi-family
properties, three are of interest. Sales number 10, 11 and 14 are larger parcels.
All three have views, none of them appear to have access problems, and it would
appear that sales 11 and 14 could expect higher densities of development once
sewer access was available. These comparables suggest values of between $3,000
and $5,000 per acre after adjustments. Mr. Davies' comparables
are of limited use since he did not complete a full direct comparison approach
by making all the usual adjustments for size, development potential, and the like.
Indeed he testified that he found none of his comparables had the topographical
or access problems of the subject; in that sense they were not comparable. However
he observed that some had similarly important restrictions on development through
restrictive zoning or location in the Agircultural Land Reserve.
If one looks primarily to development density potential as a basis for choosing
from among Mr. Davies' comparables, then the two best seem to be numbers 4 (700
sq.m. lots) and 9 (600 sq.m. lots). These lead to time adjusted values around
$4,300 per acre and $5,700 per acre respectively. The board
has decided that given all the uncertainties a reasonable value to apply to the
area of the SRW is $4,000 per acre. When this is multiplied by the 2.47 acres
it indicates a fee simple value of $9,880. The board agrees with the respondent
that the claimant has not in fact lost the full use of the area, and adopts the
respondent's suggestion that the actual loss be valued at about 50% of the fee
simple value. A strict 50% would be $4,940, but the board notes that the advance
payment of $4,590 is close to this figure, and within the range of reasonable
estimation of value. The board thus finds that the value of the interest in land
taken was $4,590, which is equal to the advance payment. No loss in value to the
remainder of the property has been proved. There being no
evidence of the other items of loss claimed, including executive time and the
cost of building access across the SRW, these claims must also fail.
5. DECISION The board finds that
the market value of the land taken is $4,590, and that there is no loss in value
to the remainder. Claims for disturbance damages or personal or business loss
fail for lack of evidence. Since the claimant received an advance payment of $4,590
at the time of the taking, the advance payment was correct, and therefore all
claims for further compensation are dismissed. The claimant
will have its actual reasonable legal, appraisal and other costs as determined
by the Chair under the Expropriation Act. The board recognizes its discretion
to award only partial costs in these circumstances, but has chosen not to exercise
it. |