| June 4, 2002, E.C.B. No.
74/92/221; 48/96/221
| Between: | Whitechapel
Estates Ltd. Piccadilly Estates Ltd. Delsom Estates Ltd. and Norman Dennis
Elsom Claimants | | And: |
The Ministry of Transportation and Highways Respondents | | Before: | Sharon
I. Walls, Vice Chair Martin A. Linsley, FCAA, FCIP, CBV Azim S.M. Jamal,
AACI, P.App, FRICS, RI(BC) | | Appearances: | David
H. Goodwin, Counsel for the Corporate Claimants N. Dennis Elsom, In Person Alan
V.W. Hincks, Counsel for the Respondent |
REASONS FOR DECISION 1.
INTRODUCTION [1] The four claimants owned 19 separate
but contiguous parcels of developable property in Delta, British Columbia occupying
approximately 60 hectares (147 acres). The claimant, Dennis Elsom, owned the majority
of the lots. The claimant, Whitechapel Estates Ltd., owned one lot, the claimant,
Piccadilly Estates Ltd., owned one lot, and the claimant, Delsom Estates Ltd.,
owned two lots. Mr. Elsom was the principal of the three corporate claimants.
Thus there were four owners of the 19 legal lots but there was one controlling
mind and the 19 lots could be said to have common ownership. [2]
The respondent, the Ministry of Transportation and Highways (the "Ministry")
required approximately 4.5 hectares (11 acres) of the subject property for the
construction of a connector route to the new Alex Fraser Bridge. The connector
route was called Nordel Way and part of the taking was for an additional access
road to Nordel Way called the 84th Avenue connector. The construction of Nordel
Way and the 84th Avenue connector and other ancillary works by the Ministry is
collectively termed the "Project". The date of taking was May 30, 1985.
This date precedes the original enactment of the Expropriation Act, R.S.B.C.
1996, c. 125 ("the Act") in 1987. The land for the Project was taken
from 11 of the total of 19 parcels of the subject property. The land was taken
by Gazette Notices under the legislation preceding the Act. [3]
One of the claimants also owned three lots of ravine land that were separate from
and to the east of the main body of development land. At the same time as the
main taking the Ministry also took 1.32 hectares (3.27 acres) from two of these
lots. The claim for compensation related to the ravine land is very small and
will be dealt with separately below. [4] The Ministry paid
the claimants $1,018,936 on July 4, 1986 and $781,064 on April 21, 1988. The takings
occurred prior to the Act coming into effect and no appraisals accompanied these
payments. Some of this money was attributed by the Ministry to compensation for
the land taken, some to injurious affection to the remainder, some to interest,
and some to work done by the claimants on the property. However, since none of
these issues has been settled, the board must decide how much should be awarded
under each head of compensation. As a result we disregard the allocations that
were made and treat both cheques as general advance payments. [5]
Prior to the taking, in June 1984, the claimants were consulted about possible
options for the taking through the subject property. Mr. Elsom advised the Ministry
of the route that he favoured and he was provided with detailed engineering plans.
He met and corresponded with the Ministry on a number of occasions both before
and after the taking about various details of the Project. Prior to the
taking the claimants on their own initiative cleared and excavated the route of
Nordel Way through the subject property. The material from the excavated route
was used to construct berms in certain areas beside the right of way. It was hoped
that these berms would mitigate the effect of the noise on the eventual subdivision
development. The claimants have submitted a bill for the clearing and excavation
work to the Ministry. [6] In late August 1995 the Ministry
took further land bordering Nordel Way to include the embankment created by the
claimants at the time of the first taking. The narrow strips taken at this time
went to the top of the embankments in certain areas and totalled approximately
0.6 hectares (1.4 acres). On October 11, 1995, the Ministry served the claimants
with an appraisal report with respect to the second taking that stated that the
1.4 acres had no value. The Ministry also made an advance payment to the claimants
of nil dollars on the same date for this second taking. [7]
The claimants commenced two applications to determine compensation. The first,
74/92, was to do with the first taking in 1985. The second, 48/96, was to do with
the second taking in September 1995. [8] The hearing occupied
a total of 30 days including argument. There were over eighteen days of expert
evidence including more than ten days of appraisal evidence and six days of engineering
evidence. There were 130 exhibits, many of them voluminous. Since it was alleged
that as a result of the Project, development was delayed for up to 20 years, there
were many volumes of subdivision applications, minutes, reports and correspondence
that had to be reviewed. Counsel for the claimants observed in his submissions:
"The Board is left with the onerous task of reviewing a massive amount of
evidence. Unfortunately, the task has not been simplified as it might have been
by either of the appraisers [whose] task it was to assemble, analyze and provide
opinions of value." Although the partial taking from such a large property
raises a number of issues, we agree with the comments of this board in Casamiro
Resource Corp v British Columbia (1993), 50 L.C.R. 99 (B.C.E.C.B.) at p. 105
"[b]y way of comment only the board is of the opinion that had [the claimants
maintained] a better focus on the relevant issues and the compensation provisions
of the Expropriation Act, more could have been achieved in substantially less
time." 2.
THE COMPENSATION CLAIMED [9] Several of the claims
for compensation changed during the hearing but counsel on behalf of the corporate
claimants made the following claims during final argument:
| (a) |
Market value of the 11.27 acres taken in 1985 at $160,000/acre |
$ 1,803,840 | | (b) |
Injurious affection or disturbance damages: | | | • |
reduced lot yield for (87 lots x $40,000/lot) - $1,803,840 |
$ 1,676,150 | | • |
net increase in servicing costs as amended* | | | with
respect to site layouts and storm sewer |
$ 110,000 | | | for
extra items such as street lights on Nordel Way |
$ 519,000 | | • |
noise | |
$ 1,257,600 | | • |
constructing overpass bridge /development cost charges | |
$ 1,400,000 | | • |
executive time | |
$ 500,000 | | • |
extra engineering costs | |
$ 220,000 | | (c) |
Market value of the 3.2 acres of ravine lands taken in 1985 |
$ 15,000 | | (d) |
Market value of the 1.4 acres taken in 1995 |
$ 411,000 | | (e) |
Reduction in market value for sewer right of way |
undetermined | | (f) |
Damages for delay | $5,500,000
to $69,000,000 | |
(g) | Cost of holding the
property | $ 622,095 |
| Total |
approximately $14,000,000 -$77,500,000 | |
*as amended in argument with corrections as set out in the most recent amendment
from the expert. | This
claim was framed as a general claim on behalf of all the claimants with no allocation
amongst particular claimants. [10] Some of the above claims
overlapped and some were made in the alternative. Not all of these claims were
consistent with the opinions of the appraiser and the engineer who were called
by the claimants. Claims for constructing the berms and miscellaneous expense
invoices from the planner, surveyor etc. were adjourned at this time because it
was hoped that these items could be agreed and in any event we did not have all
of the evidence in relation to these claims. The claimants also sought an adjournment
of the claim for any extra costs that might be imposed when development of the
subject lands finally occurs as a result of the Corporation of Delta not approving
the service connections under Nordel Way. While we do not wish to encourage a
piecemeal approach to seeking compensation we adjourn these claims at this time. [11]
While counsel drafted the pleadings and provided an overall approach with respect
to the evidence and argument, Mr. Elsom chose to represent himself as the owner
of 15 lots in his personal capacity. He was provided with considerable latitude
during the hearing. Counsel purported to represent the corporate claimants only.
At the conclusion of the evidence Mr. Elsom made a somewhat different claim than
counsel for the corporate claimants:
| (a) |
Market value of the 11.46 acres taken in 1985 at $160,000/acre |
$ 1,833,600 | | (b) |
Delay claim for Phase 1 - Doncaster 10 acres
delayed for 3 years (Jun 1983 to Jun 1986) |
$2,640,000 | | (c) |
Delay claim for Phase 2 - Harrogate 12 acres
delayed for 4 years (Jun 1985 to Jul 1989) |
$4,454,400 | | Total | $8,928,000 |
Mr. Elsom also
provided interest calculations with respect to the dates of the advance payments.
The issue of interest was adjourned by agreement. In the circumstances, we will
not restrict Mr. Elsom's claim to what he put forward in argument and will assume
counsel for the corporate claimants' submissions apply equally to Mr. Elsom's
properties. 3.
THE ISSUES [12] The primary issues in this complex
case, the specific details of which will be explained in the course of these reasons,
were as follows:
| Highest and Best Use |
| 1. |
What is the highest and best use of the property before and after the taking?
(a) Should the subject property be valued as 19 separate lots or as a whole with
one overall plan? (b) Should the subject property be valued on the basis of development
for single family residential only or on the basis of mixed use, that is primarily
single family residential but also including some multi-family and some commercial
use? | | Market Value
of the Subject Property Before and After the Taking |
| 2. |
What are the appropriate approaches to valuation of the impact of the taking on
the market value of the subject property? | | 3. |
With respect to the layouts for the subject property: | |
(a) | should they include a park? |
|
(b) | should they include residential
lots that are 60 feet wide or 66 feet wide? | | (c) |
if they contain multi-family and commercial, how many acres of each should they
contain? | |
(d) | how many residential lots should
they contain? | | | • Should
there be some allowance for Browning Drive in the before scenario? |
| | • Should
a road exchange for the unopened 104th Avenue be assumed in the before scenario? |
| 4. |
How long should valuation of lots be deferred to provide for time to obtain approvals
and what should the discount rate be? | | 5. |
Should there be an adjustment for lot size? | |
6. | What type of adjustment
should there be for easements? For size of the entire subject property? |
| 7. |
After the taking, is it appropriate that the layout incorporates a gas station
commercial site at the intersection of Nordel Way and the 84th Avenue connector? |
| 8. |
After the taking, what type of adjustment should there be for noise? For servicing
and other engineering works, including the overpass? | | Market
Value of other Takings | | 9. |
What is the market value of the taking from the ravine property? |
| 10. |
What is the market value, if any, of the second taking from the subject property? |
| • What
is the effect of Nordel Way on market value? | | • What
is the date of valuation for the second taking? | | 11. |
What is the market value of the taking for the sewer easement from Lot 112? |
| Disturbance Damages |
| 12. |
Did the Project cause delay in the development of the subject property and, if
so, to what damages are the claimants entitled? | | 13. |
Are the claimants entitled to disturbance damages for extra engineering services
incurred because of the Project? | | 14. |
Is Mr. Elsom entitled to disturbance damages for the loss of executive time? |
4.
FAMILY LAW DECISION [13] We note that the subject property
was valued as of the date of trial in a family law action that was heard in October
and December 1984, some six months prior to the valuation date in this matter,
May 30, 1985. See Elsom v. Elsom, [1985] W.D.F.L. 1578 (B.C.S.C.). The
Court of Appeal allowed Mr. Elsom's appeal on the distribution of assets between
the parties but dismissed his appeal on the valuation of the subject property.
See (1987), 13 R.F.L. (3d) 231 (B.C.C.A.). The Supreme Court of Canada allowed
Mrs. Elsom's appeal and restored the trial judge's division of property. See (1989),
20 R.F.L. (3d) 225 (S.C.C.). Locke J.'s valuation of the subject property was
of the whole property, including the part that was proposed to be taken within
the next year. Although some of the evidence from the appraisers in our hearing
appeared to overlap with that of the appraisers in the family law trial, we received
additional evidence that was not available to Locke J. In the circumstances, we
do not regard Locke J.'s evaluation as binding on us but nonetheless we find some
of the evidence reported in Locke J.'s decision of assistance. 5.
BACKGROUND 5.1 Neighbourhood [14]
The property is located in North Delta. During the 1960's and 1970's Delta had
grown faster than the Greater Vancouver Regional District as a whole. While the
population continued to grow, the growth rate slowed down in the 1980's. This
slowing of growth in Delta was attributed to four factors: less available land
in Delta, land in Surrey being available, the transportation system being overloaded
and the general slowdown in the economy. In 1985 the population of Delta was approximately
78,000 people, with North Delta being close to 45,000. [15]
North Delta was developed with primarily single-family homes (over 85% in 1985)
at a density of 4 to 8 units per acre. There were smaller houses in the older
1960's subdivisions and larger houses in the more recent subdivisions. Immediately
to the north of the subject property was the existing Sunbury neighbourhood while
to the south was the Canterbury Heights subdivision. Almost 60% of the houses
had been built between 1971 and 1981. There was commercial development along Scott
Road three miles to the east of the property. The population was largely young
families and participation in the work force was high. [16]
Prior to the taking, residents who needed to commute closer to the Vancouver area
had two main options for crossing the Fraser River: the Pattullo Bridge just east
of North Delta provided access to New Westminster, Burnaby and Port Coquitlam
while the George Massey Tunnel to the west provided access to Richmond and Vancouver.
However, to access the tunnel it was necessary to first drive south and west via
Highway 10 to reach Highway 99. This Tunnel route to downtown Vancouver was overcrowded
during rush hours by the early 1980's. In addition to these two routes, there
was a third crossing by the Port Mann Bridge further to the east. [17]
A fourth crossing from North Delta via Annacis Island was projected for some years,
at least from 1978. Access routes to what became the Alex Fraser Bridge and Highway
91 running south to Highway 10 remained uncertain in the early 1980's, but eventually
in 1984 several accesses were approved. One of these accesses was what became
Nordel Way and connected to 88th Avenue (and to 84th Avenue) through the subject
property. There was evidence that supported an increase in absorption rates and
lot prices following the completion of this new bridge link. 5.2
The Property [18] Mr. Elsom bought the 19 parcels that
make up the 147 acres of the subject property in the early 1950s. The parcels
generally form a large triangle bounded by 108th Street on the east (which is
not constructed throughout its length in the vicinity of the property), Dunlop
Road on the north-west, the closed 82nd Avenue for much of the southern boundary
and the Burlington Northern Railway for part of the western boundary. Before
the taking this triangle was bisected by 84th Avenue running from 108th Street
through to Dunlop Road. 84th Avenue was described by Mr. Blanchette, the appraiser
for the claimants, as a "major traffic route" and "a truck route
carrying high volumes of traffic" east and west through the subject property
before the taking. Many of the individual parcels border either side of 84th Avenue.
There were five parcels of land within the triangle that were owned by other owners
than the claimants, including a 2.5 acre site on Dunlop Road owned by the Delta
School Board. The engineer and planners included some of these parcels in the
site layouts showing proposed development before and after the
taking. This led to some difficulties in making comparisons, since the claimants
included only three of these other-owned parcels while the respondent included
all five. There were also problems with making comparisons for such items as the
number of lots or the servicing costs, that had initially been calculated on the
basis of different overall layouts with either three or five other properties,
and the subject property, which was smaller than either of them. [19]
As indicated above the subject property was approximately 147 acres. However,
the difficulties in reconciling the evidence began with establishing the size
of the subject property, the size of the taking, and the size of the remainder.
Mr. Buchan, the civil engineer retained by the claimants, reconciled three different
survey plans and calculated the total area of the subject property as 146.971
acres. His areas were also used by Mr. Blanchette, the appraiser for the claimants,
(at p 43 of his report, although at p 12 there is a typographical error leading
to a greater total). Ms. Watson, the appraiser for the Ministry, reported areas
by specified plan numbers and calculated the total area as 147.56 acres. The discrepancy
is minor and we accept the rounded number of 147 acres. Mr. Kruger, the engineer
for the Ministry, provided layouts based on plans originally obtained from Delta.
His total size for the subject property is somewhat greater. Mr. Jorden, the planner
for the respondent, used Mr. Kruger's size estimates. [20]
The property is relatively level bench land above an escarpment adjacent to the
Fraser River to the north. Gravel was extracted from the centre of the site at
one time and part of the old gravel pit is now a shallow man-made lake controlled
by a drainage system. The property rises to the east with some views to the north
and north-west. [21] At the time of the taking there was
a residence on the property, some storage sheds and some barns. There was also
a small office building. Both appraisers valued the property for development as
though vacant and unimproved, with the existing improvements contributing no value.
The property was zoned "RS 3 single-family 5 acres" north of 84th Avenue
and "I-3 Industrial extraction" south of 84th Avenue with a small area
zoned RS 3 single-family in the south-west corner. [22]
The subject property was encumbered by four major rights of way at the time of
taking. Again there are discrepancies in how these were described by Mr. Buchan,
the engineer for the claimants and Ms. Watson, the appraiser for the respondent.
(Mr. Blanchette, the appraiser for the claimants relied on Mr. Buchan's descriptions.)
Neither party provided the source documents, but Ms. Watson described each right
of way as it applied to each lot in considerably more detail than Mr. Buchan.
In the circumstances we accept the following descriptions. The most prominent
rights of way are those with overhead transmission lines. There is a British Columbia
Electric Company (now B.C. Hydro) right of way that runs diagonally across two
parcels in the north-east corner of the site with overhead transmission lines.
This right of way occupies 1.63 hectares (4.03 acres) according to Ms. Watson.
There is also an unused British Columbia Electric Company right of way that runs
diagonally across four parcels in the north-east corner of the site and ties in
to the first right of way. Ms. Watson states that this right of way occupies 2.0
hectares (4.94 acres) and that it was cancelled in 1988, after the date of valuation.
Running parallel to 108th Street near the eastern boundary is a BC Hydro right
of way for overhead transmission lines and two high-pressure gas pipelines. This
right of way intersects with the second right of way in the vicinity of 84th Avenue.
Ms. Watson says that 2.6 hectares (6.45 acres) are double encumbered with both
transmission lines and gas pipelines. One of the high-pressure gas pipelines turns
at the southern boundary of the subject property and extends west along the southern
boundary. It crosses 10 parcels and occupies a further 0.6 hectares (1.43 acres)
outside the area of the easement for electrical transmission lines. There is also
a closed road allowance along the southern boundary of the property that was vested
in Mr. Elsom and Delsom Estates subject to a right of way to BC Hydro for constructing
and maintaining a gas pipeline and another right of way to Delta for the existing
water mains, drainage sump and drainage ditch. The closed road added 33 feet along
the southern boundary but resulted in a 50-foot wide right of way. According to
Ms. Watson the vesting of the road allowance subject to the two rights of way
was ordered by the British Columbia Court of Appeal in November 1983 but the rights
of way were not formally registered until after the taking. She reports that these
rights of way occupy 1.97 acres. [23] Each of the rights
of way had their own contract provisions, but essentially no buildings could be
constructed on the rights of way and there was an ongoing right of access to the
right of way. Shrubs or trees that would interfere with the overhead electrical
lines could not be planted. The high-pressure gas pipelines did not permit sheds,
playhouses, decks, patios, or even roof overhangs and there were additional specifications
for roads and utilities that needed to cross these pipelines. [24] In addition
to these rights of way there were three rights of way for other services. One
of these was a right of way to the Greater Vancouver Regional District ("GVRD")
for the trunk watermain along the western boundary of Lot 112 and inside the two
British Columbia Electric Company rights of way described above. There was a second
right of way to Greater Vancouver Sewerage & Drainage District ("GVS&DD")
for a trunk sanitary sewer along the south-west boundary of Lots 112 and 666.
Finally, there was a storm and sanitary sewer right of way to Delta on Lot 666. 5.3
Economic climate [25] We were provided with evidence
as to the economic climate in the period leading up to the date of valuation.
The real estate market had peaked in early 1981 and then suffered a significant
decline of over 30% in terms of the average price of residential housing through
the remainder of 1981 and 1982. Average house prices in North Delta then stayed
more or less constant at this new lower level during 1983, 1984, and 1985. With
these lower prices, the number of sales in North Delta showed a marked increase
in 1982, followed by more modest increases in 1983 and 1985, and a small decrease
in 1984. The number of building permits for all residential housing in North Delta
fell from 1980 through until 1985 when there was some limited recovery. More generally,
1984 was one of the lowest years for housing starts in the previous 20 years.
In early 1985, both the number of house sales and the sale prices were down throughout
the Vancouver area, although there was some increase in the number of sales by
April. In March 1985, only 10% of builders reported that they were building on
a speculative basis. [26] In early 1985 British Columbia
had a low rate of economic growth. The unemployment rate in Vancouver in January
1985 was 13.9%, up from 12.9% a year earlier in January 1984. This compared with
a British Columbia rate of 15% and a national rate of 10.8%. The unemployment
rate in Vancouver rose each month from January through April 1985 when it stood
at 15%. Forecasters in May 1985 predicted that the unemployment rate in British
Columbia would remain at 15% for the rest of the year. Net migration to the province
remained low. In February 1985 the number of bankruptcies in British Columbia
was greater than in early 1984. [27] The Bank of Canada
bank rate varied between 9.7% and 11.18% during the first four months of 1985.
During early April the rate fell to 9.75% as of April 18, 1985, following which
it rose slightly for the next two weeks. One year mortgage rates varied between
11.25% and 12% falling to 10.5% on April 20, 1985. The Canadian dollar fell from
$0.75 to $0.71 during the first two months of 1985, rising in March, and falling
again to almost $0.73 in May. Although a number of indicators remained low, there
was optimism that the economy might improve somewhat. [28]
These economic factors had an impact on market valuation and the claim for damages
for delay. 5.4 Mr. Elsom's development
of other property [29] Mr. Elsom developed a number
of other properties in North Delta beginning in 1954. In more recent years he
subdivided the lots and installed the services and sold the individual subdivided
and serviced lots to one of a selected group of builders. Prior to any development
on the subject property Mr. Elsom and his companies developed a subdivision known
as Royal York. This was a 100 acre subdivision a few kilometres to the south of
the subject property that was developed in phases beginning in 1968. We heard
evidence from Eric Trygg, a realtor, who had worked with Mr. Elsom on a number
of subdivisions. We were provided with statements of adjustments and portions
of the interim agreements for the lot sales in the Royal York subdivision beginning
in 1982. These interim agreements with builders stated as one of the terms that
transfer of title to the purchaser will occur only when the purchaser has performed
all the terms and conditions of the contract and went on to provide there were
further terms and conditions on an Addendum A. However, we were not provided with
Addendum A. Mr. Trygg testified that Mr. Elsom did not pay any commission on the
sale of the lots, and Mr. Trygg obtained his commission on the eventual sale of
the lot with the residence on it by the builder. We also heard that Mr. Elsom
maintained control over the subdivision by inserting a term in the interim agreement
(presumably in the Addendum A) whereby he had to approve the design of any house
that was built. Many of these intermediary sales of lots to builders (before the
sale of the lot with a residence to the ultimate purchaser) were not registered
in the Land Title Office. [30] By January 1980 there were
66 unsold lots remaining in Royal York. The decline in the real estate market
in mid-1981 meant that no lots at all sold between August 1981 and May 1982. Thereafter,
the sales in each of 1982, 1983 and 1984 were only between six and eight lots
per year. The final eight lots were sold in 1985, with the last two not selling
until December 1985. [31] This evidence was important in
our consideration of the delay claim. 5.5
Land use planning regulations [32] We heard evidence
about the land use planning documents primarily from Michael Jorden, the planner
for the Ministry, and Mr. Dhillon, the planner retained by the claimants. This
evidence was relevant to the decision on highest and best use and the delay claim.
On May 30, 1985, Delta had a draft Official Community Plan ("OCP") 1978/1979
that governed its planning decisions. Delta was also working on the 1986 OCP and
issued a draft form for public feedback in May 1985. At the same time it was working
on a North Delta Area Plan. The 1978-79 draft OCP showed primarily single-family
residential on the subject property together with 15 acres of multi-family residential
and a new neighbourhood shopping centre in the area of the existing gravel pit.
There was also provision for both a new neighbourhood park and a new school site
on Dunlop Road, although the latter was not on the subject property as the School
Board already owned a 2.5 acre site on Dunlop Road. [33]
The new 1986 OCP was adopted in March 1986. The first draft of the OCP was mailed
out to the public in 1985 prior to the taking. The draft OCP received first and
second reading in September 1985, and third reading in January 1986, before it
was finally passed in March 1986. The new OCP contemplated a range of housing
types to provide for a variety of lifestyles. The first draft of the 1986 OCP
issued before the taking showed a significant amount of medium density residential
housing along 84th Avenue, including the subject property. However, as a result
of neighbourhood opposition the amount of medium density multiple-family housing
was scaled back considerably in the final OCP. Nonetheless there was still some
medium density multi-family residential housing located on the subject. The May
1985 draft OCP identified a new neighbourhood commercial site at the intersection
of Nordel Way and the 84th Avenue connector, and while this too was modified in
the final plan, neighbourhood commercial remained a designated use in this vicinity.
Both the draft and final OCP showed a community park in the middle of the subject
property south of 84th Avenue centred on the existing lake. More generally, the
OCP identified a desire for the development of pedestrian and bicycle trail systems.
The 2.5 acre school site on Dunlop Road was one of three sites considered surplus
and therefore available for sale. [34] The preliminary
draft of the North Delta Area Plan was issued in early 1986. There were several
drafts including ones in 1987, 1988, and 1993, culminating in the final North
Delta Area Plan that was passed and approved in 1995. The first draft in 1986
showed high density housing on the subject property at 75 units per hectare or
30 units per acre, centred on the existing lake. There was also a gas station
site identified on the subject at the intersection of Nordel Way and the 84th
Avenue connector. Later drafts in 1987 and 1988 continued to show primarily high
density multi-family together with some commercial and institutional use centred
on the lake. There was a stated need to provide a range of affordable housing
and smaller units for retirees. The 1993 draft of the North Delta Area Plan emphasized
the importance of a comprehensive development plan for the subject property in
order to plan road connections, circulation on the subject and the provision of
parks. A variety of housing densities continued to be suggested. The North Delta
Area Plan was finally adopted in 1995; it showed multi-family on most of the subject
property with single family residential only along the eastern and southern perimeters. [35]
The parks and recreation master plan in 1989 contained two goals affecting the
subject property. One of these was the development of a pedestrian and bicycle
trail system through the subject property along the B. C. Hydro right of way.
The second was the acquisition of 9.7 acres of the subject property for new playing
fields, next to the school property site, opposite the existing Sunbury Park on
Dunlop Road. 5.6 Dealings with
the subject property from 1978 to 1985 [36] Mr. Elsom
described his development work on the subject property and commented on the many
documents that related to this issue. Dr. Robert Collier, Municipal Administrator
for Delta from 1983 to 1995, was also called as a witness and provided evidence
with respect to the circumstances surrounding the claimants' efforts to develop
the subject property. In 1978 the claimants made an application for rezoning the
whole subject property with a comprehensive development plan prepared by Hanson-Erb.
This plan was a complex one with 415 single family lots around the perimeter,
and a 35 to 40 acre "village centre" that included a number of uses
such as commercial, public service, offices and multi-family, all centred on a
lake. A report from the Delta Planning Department dated August 16, 1979, recommended
refusal on two grounds: the application was premature because the proposed third
river crossing raised a number of unknowns and the application did not reflect
land uses in the Draft Delta Community Plan. On November 10, 1980 and again on
March 1, 1982 Delta Council refused the application on the grounds that the reasons
for refusal had not changed and the application was still premature. On November
4, 1982 the claimants requested that this application be cancelled. [37]
On April 7, 1983 the claimants made an application for rezoning and subdivision
of a 10 acre portion of the subject property into 63 approximately 50-foot single
family lots. In September, 1983 this Phase 1 subdivision received first and second
reading and following a public hearing received third reading on October 3, 1983.
There was an amendment at third reading to fewer larger lots (48 60-foot lots).
In a letter to the claimants later the same month, Delta confirmed that it was
looking for a park on the subject property immediately to the west of the proposed
subdivision. Under the Municipal Act it wanted a 5% dedication at the
south-west end of the subdivision that would be added to the proposed park. Mr.
Elsom offered land at some distance from the subject property as an alternative.
There was evidence that Delta continued to want a 10 acre park space on the subject
property and did not accept these alternatives as a substitute for the subject
property. [38] On February 24, 1984 Delta advised the claimants
that there would be a postponement of the application pending finalization of
the access routes for the Annacis bridge. We heard evidence that Delta had been
slow to decide on access routes because the residents of North Delta were opposed
to negative impacts on their property from increased traffic. On March 6, 1985
the claimants asked that the application proceed since the routes for the Annacis
bridge were now established. The taking occurred in May 1985 and in October 1985
the claimants confirmed that there were still some outstanding issues, one of
which the claimants had just fulfilled. Another issue that remained was the 5%
park requirement. Delta eventually decided to obtain the desired 10 acre park
site in the next stage of development and recommended approval. At a Delta meeting
Mr. Elsom stated that he was totally opposed to Delta's options for the park to
the south-west of the subdivision application. In any event fourth reading and
approval were finally given in November 1985 for what became known as the Doncaster
subdivision. 5.7 The Taking [39]
As indicated above, the claimants were provided with the detailed plans for Nordel
Way prior to the actual taking and there was considerable discussion between the
claimants and the respondent about various details of the Project that potentially
affected the development of the subject lands. Some eight months prior to the
taking, without consulting the Ministry, Mr. Elsom cut a trench up to 20 feet
deep and 80 to 100 feet wide along the proposed right of way. He used the material
from the cut to build up the embankment in certain areas. The embankments and
berms were created by the claimants in order to mitigate the effect of noise on
the future subdivisions that would border Nordel Way. Unfortunately, they were
created outside the proposed rights of way. [40] We heard
testimony from Bruce McKeown who as Special Project Engineer was the person in
the Ministry who had overall responsibility for the Project. In May 1985, the
initial taking for Nordel Way and the associated access road, the 84th Avenue
connector, took portions from 11 of the 19 parcels. This taking was reported to
be 11.273 acres by the claimants, and 4.64 hectares (11.46 acres) by the respondent.
Mr. Buchan, the engineer for the claimants, calculated the total size of the 1985
taking from his reconciliation of the plans. Ms. Watson, the appraiser for the
respondent, based her size estimate on plans prepared by G.A. Hol, the land surveyor
who did the survey for the taking that was registered in the Land Title Office.
We accept 4.64 hectares (11.46 acres) as the size of the taking. The taking for
Nordel Way runs parallel to Dunlop Road for most of its length, approximately
120 to 130 metres (400 feet) south of Dunlop Road. The taking for the 84th Avenue
connector runs from 84th Avenue at approximately the mid-point of the east side
of the property diagonally north-west across three parcels to Nordel Way. [41]
As a result of discussions between Mr. Elsom, his engineer Mr. Buchan, and the
Ministry, the Ministry installed five pre-serviced sleeves or ducts under the
highway for sanitary sewers, water, gas, hydro, telephone and cable, with manhole
covers at either end for connection to subsequent development. The Ministry also
installed a trunk storm sewer in Nordel Way with several connections on either
side so that developments could hook into this trunk sewer in due course. This
was again done in accordance with the claimants' specifications. [42]
In May 1986, before Nordel Way was opened, Mr. Elsom demanded that the embankments
that were on his property should be taken by the Ministry. He did not want to
maintain the embankments and he wanted the boundary to be at the top of the embankments.
There were ongoing discussions between the claimants, the Ministry and Delta about
the embankments but it was not until August 1995 that the Ministry effected a
second taking of the narrow strips bordering a portion of Nordel Way and the 84th
Avenue Connector to include the embankments. This taking was reported to be to
the top of the cuts and gave legal ownership of the sloped embankment to the public.
Mr. Buchan for the claimants estimated the taking at 0.58 hectares (1.436) acres
and Ms. Watson reported it at 0.55 hectares (1.36 acres). 5.8
Dealings with the subject site from 1985 to present [43]
After final approval for the Doncaster Phase 1 subdivision in November 1985, the
first of the 48 lots in this subdivision were sold in May 1986. It took two years
for the rest of the lots to sell with the final lots selling in April 1988. [44]
A second subdivision application, this time for 73 50-foot lots, was made for
the 12 acre site adjacent to the Doncaster subdivision on April 23, 1986. On September
8, 1986 Delta gave first and second reading to this Phase 2 application and the
application was amended to 63 60-foot lots. The application was held up for some
time as a result of Delta's desire for an agreement on park dedication and a road
network on the subject lands. Finally Delta agreed to take 5% of the land value
instead and fourth reading and final approval of what became known as the Harrogate
subdivision occurred on October 19, 1987. These lots sold from May 1988 through
October 1989. The Harrogate subdivision contained some land that did not belong
to the claimants. The claimants said that 57 lots were on the subject property,
the respondent 55. We find 56 lots on the subject property. [45]
Delta requested an overall comprehensive plan for the property in part to address
the issues of park dedication and traffic flow on the proposed road network. The
claimants submitted two relatively general plans for the remainder of the subject
property for comment by Delta staff: the Ducote plan in March 1987 and the Dhillon
plan in February 1989. Both of these plans, like the earlier Hanson-Erb plan,
showed a high density residential area centred on the lake, although the earlier
Ducote plan also included office and commercial uses in this central section.
No other park than the lake was identified. To the south of this central area
both plans showed an overpass in the vicinity of Centre Street and a new access
road to the overpass along 82nd Avenue. The corner of Nordel Way and the 84th
Avenue connector was identified for service commercial for the proposed gas station
and other commercial use such as a motel. Around the perimeter both plans showed
single family residential housing. Neither of these plans was submitted to Delta
in a formal application. [46] In 1988 the claimants applied
to Delta for a building permit and a temporary use permit for part of the subject
property for a school site. In part to provide an education facility for his son,
Mr. Elsom wished to establish a private school called Marlborough College on his
property. Delta's resolution refusing this application until a park site on the
subject lands was resolved was declared to be ultra vires by an order of the Supreme
Court in September 1988. Delta reconsidered the application for a temporary use
permit and objected to its design deficiencies since the proposed school was situated
primarily in modular buildings. The documentation indicates that a relatively
small school was proposed and while a future potential of up to 500 students was
discussed, the application was eventually revised downwards for accommodation
of only 100 students. The property was to be leased to Marlborough College by
the claimants. First reading did not occur until April 8, 1991. It is unclear
when the application received final approval. Notwithstanding the lack of approvals,
we understand that the school commenced operation in September 1988, across the
road from the proposed site in another part of the subject property. [47]
In January, 1989, the claimants cooperated with Chevron in applying for rezoning
for a gas station and other commercial premises at the corner of Nordel Way and
the 84th Avenue connector. Access was right in and right out and was located to
meet the Ministry's requirements. This application was eventually defeated by
Delta council in April 1991 at third reading because of public concern about potential
nuisance factors such as lights and litter, as well as such factors as children's
safety. [48] In 1989 and 1990 the claimants made a total
of five applications for single family residential subdivisions around the perimeter
of the property. The evidence showed that Delta refused to process these applications
until it had received a comprehensive plan with sufficient detail, together with
a traffic analysis in conjunction with the plan. (In Delta's opinion, neither
the Ducote plan nor the Dhillon plan provided adequate detail.) The park remained
an issue and Delta stated that it wanted a nine acre site on Dunlop Road across
from the existing Sunbury Park in order to increase its playing fields. Both Delta
and BC Gas indicated that they wanted greater setbacks for those lots situated
on the high-pressure gas pipe line that extended along two sides of the subject
property. Mr. Elsom's response to most of these requests was that he did not agree
with them. [49] In 1991 the claimants sold Lot 112 which
was an isolated lot in the south-west corner of the subject property to Whistler
Mountain Investments Ltd., a company in which Tom Goode Sr., a former mayor of
Delta, was principal. We were not provided with any documentation relating to
the sale or the development of this property. We understand that a 30 lot subdivision
with less than 60-foot lot widths was approved and built. Mr. Kruger, the engineer
for the respondent, had worked on this subdivision and told us that some acoustic
fencing was required by Delta for about half the boundary with Nordel Way. [50]
In 1996 the claimants sold Lot 666 that was one of the lots on the south-west
perimeter of the subject property to Tom Goode Jr. operating as Wiltshire Developments.
We were not provided with any documentation relating to the sale but were informed
that the sale price originally negotiated in 1995 was $800,000 for 4.59 acres.
A bonus of $50,000 was paid later to extend the closing until September 1996.
We understand that the sale was subject to development approval. The original
application for development was for 19 strata lots plus 1 fee simple lot, with
25% park. Strata lot development allowed the road to be narrower than if it was
a city street with fee simple lots. This application was rejected by Delta at
third reading on March 12, 1996 because of public opposition to the proposed density.
The application was amended to 16 strata lots with an average area of 7,000 square
feet. This amended application had a reduction in the amount of park, although
it was still 20%, with 18% in open space. In May 1996, a Delta report recommended
that this new application be further revised because the parks department did
not support the reduced width of a trail corridor compared with the initial application.
We are not certain as to the details of the development that was eventually successful
in being approved in November 1996. [51] In summary, most
of the subject property remained undeveloped at the date of the hearing in 2001.
There were two subdivisions for a total of 111 lots approved in 1985 and 1987.
In 1988 the Marlborough School started operating and it eventually occupied two
acres of the subject property, primarily in temporary modular buildings. With
respect to the five subdivision applications for single family residential housing,
Mr. Elsom continued to press for some resolution between 1989 and 1992 after which
we have no evidence that he did anything. Lot 112 was sold in 1991, with the eventual
development of 30 lots by the new owner, and lot 666 was sold in 1996, with the
development of 16 strata lots, again by the new owner. No other part of the subject
property was developed in the 15 years since the 1985 taking. [52]
During the hearing we were provided with a comprehensive plan for the subject
property that has been submitted to Delta as part of an application for rezoning
in 2001. We do not know if any part of this plan was ever approved. It showed
single-family residential lots on most of the remaining subject. It also showed
the existing Marlborough College school site north of 84th Avenue as well as the
proposed service station commercial site on the corner of Nordel Way and the 84th
Avenue Connector. A park was shown on the subject between the school board property
and Nordel Way; we note that this site had problems with access after the taking
in any event. While 360 of the proposed lots were 60 feet wide there were also
26 50-feet wide lots on an area to be developed north of Nordel Way, next to the
school board site. 6.
HIGHEST AND BEST USE 6.1 Claimants' position [53]
C.D. Blanchette of Collingwood and Associates provided appraisal evidence for
the claimants. John Buchan of Hub Engineering and Development Company Inc. was
the engineering expert, who provided layouts and servicing estimates for the claimants.
In addition to assisting the claimants with respect to their claim for compensation,
Mr. Buchan has provided services to the claimants for actual subdivision applications
on the subject property from time to time since 1984. He continued in that role
at the date of hearing although there had been little work for a period of years
as development activity had ceased. Planning advice was provided by Jag Dhillon,
a former Deputy Director of Planning for the Municipality of Delta. He left Delta's
employment in February 1988 and worked for the claimants for a brief period with
respect to an overall plan for submission to Delta and some subdivision applications. [54]
Mr. Dhillon prepared a report as to the development potential of the subject property
as of May 30, 1985. He reviewed the 1978 Overall Development Plan and the draft
Delta Community Plan. He stated that, in his opinion, before the taking,
the subject property had the potential for development as a single-family residential
subdivision with the possibility of some multi-family use and an automobile service
station use with neighbourhood commercial on the western side of the property,
near the corner of Dunlop and 84th Avenue. While Mr. Dhillon emphasized a number
of negative impacts of the taking on the subject property, the type of development
potential remained similar: 400 single-family residential lots, 150 to 200 townhouse
or apartment dwelling units and a neighbourhood shopping centre with a service
station on a central site. In the alternative, the subject property could be developed
as a conventional single-family residential subdivision. The layouts attached
to Mr. Dhillon's report, both before and after the taking, were
prepared by Mr. Buchan and showed only single-family residential. After the taking
there were two options: one showed no overpass and one showed an overpass over
Nordel Way linking an extension of 82nd Street and Centre Street. [55]
In Mr. Blanchette's opinion the most likely highest and best use of the property
was development for single-family residential. He stated that there was a significant
potential for multi-family and some, less certain, possibility for commercial
development. However, again the only layouts that were provided to him were Mr.
Buchan's layouts for single-family residential development, both before
and after the taking. As a result he valued the property as single-family
residential both before and after the taking. [56]
The evidence in this matter was lengthy and heard over the course of more than
a year. Several months after all testimony from Mr. Blanchette had been completed,
but before the remainder of the evidence had finished, the claimants repudiated
Mr. Blanchette's evidence on a number of points. Although the claimant Mr. Elsom
was not qualified as an expert, the board permitted him to testify in rebuttal
as to his opinion of the highest and best use, and market value of the subject
property in 1985, based on his experience as a developer. [57]
It was Mr. Elsom's opinion at this hearing that the highest and best use was single-family
residential. He disputed that there was a demand for multi-family development
in Delta in May 1985 and suggested that the neighbours would be opposed to this
type of development in any event. Neither did he think that there was scope for
commercial; in 1985 there was extensive commercial development along Scott Road
and after the taking the application for a Chevron site at the corner of Nordel
Way and 84th Avenue had been turned down because of objections from near-by residents.
In rebuttal, he provided evidence about the subdivision of a large number of small
5 acre sites in different areas of Surrey between 1985 and 1988. Counsel for the
claimants pointed out in argument that the 19 lots that made up the subject property
all existed as independent legal lots and could have been sold and developed independently
similarly to the 5 acre sites that were subdivided in Surrey. 6.2
Respondent's position [58] The Ministry relied on Candace
C. Watson of Watson Clee and Associates for appraisal evidence. William Kruger
of CitiWest Consulting Ltd. provided layouts and engineering servicing estimates.
Michael Jorden of Davidson, Yuen, Simpson provided planning advice. There was
evidence that layout options for the site were developed after discussions and
consultation between the planner, the engineer, and the appraiser. [59]
Mr. Jorden reviewed the Delta land use plans and associated studies. These plans
supported primarily single-family with a commercial centre and some medium density
multi-family housing. His opinion of the reasonable and probable use of the subject
property was all single-family or predominantly single-family with some townhouse
and neighbourhood commercial. He stated that the property was big enough to shield
the proposed multi-family in the centre of the property from anticipated opposition
to the increased density from the existing single-family neighbourhood that surrounded
the subject property. [60] Mr. Jorden prepared six optional
plans for development of the subject property: two before the taking and
four after. Mr. Kruger prepared conceptual engineering layouts based on
these six plans. All of the options centred on a lake that was near the existing
man-made lake on the site of the former gravel pit. The main comparison was between
a layout for single-family residential development only and a layout that provided
for some town house units (83 units on approximately 8 acres) and some commercial
use (approximately 1.4 acres) as well as single-family development. The single-family
lots had 66-foot frontages and were approximately 6,600 square feet. There were
options before and after the taking with single-family development
only and options before and after the taking showing mixed use
development. In addition, there were two more options after the taking with an
overpass over Nordel Way, one for single-family and one for mixed use development.
After consideration of the history of this issue from specified correspondence
and interviews, Mr. Jorden concluded that there was a significant chance that
an overpass would not be required. As a result the options containing an overpass
were eliminated. [61] Ms. Watson analysed the two options
prepared by Mr. Jorden for before the taking to see whether single-family
development or mixed use provided the higher value. She used the Subdivision Residual
Approach on each of these two options to see which layout produced the greater
profitability. She concluded that the highest and best use for the property was
the mixed use development; predominantly single-family residential with some multi-family
and some commercial. There were some differences between the before and
after layouts. The location of the multi-family units shifted after the
taking so that there were approximately four acres on the subject property prior
to the taking and over five acres after the taking. Before the taking
the commercial use was neighbourhood commercial at 84th Avenue and Dunlop while
after the taking it was a gas station site at the south-east corner of Nordel
Way and 84th Avenue. 6.3 Board's
Analysis and Conclusion [62] Both appraisers agreed
that development after rezoning was the highest and best use and that the primary
focus of the development would be single-family residential. The main issue is
whether some commercial and townhouse use would be part of the development. In
addition, the claimants in rebuttal, suggested that the property should have been
valued as development property consisting of 19 separate legal parcels rather
than as a common property. [63] Section 32 of the Act provides: 32
The market value of an estate or interest in land is the amount that would have
been paid for it if it had been sold at the date of expropriation in the open
market by a willing seller to a willing buyer. Thus
under the Act we must value the property on the basis of what a hypothetical purchaser
and seller would agree was the market value on the valuation date. [64]
The definition of highest and best use provided by Ms. Watson is: the
most probable use of a property at a particular moment in time that will produce
the highest net return, taking into consideration its potential utility. [65]
We agree with the comments of this board in Horsley v. British Columbia (Minister
of Transportation and Highways) (2000), 70 L.C.R. 52 at para 42 that "[w]hile
an appraiser may be assisted by the analysis of a planner or land use consultant,
in the board's opinion, it is the responsibility of appraisers to determine the
highest and best use on which to base their valuation." Planners generally
provide evidence on what are the probable uses given the applicable land use plans;
on the other hand it is appraisers who consider such factors as market demand
and potential profit. [66] With respect to Mr. Elsom's
evidence about the highest and best use, we have two comments. First, the highest
and best use (and market value) is being determined in the context of a hypothetical
purchaser buying the subject property from a hypothetical seller. An owner's plans
for the property, even where he is an experienced developer, are not necessarily
determinative. Second, the highest and best use of the subject property (and its
market value) are matters of opinion evidence. Mr. Elsom was never qualified as
an expert to give opinion evidence. In earlier proceedings in this matter at (1996),
58 L.C.R. 290 a different panel of this board refused to qualify Mr. Elsom as
an expert to give opinion evidence on highest and best use and market value. An
application that this board decision showed a reasonable apprehension of bias
by members of the board was dismissed by Mr. Justice Macdonald. See (1999), 66
L.C.R. 193 (B.C.S.C.). While we recognize Mr. Elsom's considerable knowledge and
experience in land development issues, he is a party in these proceedings and
accordingly is not a disinterested observer. Although he testified at the hearing
that single family residential was the highest and best use, there were documents
in evidence that Mr. Elsom had submitted plans to Delta with extensive multi-family
units in the centre of the subject property in 1979, in 1987, in 1989, and as
late as 1992. (The final plan submitted to Delta mid way through the hearing in
2001 did not have multi-family but we do not know if this application was ever
approved or amended.) The 1987 and 1989 plans also contemplated extensive commercial
on the subject. We also note that his evidence about the market value of the subject
property in these proceedings differed substantially from the evidence that he
gave at the family trial in October and December 1984, just five months prior
to the valuation date in this claim. As a result we have not given any weight
to his opinions on highest and best use and market value. Evidence from Mr. Elsom
about factual matters as distinct from his opinions has been considered where
relevant. • Importance of 19 separate
lots [67] The initial issue to be decided is the claimants'
assertion that the highest and best use of the subject property is to be determined
as 19 separate lots, rather than collectively as an overall development. As indicated
above, we must value the land as to what a hypothetical purchaser and seller would
agree as a sale price in an open market, assuming the highest and best use. The
engineers retained by both sides only considered development of the subject property
as a whole with an overall plan that assumed coordinated services and phased development.
Both the claimants' and the respondent's appraisers valued the subject property
on the same basis. The only reference to individual parcels was in the report
of Mr. Kruger, the engineer for the respondent, which stated that separate ownership
of parcels generally results in the properties developing one at a time depending
on the topography and the location of existing services. Maximum efficiency of
services and lot yield requires common ownership or co-operation amongst the various
owners. A prudent developer assembles as many parcels as is financially feasible
in order to maintain control over utilities and road access. [68]
It was not until Ms. Watson, the appraiser for the Ministry, was cross-examined
near the end of the hearing that the possibility of valuing the property as 19
separate lots was first raised. In our opinion, the last minute position on valuing
the property as 19 separate legal lots was an attempt by the claimants to minimize
the effect of time when some of the development and cash flow from the sale of
over 500 lots on the subject property is deferred. Ms. Watson understood that
there were persuasive engineering reasons for a single layout with coordinated
services starting at one point and was unable to comment on the engineering problems
associated with developing the 19 lots separately. The question of providing services
for the development of separate lots was not put to either engineer despite the
fact that the claimants recalled their engineer, Mr. Buchan, to provide rebuttal
evidence. Ms. Watson indicated that different parcels of the subject property
had different ripeness for development, depending in part on proximity to services,
and that in any event there was also a limitation on how many parcels might be
developed simultaneously as a result of absorption rates. [69]
A quote from p 105 of Basics of Real Estate Appraising, 4th ed., 1995
The Appraisal Institute of Canada was put to Ms. Watson: One
must always analyze the property as a separate entity. Even if potential exists
for a combined use with adjoining properties, or as part of a major land assembly
for a substantial redevelopment, an individual highest and best use analysis is
required. This provides both a bench mark for negotiations and a potential land
use should the proposed project fail to materialize. Ms.
Watson refused to agree that an individual analysis of each lot that formed part
of the subject property needed to be done. We are of the view that the 19 separate
legal titles provide the hypothetical vendor with some flexibility and that both
appraisers might have mentioned this. However, it appears to us that this passage
does not contemplate a situation where 19 separate but contiguous legal lots under
common ownership are already part of a major land assembly. [70]
In the family law decision where the subject property was valued, Mr. Justice
Locke comments on how Mr. Williamson, the appraiser for Mr. Elsom, stated that
the valuation of the 19 separate legal lots would be higher than the valuation
of the 147 acre parcel taken as a whole. However, when Mr. Williamson derived
valuations for both approaches they were similar and did not support his statement.
Mr. Justice Locke went on to observe at pp 25-26 of the decision that he had the
opposite expectation: he assumed that an overall plan for the subject would be
the most profitable and the necessary coordination with other contiguous landholders
over the overall plan might force down the values of individual parcels. [71]
It is true that many of the 19 lots before the taking had access and were
adjacent to at least some services from 84th Avenue or one of the existing roads
that bordered the subject property. (However, we note that 84th Avenue did not
have sanitary sewers or storm sewers and, although there was a water main, Delta
wanted it enlarged). At least theoretically, one or more of these 19 lots might
have been developed independently. In fact, two lots, Lot 112 and Lot 666, in
the south-west corner of the subject lands were sold separately to other developers
in 1991 and 1996. In addition, the applications for the first two subdivisions
on the subject property in 1986 and 1987, Doncaster and Harrogate, were independent
applications for development in each case of the northern portions of three or
four legal lots that had been isolated by the taking. However, we must value all
19 lots on May 30, 1985 and we accept that not all of these lots were imminently
ready for development on that date. Some were closer to services and would be
more valuable than others. Some were heavily encumbered with easements and would
be less valuable if not sold with adjoining lots that allowed more flexibility
for development. We also agree that a prudent purchaser would recognize that buying
one or two of 19 contiguous legal lots for subdivision development when they were
all being sold at the same time offered different prospects for absorption than
if only one or two of the legal lots were being sold. As a result, we reject the
claimants' position that valuing the property as 19 separate legal lots would
completely eliminate the need for phasing and the effect of time on the valuation
of a 147 acre parcel. In any event, as indicated above, all of the expert evidence
was based on valuing the subject property as a whole with one overall plan. [72]
In summary, we accept both appraisers' opinions and conclude that the highest
and best use of the subject property in May 1985 was the development of these
19 legal lots as a whole. • Single
family residential or mixed use [73] The other issue is
whether the highest and best use is development as single-family only or as mixed
use with some multi-family and commercial. While we agree with the claimants that
it might be easier to value the property on the basis of single-family residential
only, under the Act we are required to value the property on its market value
to a hypothetical purchaser. The market value must be determined on the basis
of the highest and best use, which is dependent on the most probable use with
the highest net return. Mr. Elsom's stated intentions for the property are not
determinative as it is an objective test applied to the hypothetical purchaser.
The fact that settlement negotiations in 1985 and 1986 were based on valuing the
property as single-family residential is irrelevant. Since the settlement negotiations
were unsuccessful, we must value the subject property as set out in the Act. [74]
As described above the draft OCP dating from 1978-79 as well as the 1985 draft
showed some commercial development and some multi-family residential development
on the subject. Both Mr. Dhillon and Mr. Blanchette, the planner and appraiser
for the claimants, stated that there was potential for both multi-family and commercial
at the relevant time. Despite Mr. Elsom's testimony at the hearing that only single
family residential housing made sense, the overall plans for the entire property
submitted by Mr. Elsom in 1978 (Hanson-Erb plan), in March 1987 (Ducote plan),
and in February 1989 (Dhillon's plan) all provided for substantial multi-family
and commercial. As late as 1992, there was evidence that the claimants intended
to develop the centre of the subject property with stacked townhouses or apartment
buildings. We note that the present application to Delta in 2001 leaves a "white
area" location on Nordel Way to the east of the 84th Avenue connector where
the Chevron gas station application had been made. This white area shows no single-family
lots and Mr. Elsom agreed that it was being left for future possibilities such
as a hotel or townhouses or a church. Although May 31, 1985 is the valuation date
this evidence shows that the claimants have continued to make submissions from
1978 through to 2001 that showed development on some portions of the subject property
that was more lucrative than single-family housing. [75]
Mr. Jorden, the planner for the Ministry, testified that on the basis of the Delta
plans he included some townhouses and 1.4 acres of neighbourhood commercial. The
townhouses were low density at 10 units/acre and the total number of 83 units
(44 on the subject property) was approximately half that in Mr. Dhillon's report.
Mr. Jorden stated that Mr. Cowie, the Planning Consultant for Delta at the time
of the taking, strongly favoured more multi-family housing and more innovative
housing. In cross-examination Mr. Jorden agreed that there were relatively few
townhouses in Delta in 1985 but he also discussed some successful projects in
other municipalities. It was his opinion that the sale of the townhouse site would
be postponed to a later phase of the project. He also conceded that the site might
be discounted because of slow markets. With respect to commercial, while there
was some risk to obtaining zoning approval, there was a reasonable basis for considering
a small site of neighbourhood commercial before the taking. After the taking,
there was greater potential for commercial in a new location on Nordel Way that
took advantage of the increased traffic on the new highway. Again there was a
risk associated with obtaining zoning approval, as well as problems with limited
access. However, we note that Chevron was interested in the site almost as soon
as Nordel Way opened in 1986. [76] We recognize that in
the absence of an approved plan there is some uncertainty with respect to multi-family
and commercial use. However, having reviewed the evidence that would be available
to a prudent purchaser in 1985, we agree that in addition to the primary use of
single-family residential, 8 acres of low density townhouses and 1.4 acres of
commercial proposed by Mr. Jorden were reasonable and probable uses for the subject
property. [77] This leaves the issue of which probable
uses drive the highest market value. In this case while Mr. Blanchette acknowledged
that some multi-family and commercial were feasible he did not independently consider
the market return on any other development but single-family residential. He chose
to rely on the layouts already prepared by Mr. Buchan, the engineer for the claimants,
that contained only single-family lots. On the other hand Ms. Watson, the appraiser
for the respondent, decided between single-family residential development only
and mixed-use development with 8 acres of low-density townhouses and 1.4 acres
of commercial, by analyzing both developments using the Subdivision Residual Approach
to see which produced the greater market return. In addition, her valuation of
single family, multi-family and commercial comparables in the Direct Comparison
Approach clearly yielded higher values for the multi-family and commercial sites.
Counsel for the corporate claimants' submission that there was no evidence to
support a higher value for multi-family use was clearly mistaken. We accept Ms.
Watson's opinion that the highest and best use is mixed use development that is
primarily single-family residential. 7.
MARKET VALUATION OF THE LAND TAKEN IN THE FIRST TAKING 7.1
Appraisal Approaches [78] In order to value the approximately
11 acres taken in 1985, Mr. Blanchette used the Direct Comparison Approach to
determine the market value of the subject property in both the before
and after situation. This method values the subject property by comparison
to properties that are similar in size, location and development potential and
that have sold at approximately the same time as the date of valuation. It was
the only method that Mr. Blanchette employed. Using eight comparables Mr. Blanchette
estimated the value of a raw lot, without servicing. On the basis of site layouts
prepared by Mr. Buchan of Hub Engineering, he calculated the value of the subject
property before the taking assuming 635 lots that were 60 feet wide. He
did the same thing after the taking, assuming that the number of lots
had decreased to 548. The estimated value of the partial taking was the difference
between these two valuations which, after amendment, was $2,364,000. This market
valuation for the partial taking was based solely on the difference in the number
of lots. To this sum Mr. Blanchette added two additional amounts for injurious
affection as a result of the taking: an allowance for noise for those lots affected
by Nordel Way and the 84th Avenue connector ($1,195,000) and an allowance for
net extra servicing costs ($790,000), based on servicing costs prepared by Mr.
Buchan. This allowance for extra servicing costs was amended in argument to approximately
$110,000 plus $519,000 for extra costs for such items as street lights. [79]
While Ms. Watson carried out a Direct Comparison approach before the taking,
she stated that she used this method only as a check on the Subdivision Residual
Approach, or Development Approach the approach on which she primarily relied.
This approach assumes a model in which the estimated development costs, financing
costs, and profits are deducted from the estimated selling price of the lots or
units in a development to yield an estimation of the raw land value before development.
This residual land value represents what a prospective purchaser would pay for
the land. Ms. Watson used site layouts and phasing provided by the planner, Mr.
Jorden of Davidson, Yuen, Simpson, and the engineer, Mr. Kruger of CitiWest. Engineering
costs were also provided by Mr. Kruger. Before the taking there were 539
single-family lots (primarily 66 feet wide), 44 townhouses and 1.2 acres of neighbourhood
commercial on the subject land and Ms. Watson assumed that the development would
be phased over nine years. After the taking there were 490 single-family
lots (the majority were still 66 feet wide), 57 townhouses and 1.4 acres of commercial.
She adjusted each of the subject lots for size, views, topography, proximity to
major arterial routes, including the Burlington Northern Railway, and for the
presence of rights of way, although she did not provide us with any details of
which lots were adjusted and how. In the after scenario, a number of the
lots backing onto the highway were worth less as a result of the noise. In addition,
there was an area of 1.15 acres of severed land that could not be accessed and
therefore had no value. [80] In spite of these factors
that reduced the after value, the difference between the before
and the after value of the land using the Subdivision Residual Approach
was less than the pro rata market value set out as a minimum in section
40(3) of the Act. (The ratio of the land taken to the total land before
the taking times the market value of the land before the taking) In other
words, the difference between the before and after approach was
only 3.9% of the before market value while the land area of the taking
represented 7.8% of the total land area of the subject property. Ms. Watson attributed
this to two factors: a decrease in engineering costs as a result of the project
and a more valuable commercial site after the taking. As a consequence,
Ms. Watson had to resort to the provisions for minimum compensation in section
40(3), (4) and (5) of the Act. She used what she called the Summation Approach
to calculate the value of various single-family lots and townhouses that were
located on the land taken and thus were lost as a result of the taking. She valued
these lots that were lost differently depending on whether they were ripe for
development or were deferred for three years and whether or not they were encumbered
with an easement and what type of easement. [81] The loss
in market value estimations of each party, based on the appraisal evidence, may
be summarized as follows:
| |
Claimants | Respondent |
| | Before |
After | Before | After |
| Direct Comparison Approach |
$17,273,000 | $14,909,000 |
$9,200,000 | |
| Subdivision Residual Approach | | |
$8,052,890 | $7,741,776 | |
Conclusion | | |
$8,052,890 | $7,741,776 | |
Difference between Before and After | |
$2,364,000 | |
$ 311,114 | | Value of land taken - Summation | | | |
$ 874,000 | | Injurious Affection - noise | |
$1,195,000 | | |
| - extra servicing* | |
$ 110,000 | | |
| | |
$ 519,000 | | |
| Estimate of Compensation | |
$4,188,000 | |
$ 874,000 | | * as amended
in submissions | [82] As indicated above,
Mr. Elsom in rebuttal, provided evidence on his opinion of market value. He testified
that it was his opinion the subject property was worth $200,000 per acre and in
submissions he adopted the more conservative estimate of $160,000 per acre for
a value of the taking of $1,833,600. 7.2
Appropriate Valuation Methods [83] During the hearing
there was much testimony about the relative merits of the Direct Comparison Approach
and the Subdivision Residual Approach or Development Approach. Mr. Blanchette
stated in his report that the Subdivision Residual Approach was not appropriate
because there was not an approved lot layout with associated engineering costs.
He also commented on the subjectivity and volatility of this approach. Mr. Elsom
testified that the Subdivision Residual Approach was not one used by developers
looking to purchase property; they did not have time to have such a complex valuation
done. During submissions Mr. Elsom indicated that the Ministry was trying to devalue
his property by using the Subdivision Residual Approach and spreading out the
development which resulted in a discounting of the value. [84]
In the family law trial Mr. Elsom provided an opinion as to the market value of
the subject property and contrary to what he has stated in this hearing he used
a residual approach spread over a 20-year development. However, Mr. Justice Locke
commented on p 24 of the decision that this evidence did not seem to provide much
assistance since both counsel and both appraisers said that land residual approaches
were not applicable. [85] Ms. Watson stated that the problem
with relying on the Direct Comparison Approach was that there were no good comparables
for such a large property at the valuation date. The largest property that she
could find to be used as a comparable in this approach was 10 acres which was
not very comparable to the subject at 147 acres. (While Mr. Blanchette used seven
of the same comparables, he did use one different comparable dating from July
1982 that was 16.5 acres.) She argued that the Subdivision Residual Approach was
preferable because it was the only approach that properly considered the effect
of time for absorption of lots on such a large property. She did use the Direct
Comparison Approach as a check on the valuation she obtained from the Subdivision
Residual Approach in the before scenario. [86] In Sequoia
Springs West Development Corp. v. British Columbia (Minister of Transportation
and Highways) (2000), 69 L.C.R. 1 (B.C.E.C.B.), this board discussed some
of the problems associated with the Development or Subdivision Residual Approach
at para 49 through 55. One problem was the degree of uncertainty inherent in this
approach unless a proposed subdivision has already been approved. In Sequoia
Springs there was an approved subdivision plan for the after situation,
and all of the evidence was based on this approved layout, although there was
some difficulty in establishing an appropriate layout for the before situation.
Another problem with the Development Approach was the volatility of the approach
when a comparatively minor change in one of the large number of subjective factors
can significantly affect the residual value for the raw land. In Premanco
Industries Ltd. v. British Columbia (Ministry of Environment, Lands and Parks)
(2000), 71 L.C.R. 6; leave to appeal to B.C.C.A. refused, (2001), 72 L.C.R. 1
(B.C.C.A.) this board noted at para 129 that the volatility associated with the
"residual method" was magnified in an arbitration setting such as this,
where the constraints provided by the real market place are lacking. The board
in Premanco quoted a passage from a decision of the English Lands Tribunal,
Clinker & Ash v. Southern Gas Board (1967), Digest of Cases, 1967
533, and went on to comment that the Lands Tribunal in the Clinker & Ash
case suggested that valuers using this method in proceedings before the Tribunal
"have a natural tendency to put forward opinions of value that are either
undependably high or undependably low", depending on the party they represent.
In Sequoia Springs the board commented at para 53 that because of the volatility
inherent in the Development Approach, "the Direct Comparison Approach is
to be preferred except where there is insufficient evidence to support a comparative
approach". It reluctantly accepted the Development Approach in the after
situation because of the lack of any other evidence. [87]
In this case we do not have any approved plan for the whole subject property.
All we have are four actual subdivisions for a total of 157 lots (150 lots on
the subject property) that occurred after the taking, with the last one occurring
some ten years after the taking. Both parties utilized these approved lots to
some degree in their after layouts, although there were some criticisms as to
how this was done. But this leaves approximately a hundred acres of the subject
property after the taking for which there is considerable uncertainty as to what
will be approved. Although we have the claimants' plan that forms part of a new
application for subdivision of the remainder of the subject property in 2001,
reviewing the correspondence between Delta and the claimants over 15 years suggests
to us that a number of changes will be required before it is approved. In any
event, the plan in this application has been submitted some 16 years after the
date of taking, and some aspects of it such as the private school, are clearly
not applicable to a layout for a hypothetical purchaser. We do not know what size
single family lots would have been approved for the remainder of the site nor
how many. We have concluded that the highest and best use will include some modest
amount of multi-family and commercial, but we do not know the number of multi-family
units that would have been approved, nor the density. We do not know where the
multi-family units would have been located. We do not know how much land would
have been approved for commercial, nor what type of commercial would have been
approved. We also do not know how much land for a park would have been required.
We note that in the subdivision that was eventually built on Lot 666, for example,
the evidence shows that Delta was requiring land for a trail system. Although
we do not have the final approved plan, the total park and open space in the two
applications for this subdivision that were in evidence were considerably more
than 5%. Thus we are faced with much greater uncertainty than the board had in
Sequoia Springs where an after plan for the entire remainder of
the subject property had been approved within a few years of the taking. [88]
We note that the approved plans for these four small subdivisions appear to be
the only relevant changes in the consideration of the Subdivision Residual Approach
since the family law trial in December 1984 when Mr. Justice Locke accepted the
evidence and submissions of counsel that this approach to determine the market
value of the subject property was not applicable. [89]
In any event, as we indicated above, Ms. Watson does not in fact use the Subdivision
Residual Approach to arrive at her final estimation of value. She used the Subdivision
Residual Approach to derive a value both before and after the
taking. But the value of the difference between these two values that she obtained
was below the minimum set out in section 40(3) of the Act. In considering the
value of the land that had been taken as required under section 40(3), she concluded
that some of the land that was taken was more valuable (the land that was ripe
for development) while other land was less valuable (the land that was encumbered
by easements). As a result she valued each of the lost lots differently depending
on whether or not they were ripe for development and whether or not they were
encumbered with an easement. A close review of this valuation indicates that it
was based on the discounting model and the adjustment for easements that she had
used in the Direct Comparison Approach. Thus, although she did carry out the Subdivision
Residual Approach, it was eliminated when the difference between the before
and after value was too low and the basis for the final estimate of value
was from information derived from the Direct Comparison Approach, rather than
the Subdivision Residual Approach. This did not appear to be recognized during
the hearing. [90] While we agree with Ms. Watson that the
comparables used by both appraisers in the Direct Comparison Approach are far
from ideal, after consideration of all of the relevant factors, we are not necessarily
convinced that the reasons for avoiding the Subdivision Residual Approach have
been overcome in this case. In any event, the Subdivision Residual Approach analysis
depends on a particular layout and all the costs that are used in the approach
are based on that layout. When we reviewed the layout used by the respondent,
in addition to the general uncertainties as to what might be approved, we have
some difficulties with the before and after layouts adopted by the Ministry's
experts that appear to diminish the value of the taking. [91]
One such difficulty was that the planner, Mr. Jorden, adopted 66-foot lots
before the taking (except for the 48 60-foot lots in what became the Doncaster
subdivision that had already been submitted to Delta prior to the taking) but
after the taking he used the three other subdivisions that were subsequently
approved. This included 63 60-foot lots for the Harrogate subdivision (55 on the
subject property), 30 50-foot lots on Lot 112 and 13 60-foot lots on Lot 666 (Mr.
Jorden appears to have put 13 lots on Lot 666 although the actual development
was 16 strata lots). Omitting Lot 666, there were almost 100 out of a total of
490 lots that were smaller after the taking than before. In a valuation
for the taking that depends on subtracting the after valuation from the
before valuation, when both valuations are primarily based on the valuation
of each of the lots, this would tend to minimize the impact of the taking. On
a purely mathematical basis, the underestimation of the loss of lots for this
particular factor is approximately 10 lots. [92] In
Sequoia Springs this board dealt with a similar issue of what differences
were appropriate in before and after layouts. In that case the after plan
had been approved by the municipality and the issue was the relative ratio of
single and multi-family units in the before scenario. At para 89 the board
said: We do not agree that the unit mix necessarily
needs to be identical in both scenarios. Any number of before plans could have
been approved for the site; in fact, the plan attached to the OCP makes only general
reference to the mix of housing styles. We do agree with Sequoia Springs, however,
that the scheme which gives optimum value to the property is the appropriate one
under the circumstances. The board went on to
alter the ratio of single-family lots and multi-family units in the before
so that it was consistent with the ratio after the taking since that change
would drive a higher value. This it said would result "in a more equitable
comparison for measuring the value of the taking and the loss in value to the
remainder". [93] In this case we acknowledge that
developing a before and after scenario with no comprehensive approved
plan is a complex exercise. During the hearing each party was criticized by the
other for inequities in their layouts for before and after the
taking. Designing sequenced phases of approximately 500 lots for before
and after layouts that take into account servicing requirements and at
the same time consider such issues as keeping lot sizes and/or lot densities similar,
and incorporating various aspects of the subdivision plans that have been approved,
is not a simple task. However, we agree with the board in Sequoia Springs,
that the layouts both before and after must be chosen in regard
to the principle of providing optimum value in an equitable manner. [94]
In both the before and after layouts the hypothetical prudent
purchaser is assumed to have the same information, but for the fact that there
is a taking for the Project in the after layout. If hindsight is used
after the taking to factor in the important consideration of what was
in fact approved by the municipality, it should generally be applied before
the taking as well, in order to be equitable. We do not see that the taking for
Nordel Way in any way supports a position for many of the lot sizes becoming smaller
after the taking. Although Ms. Watson did not directly compare the profitability
of a layout with 66-foot lots to one with 60-foot lots, she did testify about
the relative developer's profit for three of the comparable sales where the serviced
lots had been sold. After making various assumptions about costs, the layout with
more, but smaller, lots produced the most profit, while the layout with the largest
lots produced the least. Ms. Watson stated in her report that she adjusted for
the size of lot in the Subdivision Residual Approach on the basis of $1,000 per
1,000 square foot deviation from the base lot size of 6,458 square feet. There
was no indication in the report as to which lots were adjusted or how many lots
were adjusted. It is not clear to us whether there was a minimum difference in
size before the adjustment was made. Even if an adjustment was made in accordance
with Ms. Watson's formula, it does not begin to account for the underestimation
of the loss of lots. We do not think that it was equitable for the Ministry to
transform approximately 100 lots in the after scenario to smaller, and
possibly more profitable lots, and in any event cause an unnecessary reduction
in the number of lots that were lost. [95] Another inequity
with the before and after layouts is the Ministry's choice of
the number of multi-family units. Before the taking there were 83 townhouse
units in the overall layout but only 44 of them were on the subject property.
The shifting of the location after the taking meant that although there
was a slight decrease in the number of townhouse units in the overall layout from
83 to 77, there was an increase in the number of units on the subject property
from 44 to 57 units. Since the multi-family use was more valuable, a greater number
of townhouses in the after situation would decrease the effect of the taking.
As the board stated in Sequoia Springs it is more equitable to attempt
some consistency between the ratio of single-family lots and the number of multi-family
units both before and after the taking unless there is a reasonable
explanation that arises from the circumstances of the taking. It may be that the
change in the location of the townhouses after the taking is appropriate
but we were not convinced that efforts had been made to be more equitable in maintaining
the ratio of single-family lots and multi-family units. [96]
Thus there are at least two aspects with the Ministry's before and
after layouts that we do not accept, in particular the use of approximately
100 smaller lots in the after layout. The engineering costs prepared by
Mr. Kruger depend on a particular layout. If we change the layout by changing
such factors as the size of the lots, the number of lots and the number and location
of the townhouse units, we do not have the necessary information to amend the
engineering costs. As pointed out by E.C.E. Todd in The Law of Expropriation
and Compensation in Canada, 2nd ed. (1992), at p. 221, the Subdivision Residual
Approach depends on servicing costs that have a "solid factual basis"
as one of the several factors that are fed into the model. While it is possible
to rework the model for the Subdivision Residual Approach if certain factors are
changed, in this case we were not provided with the evidence to recalculate the
servicing costs if the number and location of lots and townhouse units are changed. [97]
In summary, we conclude that we are unable to use the Subdivision Residual Approach
in this case. As we have indicated, the Subdivision Residual Approach was not
in fact used by either appraiser to determine the final market value of the effect
of the taking. More importantly, there are too many uncertainties with respect
to the potential development in 1985 to use the Subdivision Residual Approach
when this approach depends on a particular layout and detailed engineering costs
associated with that layout. Having rejected certain aspects of the respondent's
layouts, we simply do not have the necessary evidence. In these circumstances,
a somewhat more general approach to the valuation is appropriate. 7.3
Market Valuation Before the Taking 7.3.1 Claimants'
position [98] Mr. Blanchette relied on layouts provided
by Hub Engineering that showed 635 lots on the subject land before the
taking that were all 60 feet wide. He used the sales of eight comparables, ranging
from 0.73 hectares (1.8 acres) to 6.68 hectares (16.5 acres). These sales ranged
from $62,762-$189,591 per acre or $22,500-$27,778 per raw lot. From this data
he concluded a value per raw lot of $25,000. He made one adjustment for density.
The layouts for the subject property had a lower density before the taking
than the comparables. Since Mr. Blanchette estimated the comparables had 20% more
lots per acre, he made a 20% upward adjustment to the raw lot value of $25,000
per lot to arrive at an adjusted raw lot value of $30,000. [99]
Mr. Blanchette amended his report to allow for a one year deferral in his valuation
to allow time for approval of a comprehensive development plan. He considered
data on bank and mortgage rates at various times and concluded a discount rate
of 10% as appropriate. As indicated above, his value before the taking
was $17,273,000 (635 lots x $30,000/lot discounted 10%). [100]
In rebuttal Mr. Elsom presented some evidence to support a higher valuation than
Mr. Blanchette. With respect to lot value, he provided his opinion that specified
properties that had been used as comparables by both Mr. Blanchette and Ms. Watson
were not as valuable as the subject property because of such factors as lacking
a view or being close to commercial development. Mr. Elsom was asked his opinion
as to the market value of the subject property in May 1985 which he answered at
$200,000 an acre or $50,000 per raw lot value. In argument, the claimants stated
that they would adopt a "conservative" approach to this evidence and
claim $160,000 per acre or $40,000 per raw lot. The claimants submitted that because
the Project had frozen development applications for the subject property in 1979
and in 1983 that the entire property should be treated as imminently developable
in 1985; there was no need for any discounting. We note that in the family law
trial Mr. Elsom testified that the property value was only $45,000 per fully serviced
lot on sale to a purchaser, including development costs, developer's profit and
real estate commission. 7.3.2
Respondent's position [101] Ms. Watson carried out
a valuation before the taking using the Direct Comparison Approach. As
indicated above her highest and best use was mixed use and she relied on the mixed
use layout prepared by the planner, Mr. Jorden, and the engineer, Mr. Kruger.
On that part of the subject lands owned by the claimants, there were 539 single-family
lots (491 lots were a minimum of 66 feet wide and 48 were a minimum of 60 feet),
44 townhouses and 1.2 acres of commercial space before the taking. With
respect to the 57.61 hectares (142.34 acres) assumed to be single-family residential,
she used eight comparables, seven of which were the same as those used by Mr.
Blanchette. She also concluded a value of $25,000 per raw lot from the comparable
sales, although her raw lots are larger than those of Mr. Blanchette. She divided
the single-family residential portion of the property into three sections. In
May 1985 development for Phase 1 or what became the Doncaster subdivision was
imminent, and as a result she applied no discount for time for those 48 lots.
Since she had assumed that Phase 2 or what became the Harrogate subdivision was
in the planning stage she applied a discount of one year for approval to the 55
lots in that subdivision that were on the subject property. The remaining 436
lots on the subject property were discounted for three years to allow for time
to obtain approval for a comprehensive development plan and for some of the services
to go in. After considering a variety of financial information she determined
that a discount rate of 11% was appropriate. The total value for the 539 single
family raw lots was $10,428,721. [102] For the 1.62 hectares
(4.01 acres) multi-family area of the subject property Ms. Watson had four comparable
sales that provided a range of values per estimated townhouse unit of $12,833
to $17,283. She concluded a value of $15,000 per unit for the lakeside units and
$12,000 per unit for those that were not lakeside. The valuation for the 44 townhouse
sites was discounted for three years at 11% for a final valuation of $425,553. [103]
Finally, Ms. Watson valued the 0.49 square hectares (1.2 acres) of the subject
property on the commercial site using seven comparable sales. Ms. Watson concluded
a value for the subject of $6.50 per square foot. This yielded a valuation of
$223,743 after discounting for four years at 11%. [104]
The total valuation of the portions of the subject property used for single-family
residential, multi-family and commercial was $11,058,017. Ms. Watson made two
further adjustments to the sale prices. First, she made an adjustment for the
four easements, after reviewing the restrictions for each easement. A total of
7.82 hectares (19.31 acres) was encumbered by various easements, with some of
this land encumbered by more than one easement. She reduced the value of the actual
land that was encumbered between 30% and 80%, depending on the type of easement
and the restrictions on development. She also applied a general discount of 10%
for a number of factors including the large size of the subject property, uncertainty,
and the time for absorption for so many lots. [105] After
these adjustments, her overall valuation for the property before the taking
was $9,199,899 or $9,200,000 rounded by this approach. [106]
Because the subject property was so much bigger than any of the comparables, 59.5
hectares (147 acres) compared to 3.8 hectares (9.48 acres) for the largest comparable
for single-family development, Ms. Watson attempted to check her final valuation
with two sales of large development property. One of these was the sale of British
Columbia Penitentiary site in New Westminster that yielded a price of $70,383
per gross acre or $131,926 per net developable acre in April 1986. The second
sale Ms. Watson used was Riverview Heights in Coquitlam. This sale price in June
1985 translated into $93,346 per acre for the single-family development at 4.75
lots per acre. In her report Ms. Watson stated that this value for the second
sale supported her market value per acre for the subject of $62,348 after taking
into account the lack of approvals for the subject. 7.3.3
Market Valuation Before the Taking -- Board's Analysis [107]
The two parties' estimations of market value for the subject property before
the taking using the Direct Comparison Approach are very far apart: Mr. Blanchette
estimates $17,273,000 and Ms. Watson $9,200,000. There are two main reasons for
this significant difference. First Ms. Watson has assumed that most of the development
on the subject property should be discounted for three years to permit time for
a comprehensive development plan to be approved and for services to be installed.
Mr. Blanchette, in contrast, initially valued the property without any discounting,
and then in an amendment, assumed only a one year delay for a comprehensive development
plan. Second, because his raw lots on the subject property were larger than the
lots in the comparables, Mr. Blanchette made a 20% adjustment for density, while
Ms. Watson, despite using larger raw lots on the subject than Mr. Blanchette,
made no adjustment. Other differences are the presence of a park in the respondent's
layout, the size of the single family lots, and the adjustments for easements
and size of the property. Ms. Watson has used a few acres of multi-family and
commercial which have a higher value than single family residential, but this
has been off-set by the other factors listed above. [108]
In arriving at a valuation of the property before the taking we have to
consider a number of factors including the layout that should be adopted, the
number of years that the sale price should be discounted, the discount rate, the
comparables that should be used, and the appropriate adjustments. 7.3.3.1
Layouts [109] Both appraisers provided us with detailed
layouts. Since the Direct Comparison Approach depends primarily on the value for
every single family lot (plus the value for each townhouse unit and the value
for the designated commercial space) the layout that is adopted will have a significant
effect on the value. There were a number of aspects of the layouts presented by
the two parties that were in dispute and that need to be resolved. These were
as follows: • Park [110]
The claimants did not include any park in their layouts before and
after the taking, despite Delta's demands that a park site be located on the
subject property. Mr. Elsom strongly objected to providing a park on his property
and he had attempted to avoid this requirement in various ways including the offer
of other land and successive applications for small subdivisions. Mr. Buchan stated
that since the location of the park was unknown he had simply omitted it. It would
require more work to modify the layouts if you moved the park from one location
to another, than if you simply inserted a park in the location where it was eventually
required. The Ministry's layouts showed a park centred on a lake in the middle
of the development. The portion of the park on the claimants' land both before
and after the taking was approximately 5% of the total amount of the claimants'
land in the development. [111] In 1985 the Municipal
Act required owners of land applying for subdivision to provide up to 5% of
their land for park, or, in the alternative to pay 5% of the market value of their
land instead of providing the land itself. The evidence made clear that Delta
was determined to have a park located on the subject property. Although the OCP
had not yet been passed identifying a park site on the subject property, the draft
OCP showed a park site. A prudent hypothetical purchaser of the land would have
known about Delta's requirements and would have taken the park requirement into
account. We conclude that 5% of the overall subject property should be deducted
for a park. Using 147 acres for the subject property this results in 7.35 acres
being deducted. [112] We note that in the family trial
Mr. Elsom's report on the market valuation of the subject property deducted 5%
for park dedication. Locke J.'s valuation of the property was based on a developable
area after a 5% deduction had been made for a park. [113]
The claimants criticized Mr. Jorden's choice of a lake as part of the park site
when Delta had indicated different things with respect to its plans for a park
at different times. They were particularly critical that the lake in the layout
was not in the same place as the existing lake. In our view the nature and location
of the park is irrelevant, especially given the general nature of the layouts
in the Direct Comparison Approach. •
Size of single family lots [114] The claimants used 60
feet wide lots in both the before and after scenarios. The Doncaster
subdivision was developed with 60-foot lots, and the decision for this width of
lot had been made in late 1983. Mr. Trygg, the realtor who had worked with selling
the lots on Doncaster, and Mr. Buchan, both provided evidence that the initial
subdivision application for Doncaster in 1983 used 50-foot lots but that for market
reasons the decision was made to go with 60-foot lots. [115]
The Ministry generally used 66-foot lots in its before layout. Mr. Jorden
gave evidence that this choice was made based on the Sunbury subdivision to the
north and the Canterbury Heights subdivision to the south of the subject property.
A number of the subdivisions with smaller frontages occurred after 1985. However,
after the taking Mr. Kruger explained that the actual layouts for the
four subdivisions that have actually been built were used and all of these were
smaller at 60 or 50-foot. As we have already stated, we think that it was unfair
of the Ministry to transform approximately 100 lots in the after scenario
to smaller, and possibly more profitable lots, when that change causes an unnecessary
reduction in the number of lots that were lost. [116] The
choice of size of lot in the market valuation in this case is not necessarily
what the claimants decided to do in the Doncaster and Harrogate subdivisions,
or what they say that they plan to do in future development. The claimants suggested
that Delta's bylaws were changed at some point to allow smaller lots than those
that had been built earlier in Sunbury and Canterbury Heights but we did not receive
specific evidence on the details. Mr. Jorden stated that he was unaware that Delta
approved smaller lots before 1985. However, we note that the initial subdivision
application for Doncaster was for 50-foot lots and that in October 1983 at third
reading the claimants changed the layout to 60-foot lots. Thus, we accept that
60-foot lots were approvable in 1985. [117] Having reviewed
all of the evidence, we conclude that a hypothetical purchaser would use 60-foot
lots, both before and after the taking, as a basis for determining valuation. •
Multi-family and commercial [118] The Ministry's layout
before the taking included a total of 8.2 acres of multi-family but only
4.01 acres on the subject property and 1.4 acres of commercial with 1.2 acres
on the subject property. While the acreages of multi-family and commercial in
the overall layout were much the same after the taking, as a result of
shifting the locations for these uses, there were higher acreages of multi-family
and commercial on the subject property. Both multi-family and commercial uses
are more valuable than single family. If there are more of these uses on the subject
property after the taking than before, the effect of the taking
is minimized. As indicated above, we do not think that it was fair and equitable
for the Ministry to place more of these uses on the subject property after
the taking than before, unless there were compelling reasons to do so arising
out of the taking. In our opinion, there was no reason why the limited amount
of multi-family and commercial uses could not have been located entirely on the
147 acre subject property. As a result, we conclude that a hypothetical purchaser
having concluded a highest and best use of 8 acres of low density townhouses and
1.4 acres of commercial was reasonable would expect that these more valuable uses
would be located on the subject property. •
Number of single family lots [119] The claimants used layouts
with 635 60-foot single family lots on 147 acres before the taking, while
the respondent had 539 66-foot single family lots on approximately 135 acres.
We have decided that the hypothetical purchaser would have relied on 60-foot single
family lots on approximately 130 acres (147 acres - 7.35 acres for park - 8 acres
for multi-family - 1.4 acres for commercial). Although we have selected an average
lot size similar to what was used by the claimants, we reiterate that we do not
know that the claimants' layout would have ever received approval. [120]
There were a number of disputes about both parties' lot layouts before
the taking. One of these was to do with the Ministry's omission of lots on the
south-western boundary of Lot 112 and Lot 666 next to the BNR railway. Prior to
the taking Delta had acquired a road allowance on adjacent properties on either
side of the subject property for a projected north-south route called Browning
Drive. In fact there was evidence that rights of way had been acquired for much
of the entire length of North Delta. There were references to the proposed Browning
Drive in the 1978 comprehensive development plan for the subject property prepared
by Hanson-Erb for Mr. Elsom. Mr. Jorden reported that the planners in Delta had
told him that if the Alex Fraser bridge had not been built, then a road allowance
for Browning Drive adjacent to the BNR railway would have been required as a condition
of development of the subject property. We note that this requirement is by a
different authority than the respondent and is independent of the Project.
After the taking Browning Drive was no longer necessary because Highway 91
provided a north-south route. In argument the claimants suggested that Browning
Drive was not being contemplated by Delta in 1979 but the evidence for this was
far from clear and in any event, by 1979, the new bridge and Highway 91 were generally
expected. In our opinion, the evidence supports the fact that there is a probability
that a prudent purchaser before the taking, in the absence of the whole Project,
would have taken the risk of this requirement into account when he or she was
negotiating a purchase price. [121] The area on which the
claimants put lots, but the respondent did not as a result of the Browning Drive
right of way, was approximately 3 acres. Portions of this area were steep and
significantly encumbered with easements for high-pressure gas pipelines. Because
these features limit the number of single family lots that can be located on this
area, we find that it is reasonable to allow the equivalent of 2 acres for the
Browning Drive right of way. Thus, the new total that is available for single
family lots is 128 acres (130 acres - 2 acres). [122] The
Ministry pointed out that both appraisers' layouts before the taking showed
lots on a unopened road allowance for 104th Avenue, when this land did not belong
to the claimants. We heard some evidence that road exchanges could occur between
a municipality and a developer but we have no evidence as to whether this was
likely in this case. In our opinion a hypothetical purchaser would not necessarily
count on such an exchange and therefore the total number of lots achieved
before the taking may be somewhat overestimated. [123]
Another issue was the presence of easements and how the layouts accommodated them.
The claimants left leave corridors on much of the B.C. Hydro electrical easements
but placed lots on the high-pressure gas pipeline along the southern boundary.
The respondent placed lots on all the easements with sufficiently large lots to
provide a building envelope. The evidence showed that Delta and B.C. Gas had objected
to the size of the lots that backed onto the high-pressure gas pipeline along
108th Street and the southern boundary as shown in the claimants' subdivision
applications. Larger lots were required to accommodate sheds, decks, patios and
overhangs. Although the present layouts prepared by Mr. Buchan for the claimants
contain larger lots than the initial subdivision applications, we remain uncertain
as to whether a number of lots in the before layouts prepared by the claimants
would have been approved without further accommodation for the easements. Any
further accommodation for the easements would decrease the number of lots. [124]
Before the taking the claimants' layout showed 4.32 lots per acre, while
the respondent's mixed use layout lots (using somewhat larger lots) showed 4.1
lots per acre on the land that was used for single family. We have indicated that
we are uncertain about the lots on the closed 104th Street road allowance as well
as the number of lots on the high-pressure gas easement. As we no longer have
an engineered layout and we do not know if either of the layouts would have been
approved, we must be somewhat conservative in our estimated lot density. We conclude
that a density of 4.2 is appropriate. Assuming 128 acres is available for single
family lots, at a density of 4.2 we conclude that approximately 538 60-foot single
family lots is reasonable. 7.3.3.2
Deferred development [125] Mr. Blanchette initially
had no discounting and arrived at his valuation based on the value of the total
number of lots in his layout. He later amended his report to allow for a one year
deferral for the whole property to obtain zoning and planning approval for a comprehensive
development plan. Ms. Watson considered the claimants' work on subdivision applications
at the time of taking. The Doncaster subdivision had received third reading in
October 1983, but in February 1984 Delta notified the claimants that the application
would be delayed pending the finalization of the access routes for the new bridge.
Final approval occurred in November 1985. As a result of this application being
so far advanced Ms.Watson stated that the 48 lots in this subdivision were ripe
for development and thus needed no discount. The Harrogate subdivision application
was submitted in April 1986 and was eventually approved in October 1987. Ms. Watson
applied a 1 year deferral to these 63 lots. Ms. Watson deferred the remainder
of the subject property three years to obtain a Comprehensive Development Plan. [126]
At the date of valuation the 48 lot subdivision application was relatively advanced
and we agree that a hypothetical purchaser would treat these lots differently
and expect them to be on stream shortly. However, we do not think that the lots
in Harrogate would be accorded any special categorization by a hypothetical purchaser
when no application had yet been made and inquiries to Delta would make it clear
that a formal application with an overall plan including a traffic plan and some
commitment on a park site was desired. [127] Mr. Dhillon
who had been Deputy Director of Planning for Delta in 1988 stated in his report
that an overall plan for the subject property could have been approved in between
one and three years depending on its complexity. There was evidence that several
other large projects in Delta had taken two to four years to achieve an overall
plan. In the family law decision Locke J. relied on the opinion of the appraiser
for Mrs. Elsom, Mr. Squarey, that two years would be necessary before any lots
would be approved, followed by one third of the unserviced raw lots being approved
in each of the next three years. Thus the value of one third of the lots was deferred
two years, the value of the next third was deferred three years and the value
of the final third was deferred four years. This approach gave some recognition
that while initial subdivision applications for part of the subject property might
be made concurrently with an application for an overall plan that other parts
of the property would achieve subdivision approval later. [128]
Because our valuation of the subject property is based on a hypothetical purchaser
and seller in May 1985, Mr. Elsom's particular history with Delta and the difficulties
he experienced in obtaining approvals is irrelevant. On the other hand, the subject
property was very large and in 1985 there was some history of public opposition
to increased traffic and perceived problems from development from residents in
the adjacent neighbourhoods. We note that all of the comparables were for developments
that were much further advanced in terms of land use approvals. We conclude that
deferring all of the subject property, but for the 48 lots in Doncaster, for an
average of three years to obtain both approval for an overall plan and subdivision
approval is reasonable. 7.3.3.3
Discount rate [129] Mr. Blanchette used a discount
rate of 10% while Ms. Watson used 11%. Mr. Blanchette reported that the Bank of
Canada rate fluctuated around 10% in January and February 1985, rising to 11.5%
by the end of February. By mid April it had fallen to 9.75%. Mortgage interest
rates ranged from 11% to 12.5% depending on the term and the time of year. Ms.
Watson relied on data for May 30, 1985: the prime rate was 10.5% and the 5 year
mortgage rate was 12.25%. Ms. Watson's analysis is more precisely related to the
date of taking and we accept 11%. 7.3.3.4
Comparables • Single family [130]
Seven of the comparables used by Mr. Blanchette and Ms. Watson for single family
residential were common. Each appraiser used one comparable not used by the other.
The range in values per projected lot was relatively tight, with the lowest being
$22,159 and the highest being $27,778, after the exclusion of the one property
used by Ms. Watson but not by Mr. Blanchette. Both appraisers concluded $25,000
per lot. [131] We note that in the family law decision
Locke J. details the comparables used by Mr. Squarey. From the description of
these sales, it appears that several of them were the same as the total of nine
comparables used by Mr. Blanchette and Ms. Watson. Mr. Squarey concluded $25,000
per lot as well, and he applied this lot value to a projected density of 6.0 lots
per acre. Locke J. based his conclusion of $23,107 per lot by averaging six of
Mr. Squarey's comparables. [132] In our opinion three of
the larger comparables used by both appraisers are of particular assistance. These
are Mr. Blanchette's comparables 2, 5 and 8 (Ms. Watson's comparables 8, 3 and
6 respectively). All of these comparables were much further along in the approval
process than the subject; two had reached third reading and the other had zoning
in place with a subdivision application that had already been submitted a number
of years prior to the sale. These three comparables yielded lot values on the
number of lots achieved of $22,500, $27,778 and $22,675. While Ms. Watson relied
on the number of lots contemplated at the time of purchase, rather than the number
of lots achieved, the evidence as to what the purchaser had hoped to achieve at
the time that he or she had negotiated the purchase price was far from clear,
given that the research had been done some 10 to 15 years after the sale. [133]
Mr. Blanchette made a 20% adjustment to his lot value for density. Mr. Blanchette
stated that the Hub layouts that he was using for the subject property had a density
of 4.8 single family lots per acre before the taking. In comparison, the
comparables had projected densities at the time of sale of 2.8 to 7.3 lots per
acre, or 5.4 to 7.3 if the comparable with the lowest density is omitted. Since
4.8 lots per acre on the subject property is 20% less than an assumed density
of 6.0 lots per acre for the comparables, Mr. Blanchette made a 20% upward adjustment
to the raw lot value of $25,000 per lot to arrive at an adjusted raw lot value
of $30,000. [134] Although Ms. Watson's average lot size
was larger than Mr. Blanchette's and her density was therefore lower, she did
not make any adjustment for size. As we have described above, Ms. Watson did adjust
for lot size in her Subdivision Residual Approach on the basis of $1,000 per 1,000
square foot deviation from the base lot size of 6,458 square feet. This adjustment
was applied to fully serviced lots. [135] Mr. Blanchette
did not provide any market evidence for his 20% adjustment. As he pointed out,
the density of the number of lots per acre is affected by the relative proportion
of land that is necessary for roads, and on the smaller comparables this may be
less than on the subject property. As a result we find the average lot size more
useful than the density in making our comparisons. We also note that Ms. Watson's
adjustment based on serviced lots has some basis in market value. [136]
Ms. Watson stated that the average lot size before the taking on Mr. Jorden's
layout using 66-foot lots was 8,172 square feet, while the base lot size from
which she made adjustments was 6,458 square feet. Neither Mr. Blanchette nor Mr.
Buchan provided the average lot size on the claimants' layouts using 60-foot lots.
We estimate that for our general layout with a minimum lot size of 6,000 square
feet the average lot size is more than 7,000 square feet. While some of the comparables
had much smaller lots than the subject property, two of the three comparables
that we find of most assistance achieved lots that are closer in size to those
on the subject property, although they are still somewhat smaller. Mr. Blanchette's
comparable 5 (Ms. Watson's comparable 3) had lot sizes ranging from 4,725 to 6,857
square feet with an average of 5,600 square feet. This comparable provided a lot
value of $25,000 based on the initial subdivision proposal and $27,778 based on
the smaller number of lots achieved. This layout, like the subject property, had
a 5% park. Mr. Blanchette's comparable 8 (Ms. Watson's comparable 6) had lot sizes
ranging from 4,785 to 9,928 square feet with more than a third of the lots significantly
over 6,000 square feet. This comparable provided a lot value of $22,159 based
on the original subdivision proposal or $22,675 based on the final subdivision
that was built. There was no park in this layout, but the developer would have
paid 5% of the market value in lieu. Therefore the lot value needs to be adjusted
upward to approximately $24,000. We are unable to use the third comparable in
this analysis as it was never built and so we do not have the actual lot sizes. [137]
Based primarily on these two comparables and Ms. Watson's adjustment for lot size,
together with an adjustment to Mr. Blanchette's comparable 8 for the lack of park,
we conclude an adjusted raw lot value of $28,000 is reasonable. [138]
Mr. Elsom in rebuttal suggested that the subject property was superior to various
of the comparable sales because the subject property had better views and was
not near commercial development. Mr. Elsom conceded that one of the comparables
that we are relying on did have a view (Mr. Blanchette's number 8, Ms. Watson's
number 6) and in any event we accept the two appraisers' opinion that the lot
values on these three sales were comparable. •
Townhouse [139] Ms. Watson provided the only evidence for
the value of townhouse sites. She used four comparable sales for the 4.01 acres
of the subject property to be used for townhouses. These sales ranged from 1.47
acres to 7.04 acres with a projected range in density of 8.8 to 13.1 units per
acre. These sales provided a range of values per unit of $11,688 ($12,813 after
correction) to $17,283. She concluded a value of $15,000 per unit for the lakeside
units and $12,000 per unit for the others. The valuation for the 44 townhouses
sites was $582,000 undiscounted or $145,137 per acre. [140]
We have concluded that the multi-family units in the before layout should be located
on the subject property. We note that Ms. Watson's comparable sales were corrected
during the hearing with the result that the lowest was $12,813 per unit. In our
opinion the two lowest sales were less desirable than the multi-family sites on
the subject property because they were at a higher density. We conclude a base
value of $14,000 per unit. Assuming the same total area of 8 acres, with the same
density of townhouses we conclude a total of 85 townhouses is reasonable. Because
we are using a general layout, we are not including a lake and we value all the
townhouses at $14,000. We conclude a total valuation of $1,190,000 undiscounted
for all the multi-family unit sites or $148,750 per acre. •
Neighbourhood commercial [141] Again the only evidence
we have about the value of neighbourhood commercial is from Ms. Watson. She used
seven comparable sales to value the 1.2 acres or 52,255 square feet of the subject
property that was to be used as commercial. These sales yielded a range of $4.41
to $11.91 per square foot and after adjustment for location Ms. Watson concluded
a value for the subject of $6.50 per square foot. This provided a value of $339,658
undiscounted or $283,048 per acre. [142] We have decided
to use 1.4 acres of commercial rather than the 1.2 acres used by Ms. Watson. At
the same valuation per square foot this provides a valuation of $396,266 undiscounted
or $283,048 per acre. 7.3.3.5
Easements [143] Ms. Watson adjusted her total before
valuation of $11,058,017 for the actual land that was occupied by the four easements.
She assumed an average value per acre of $74,944 from this total before valuation.
She reduced the value of the land that was encumbered with overhead transmission
lines by 60%. (This was not a reduction to all the raw lots that were partially
encumbered, but a reduction only to the land with the encumbrance.) The land with
an unused easement for overhead transmission lines was reduced 30%. Land with
underground water, gas, or sewer pipelines was reduced by 50%. An area encumbered
by both overhead transmission lines and a gas pipe line was reduced by 80%. The
total of 19.31 acres that were occupied by encumbrances were reduced in value
from $1,447,326 to $611,419 for a reduction of $836,000. [144]
Mr. Blanchette made no adjustment for easements. While his report contained a
useful map of the easements, there is no indication in the text as to the total
area of each easement. Although Mr. Buchan provided us with many calculations
of area including the area of the overall layout, the area of the subject property,
the area of the first taking and the area of the second taking, he did not provide
us with any area for the easements. [145] The layouts of
both parties had fewer lots as a result of the easements. Mr. Buchan's layouts
left corridors on most of the electrical easements, with no lots placed on them.
Mr. Buchan did place lots on portions of the underground high-pressure gas easement.
The layouts developed by Mr. Jorden and Mr. Kruger, included most of the easement
area in the lots and as a result a number of lots were larger than average. This
approach also resulted in fewer lots. [146] Ms. Watson
stated that she obtained the percentage deductions for the actual land encumbered
by various types of easements from the literature and cases rather than from market
value analyses. Market value information provides a measurement of the impact
of easements on individual serviced lots and she used this information in the
Subdivision Residual Approach. Ms. Watson described the deductions that she used
for each easement in the Subdivision Residual Approach. For the unused electrical
easement she reduced a serviced lot 2%, for an underground gas easement she reduced
a serviced lot 3% and for double easements of both electrical and gas she reduced
the value of the serviced lot 10%. She did not provide the percentage deduction
for electrical easements alone but it must be between the 3% for an underground
gas easement and the 10% for both an underground gas easement and an electrical
easement. We conclude 8% is appropriate. During cross-examination she went on
to testify that because the cost of servicing is not effected by the easements
the appropriate deduction for raw unserviced lots was approximately twice the
deduction for serviced lots; namely, 4%, 6% and 20% (and 16% for the electrical
easement). [147] We note that the basis of the Direct Comparison
Approach for both Ms. Watson and Mr. Blanchette is the market value per raw lot.
We were able to determine the deductions for the four different types of easements
by counting how many raw lots on Mr. Jorden's layouts had each type of easement
and applying these deductions of 4%, 6%, 20%, and 16%. When we added up the total
deductions for all the raw lots with different types of easements we obtained
a deduction of less than $450,000 undiscounted. When we discounted the deduction,
in accordance with Ms. Watson's allocation of lots to one of her three phases
of development, the total deduction for different types of easement dropped to
less than $350,000. These numbers are much lower than the $836,000 deducted by
Ms. Watson using her various percentage deductions for acreage land with easements.
In our opinion, these two models for measuring the impact of easements should
yield somewhat similar results, although the percentage deduction for acreage
land includes land that will be used for roads and sidewalks. Since the basis
of the valuation in this Direct Comparison Approach is the market value per raw
lot, rather than per acre, we conclude that the adjustment using 4%, 6%, 20% and
16% of the raw lot value is a better measure of the impact of easements. [148]
We are using a general layout with 60-foot lots rather than Mr. Jorden's layouts
with 66-foot lots (although Mr. Jorden's before layout does use 60-foot
lots in the Doncaster Phase 1 subdivision and 15 of these lots are affected by
easements). We have reviewed Mr. Buchan's layouts that use 60-foot lots. We note
that although Mr. Buchan did not place lots on some of the electrical easements,
in our opinion, those lots that back onto the electrical easements with overhead
transmission lines would be effected in a similar manner as Mr. Jorden's lots
that actually included some of the electrical easement. We also note that our
general layout already contains a downward adjustment for easements because the
density takes into account that there are fewer lots as a result of the easements.
However, in our opinion, this reduced density is not a sufficient measure of the
impact of the easements. Taking all of the evidence into account, we conclude
that a specific deduction for easements of $350,000 should be made in addition
to the reduced density. This deduction assumes a discount for three years for
all of the lots in our general layout except those in the Doncaster Phase 1 subdivision. 7.3.3.6
Size of subject property [149] Mr. Blanchette made
no adjustment for size or risks or time but for the one year deferral to obtain
a comprehensive development plan that he added in a supplementary report. Ms.
Watson made a 10% adjustment to the overall value for the large size of the subject
property, the greater uncertainty with respect to development, and the increased
time frame to obtain necessary approvals, to install servicing and to obtain revenues
from the sale of the lots. [150] We have included one aspect
of this, the time frame to obtain necessary approvals, in the deferral time of
three years for most of the subject property that is discussed above. But, there
must still be a consideration for the great difference in size of the subject
property and the related problem of time to install servicing and time to obtain
revenues from the sale of the lots. The comparables were for small developments
where the time for absorption would be short. The size of the subject property
also means that there was a greater risk associated with its development. In the
circumstances, we agree with Ms. Watson that a 10% adjustment for these factors
is reasonable. 7.3.4 Market Valuation
Before the Taking -- Conclusion [151] Thus our final
valuation for the subject property before the taking using the Direct Comparison
Approach is as follows:
| | 48 single family
lots at $28,000 | | | = | $
1,344,000 | | |
490 single family lots x $28,000 | = | $13,720,000 | | |
| | 85 townhouses at
$14,000 | = | $
1,190,000 | | |
| | 60,964 sq ft commercial
at $6.50/sq ft | = | $
396,266 | | |
| | Subtotal | | $15,306,266 | | |
| | | | | |
| | Deferred three
years | | | | $11,191,941 |
| | | | |
| | | Subtotal | | | | $12,535,941 |
| | Easement adjustment | | | | –
$ 350,000 | | | Size
adjustment | | | | –
$ 1,218,594 | | | | | |
| | | Total | | | | $10,967,347 |
This valuation before the taking of $10,967,400
rounded yields a value of $74,608 per acre rounded for 147 acres. 7.3.5
Check using large properties [152] Ms. Watson compared
her final value of $9,200,000 for the subject property before the taking
($62,348 per acre) to two other sales of large development sites in the Lower
Mainland. One of these was the sale of the B.C. Penitentiary site in New Westminster,
a 71 acre site, of which 37.9 acres was developable. The sale price of $5,000,000
in April 1986 was based on 820 multi-family units and 73 single family lots. This
price yielded a value per net acre of $131,926 (or $70,383 per gross acre). Ms.
Watson comments that this sale is difficult to compare with the subject property
because it is more urban with higher density development. [153]
The other sale of a large development site was Riverview Heights, a 128 acre development
site in Coquitlam. This sale, like the subject property, was for primarily single
family residential development (571 single family lots and 94 townhouses). The
sale price was $20,564,997 in June 1985. However, Ms. Watson reported that the
sale terms provided for a phased development with the developer being required
to pay for the land in each phase when it came on stream with no interest. When
she discounted the price in accordance with the sales contract and adjusted for
single family only, she stated that the adjusted value for each raw lot was $19,650
(at 4.75 lots per acre) or $93,346 per acre for the single family land. She pointed
out that these provisions in the sales agreement significantly decreased the risk
for the developer. There were also services worth $3,300,000 in place. Ms. Watson
stated that her valuation of $62,348 per acre for the subject property, which
included adjustments for the easements and the associated lower density, together
with the lack of approvals, was supported by the adjusted price of $93,346 per
acre for the single family portion of the Coquitlam property. We note that the
unadjusted price for the whole Coquitlam property was $160,514 per acre. [154]
Ms. Watson's description indicates that the Coquitlam site has a number of features
in common with the subject property, such as overall size, proposed density, proposed
mix of single-family and townhouse, date of sale, projected servicing costs and
projected sale price of the subdivided (somewhat smaller) lots. Differences include
the fact that the subject property has significant easements and no approvals.
We also have to assume a sale price for the subject property that is independent
of financing and includes the various risks of development of a large parcel.
However, given the number of similarities, we would have appreciated more details
on this transaction. Ms. Watson adjusted the sale price of the Coquitlam property
from $160,514 per acre to $93,346 per acre to take into account the financing
terms in the sales contract and the multi-family component, but we were not provided
with the details of that adjustment. Her valuation of $62,348 per acre for the
subject property included the multi-family and commercial components and therefore
the adjustment of the Coquitlam property to exclude the multi-family appears to
be inappropriate. In the final analysis, we were not provided with sufficient
evidence about the Coquitlam property and Ms. Watson's adjustment to provide any
meaningful comparison with the valuation of the subject property. 7.4
Market Valuation After the Taking 7.4.1 Claimants'
position [155] After the taking the claimants'
layouts showed a drop in the number of 60-foot lots on the subject property from
635 to 552, assuming no overpass, or to 548 assuming an overpass would be built.
Mr. Buchan testified that he had made efforts to be consistent with 60-foot lots
both before and after the taking which meant that he modified
the layouts that were actually achieved on Lot 112 and Lot 666 since they were
developed with 50-foot lots. He used the actual layouts for Doncaster and Harrogate
in the after scenario. In addition, Mr. Buchan increased the length of
lots bordering Nordel Way and the 84th Avenue connector in the after layout
so that they were at least 120 feet instead of the more general 100 feet. This
was to partially mitigate the effect of noise from Nordel Way on these lots. Mr.
Blanchette, relying on Mr. Buchan's layouts, concluded a value after the
taking of $14,909,000 (548 lots x $30,000/lot discounted for one year at 10%). [156]
Mr. Blanchette deducted his after value of $14,909,000 from his before
value of $17,273,000 for an opinion of value of the 4.6 hectares (11.46 acres)
that was taken of $2,364,000. To this sum, representing only the value of the
lots lost in the taking, Mr. Blanchette added two additional amounts for injurious
affection to the remaining land. First, with respect to noise he made an 18% downward
adjustment in the value of the 112 lots that backed onto Nordel Way or the 84th
Avenue Connector as well as a lesser adjustment of 10% for the eight lots that
backed onto the overpass. After estimating the effect of these adjustments on
the raw lot values he calculated a net reduction in value for noise of $1,195,000
rounded. [157] Second, relying on figures obtained from
Hub Engineering he concluded an increase in net servicing costs. Although Mr.
Buchan's estimation of the total servicing costs after the taking were
lower than in the before scenario, the servicing costs per lot after
the taking were somewhat more per lot than before. Mr. Blanchette used
this extra cost per lot to calculate the total additional servicing costs
after the taking. From this he subtracted Mr. Buchan's estimate of the benefit
to the claimants as a result of the Ministry installing a storm sewer under Nordel
Way with connections for any future development. The net increase in servicing
costs was approximately $110,000. [158] Finally, Mr. Buchan
calculated the extra costs for a number of items that may be required as a result
of the taking which was amended to $519,000 in argument. [159]
Thus Mr. Blanchette's total claim (as amended) for the market value of the land
that was taken plus injurious affection for noise and a net increase in engineering
costs and additional costs was $4,188,000. [160] Mr. Elsom
valued the 11.46 acres lost in the taking at $160,000 an acre for a total claim
of $1,833,600 for the loss in market value as a result of the taking. He did not
make any further claims for the impact of the taking on lot layout, noise, or
engineering costs. 7.4.2 Respondent's
position [161] Ms. Watson did not do a Direct Comparison
Approach after the taking. However, aspects that she used in the Subdivision
Residual Approach can be applied to her Direct Comparison Approach in the
before situation. After the taking the Ministry's layouts showed 490
single-family lots, 57 townhouses, and 1.4 acres of commercial space on that part
of the subject lands owned by the claimants. This was a decrease of 49 single-family
lots. As described above, after the taking, the actual layouts for the
four subdivisions that have actually been built were used and all of these were
smaller at 60 or 50-foot. On the other hand, after the taking, most of
the 79 lots in the Ministry's layouts that bordered Nordel Way and the 84th Avenue
connector were larger as they had been lengthened in order to partially alleviate
the noise factor. [162] With respect to multi-family units,
there was a shift in their location after the taking from an area near
the lake to an area at the intersection of Nordel Way and the 84th Avenue connector
near the new commercial site. Because of the shift in the location, the number
of townhouses on the subject property increased from 44 before the taking
to 57 after. Most of the townhouse units (38) continued to be valued at
$12,000 while the 19 townhouses in the new location near the commercial site were
valued at $11,000 per unit. [163] As a result of the taking
a new commercial site of 1.4 acres was created adjacent to Nordel Way, near the
intersection with the 84th Avenue connector. Ms. Watson used six comparable sales
of gas station sites that ranged in value from $9.43 to $15.09 per square foot.
She concluded a higher value for the new commercial site in the range of $10.00
to $12.00 per square foot for the 61,000 square feet and used the low end of that
range or $10.00 per square foot in her valuation. [164]
If these numbers are inserted into the Direct Comparison Approach model used by
Ms. Watson in the before scenario, the total valuation after the
taking was approximately $10,479,000 before any considerations for easements or
noise or engineering costs. [165] As we have already indicated,
Ms. Watson initially used a before and after approach based on
the Subdivision Residual Approach to measure the value of the taking. In her
after valuation, she provided a 15% downwards adjustment for noise for the
79 fully serviced lots and 19 townhouse units that now backed onto Nordel Way
or the 84th Avenue Connector. With respect to the servicing costs, Ms. Watson
relied on Mr. Kruger's estimates that the taking would result in a decrease of
$890,000 when adjusted for the subject property only. When she subtracted her
after valuation from her before valuation she obtained a difference
of only $311,114. [166] Subsections 40(3) and (5) of the
Act provide that the minimum valuation in a partial taking must be "the amount
determined by multiplying the ratio of the area of the land taken to the area
of all of the land before it was taken, times the value of the land before it
was taken", with adjustments to take into account land that is more or less
valuable than the average value. Although Ms. Watson does not set out the calculation
for this minimum valuation of the taking, based on her conclusion on the market
value of the whole subject property before the taking, it would appear
to be approximately $630,000 rounded. Ms. Watson's valuation of $311,114 for the
taking using the before and after valuations was well below this
minimum valuation. As a result of Ms. Watson's before and after
valuation falling below the minimum valuation set out in section 40(3) she had
to resort to section 40(3) and (5) for her final valuation. However, Ms. Watson
did not use the straight percentage calculation found in section 40(3) because
she was of the opinion that some of the land in the taking was more valuable and
some was less valuable than the average land. She stated that the land taken closest
to Phase 1 (Doncaster) and Phase 2 (Harrogate) of the development was more valuable
than the average land value because, at the valuation date, development of these
areas was more imminent. On the other hand, the land that was taken that was encumbered
by various easements was less valuable than the average. She concluded a market
valuation of $874,000 for the land taken based on the value of each lot and townhouse
unit site that she said was lost in the taking, adjusted for the stage of development
and for the different easements. Because she has resorted to section 40(3) and
(5), there is no provision in this minimum market valuation of the taking for
any injurious affection for such factors as noise. 7.4.3
Market Valuation After the Taking -- Board's Analysis [167]
There is a huge difference in valuation for the land taken between the claimants
at $4,188,000 and the respondent at $874,000. As we have described above, the
two main reasons for this large difference are Ms. Watson's greater deferral for
lack of approvals and Mr. Blanchette's adjustment for lot density. Because of
these factors, Mr. Blanchette's valuation of the 11 acres of land taken alone
is $2,364,000. Mr. Blanchette has added two sums to this market value for the
effect of noise, $1,195,000, and the net extra engineering costs, $110,000 plus
$519,000, as a result of the taking. While Ms. Watson also considered the effect
of noise after the taking, it was more than offset by the more valuable
commercial site in her valuation model and the $890,000 savings in engineering
costs. As a result of resorting to the minimum provisions set out in section 40
of the Act, her final estimate of valuation omits the effect of noise and the
engineering costs and depends only on market valuation of the single family lots
and townhouse sites that she says were lost by the taking, adjusted for easements
and discounting. [168] Ms. Watson's final valuation of
$874,000 was based on a summation approach in which she valued the units that
she states were lost in the taking, adjusted for the presence of easements and
ripeness for development. Although Ms. Watson's report was lengthy and detailed
this final valuation was based on one small chart with little supporting narrative.
A close review of the calculation reveals that it contained two significant mistakes.
Her report clearly described that in the before and after layouts
developed by Mr. Jorden and Mr. Kruger the number of townhouses on the subject
property increased in the after layout from 44 units before the
taking to 57 units after, a gain of 13 townhouse units. However, during
the hearing one of the panel members pointed out that the chart, in which she
calculates the final valuation of the taking, assumes 10 townhouse units have
been lost in the after layout. After discounting, 10 lost units amounted
to a mistake of $87,743 when, in fact, the gain of 13 units meant that $114,062
should have been deducted. These two together mean that the loss in market value
was overestimated by $201,800 or almost 25%. [169] A second
mistake was that she applied the adjustments for land area affected by various
easements ranging from 30% to 80% used in her Direct Comparison Approach to raw
lots when only part of the raw lot was affected by the easement. As Ms. Watson
explained in cross-examination the appropriate percentage adjustment for the different
easements on serviced lots ranged from 2% to 10% and the appropriate percentage
adjustment for raw lots ranged from 4% to 20%. This is much less than the 30%
to 80% that she used in this final estimation of value. As a result the effect
of the easement was significantly overstated and that part of the total valuation
was understated by approximately $140,000. (It would have been greater but the
discounting for time was not applied consistently.) This error for the effect
of easements was in the opposite direction of the error concerning the alleged
loss of townhouses, and as a result Ms. Watson's final valuation should have been
approximately $60,000 lower or approximately $815,000 instead of just less than
$875,000. This mistake was not identified at the hearing. 7.4.3.1
Layouts and comparables • Townhouses [170]
We have already indicated that it is equitable if the more valuable uses of multi-family
and commercial are not increased after the taking as they were by the
respondent. But a taking of over 11 acres may decrease the amount of land for
these uses. Before the taking we had 85 townhouse units on 8 acres.
After the taking we conclude 78 townhouses on 7.4 acres is appropriate. Ms.
Watson valued the 19 lots near the new commercial site at only $11,000 per unit
because of proximity to the highway and the commercial site. This is less than
any of her comparable sales for townhouses. Because the main factor in the proximity
to the highway is noise, which we consider separately below, we apply the valuation
of $14,000 to all of the townhouses. This provides a total of $1,092,000 undiscounted. •
Commercial site [171] The new commercial site after the
taking is at the location of Nordel Way and the 84th Avenue connector. This location
has a potential of being more valuable because of its proximity to the highway
and the exposure to highway traffic, even though a potential purchaser would have
some concerns about access and obtaining approvals. After reviewing the evidence,
we are satisfied that a purchaser would allocate a higher value to this site. [172]
No statutory provisions that might have application to this issue were raised
in the hearing. Nonetheless, we have considered the effect of sections 33, 40
and 44 in the context of a partial taking and the valuation of the remainder of
the subject property after the taking. These sections provide: 33
In determining the market value of the land account must not be taken of
… (d) an increase or decrease in the value of the land
resulting from the development or prospect of the development in respect of which
the expropriation is made, (e) an increase or decrease
in the value of the land resulting from any expropriation or prospect of expropriation, (f)
an increase or decrease in the value of the land due to development of other land
that forms part of the development for which the expropriated land is taken, …
40
(1) Subject to section 44, if part of the land of an owner is expropriated, he
or she is entitled to compensation for (a)
the market value of the owner's estate or interest in the expropriated land, and (b)
the following if and to the extent they are directly attributable to the taking
or result from the construction or use of the works for which the land is acquired: (i)
the reduction in the market value of the remaining land; …
44
(1) If part of the land of an owner is expropriated, and the expropriation or
the construction or use of works by the expropriating authority are of special
benefit to that owner or to his or her remaining land beyond any general benefit
to any other owner benefited by the expropriation or the construction or use,
there must be deducted from the amount of compensation payable to that owner the
estimated value of the benefit. (1.1) If part of the land
of an owner is expropriated, and the expropriation or the construction or use
of the works for which the expropriated land was acquired are of any benefit to
that owner, the estimated value of the benefit must be deducted from the amount
of compensation otherwise payable to that owner, under section 40 (1) (b) (i),
for the reduction in the market value of the remaining land, whether or not any
other owner is benefited by the expropriation of the expropriated land or by the
construction or use of the works.
In our view
these sections must be read together. After the taking the intent of the legislation
when read as a whole is to provide the owner with compensation for a reduction
in the market valuation of the remaining land caused by the taking or the construction
of the works for which the land was acquired. This would include such factors
as a reduction in market valuation of the remaining land caused by noise from
the highway for which the partial taking was made. Similarly, the legislation
when read as a whole makes clear that any benefit the owner receives for the remaining
land as a result of the taking or the construction of the works for which the
land was acquired, is to be taken into account in the overall compensation. Although
section 33 states that "an increase or decrease in the value of the land
resulting from the development … in respect of which the expropriation is made"
is to be ignored, we must construe "the land" in this section to mean
something other than the remaining land after a partial taking. We conclude that
the new commercial site as part of the remaining land with an increased value
after the partial taking as a result of the Project, is to be taken into
account when we are determining compensation. The fall-back provision in section
40(3) of the Act will come into play if, as a result of all the negative and positive
effects arising from the partial taking, the difference in value between the
before and after is less than the pro rata value of the taking. [173]
We agree with Ms. Watson's valuation at the low end of her comparables of $10.00
per square foot for the 1.4 acre site which provides a total of $609,640 undiscounted. •
Single Family Lots [174] After the taking we have
concluded that 7.4 acres of the subject property will be multi-family use and
1.4 acres will be commercial. The park area is slightly smaller at 6.8 acres since
the subject property is now smaller. There also is an area near the school board
property on Dunlop Road that is severed after the taking and cannot be
developed. This severed area in the claimants' layout is somewhat larger at 1.6
acres than this area in the respondent's layout at 1.15 acres. We prefer the claimants'
allocation because it did not depend on lots being placed on the school board
property when we do not know if the hypothetical purchaser will be able to acquire
it. Finally, we note that the allowance of 2 acres for the Browning Drive right
of way is no longer necessary as Highway 91 has made this right of way unnecessary.
This, like the more valuable commercial site discussed above, is a factor that
is properly taken into account when determining the compensation to which the
owner is entitled. As a result we conclude that there are 118 acres available
for single family lots. [175] Before the taking
we used a density of 4.2 lots per acre. This density took into account the lack
of either an engineered or an approved layout. After the taking, both
appraisers lengthened between 79 and 112 lots to partially mitigate the effect
of noise. This would result in a slightly lower density compared with before
the taking. However, we no longer have an engineered layout and we conclude that
it is more equitable if the density of the lots is the same after the
taking as before and consider an adjustment for noise separately. As a
result we conclude that a density after the taking of 4.2 is appropriate. [176]
With 118 acres at a density of 4.2 we estimate a total of 496 single family lots
(rounded up) after the taking. At $28,000 per lot this provides a valuation
of $13,888,000 undiscounted. 7.4.3.2
Easements [177] Similar adjustments for easements need
to be made in the after valuation as in the before. After reviewing the layouts
and the percentage reduction for lots on each type of easement, we estimate that
an adjustment of $300,000 is appropriate after the taking. Since the taking included
portions of the electrical easements, fewer lots are effected by easements after
the taking and the relative size of this adjustment is less than the adjustment
for easements before the taking. 7.4.3.3
Size of subject property [178] After the taking an
adjustment of 10% for size and the uncertainties and risks associated with size,
including the increased time frame to obtain revenues from the lots, is again
appropriate. 7.4.3.4 Noise [179]
Both appraisers adjusted the lots in their layouts that bordered Nordel Way and
the 84th Avenue connector for noise. Mr. Blanchette purported to make an 18% adjustment
to the value of each of 112 raw lots. In fact, his adjustment was close to 35%
because he stated the effect on raw lots should be higher than the percentage
based on serviced lots, because the costs of developing the raw lot would be unaffected
by noise. Ms. Watson made a 15% adjustment to the 79 serviced lots and to 19 of
the townhouse units that backed onto Nordel Way and the 84th Avenue connector
in her Subdivision Residual Approach. She stated that she also made a 10% adjustment
for those lots that bordered two other arterial routes, 84th Avenue (in the
before scenario only) and Dunlop Avenue (in the before and after
scenario). She did not provide us with the number of lots and townhouse units
that were adjusted for noise with respect to these other arterial roads. [180]
Mr. Blanchette's total adjustment for noise on the raw lots was $1,195,000. One
of the reasons for this number being so high is that although Mr. Blanchette eventually
discounted his before and after valuation for one year, he did
not discount the valuation for noise at all even though it was calculated on the
basis of a percentage effect on the value of raw lots. [181]
Both appraisers based their adjustments for noise on the sales of lots in the
Doncaster and/or Harrogate subdivisions. In 1987 Doncaster lots that backed onto
Nordel Way sold for an average of 16% less than interior lots sold in that year
but in the other two years the decrease was less than 10%. When the sale prices
for the Harrogate subdivision were reviewed, the effect of noise was much diminished.
Harrogate lots that backed onto Nordel Way sold for an average of only 2 and 3%
less than interior lots in both 1988 and 1989. Dunlop Road also had an effect
on lot sale prices although this too was diluted in the Phase 2 Harrogate subdivision.
Mr. Blanchette used only the evidence from the Doncaster subdivision and ignored
the more equivocal evidence from the Harrogate subdivision. We note that the Doncaster
lots that back onto Nordel Way all contain an easement for the B.C. Electric right
of way as well as a GVRD trunk watermain, both of which likely had a negative
impact on the market value of these lots. These two rights of way were not present
in the Harrogate subdivision. This evidence from the Doncaster and Harrogate subdivisions
were for serviced lots, and although there is no data for raw lots we would expect
the effect to be higher. [182] We were also provided with
two reports from acoustical engineers as to the effects of traffic on Nordel Way
on the noise levels at various locations on the subject property. These reports
indicated that the maximum acceptable noise level in a back yard was about 55dBA
based on 24 hour noise levels. Before the construction of the Project
in 1980, properties adjacent to the subject property recorded background noise
levels in the range of 53 to 56 dBA. After the Project, noise levels beside
Nordel Way or the 84th Avenue connector were between 70 and 75 dBA. However, noise
levels in the backyards of Doncaster lots backing onto Nordel Way, but with a
berm, were recorded at 55.8 and 56 dBA. Areas adjacent to the Project but without
a barrier recorded noise levels of 60.9, 61, and 69 dBA at a distance that approximates
the exposed face of a residence. Noise levels were higher on the pedestrian walkway.
The barriers appeared to lower the noise level between 5 and 10 dBA. One of the
reports concluded that barriers would effectively reduce the noise level and that
further analyses would be necessary before development to consider setbacks and
the relative elevations of the roadways and residences. [183]
This evidence shows that Mr. Elsom's work on creating berms has decreased the
effect of noise. We also note that much of Nordel Way is below grade and in a
cut, which also helps to reduce the effect of noise. We were not provided with
any evidence as to how much of the subject property is protected by berms. Given
the sketchy evidence on the extent of the berms, together with the minor impact
of noise on the sale prices for Doncaster and Harrogate, and the contributory
effect of the easements on the sale prices in Doncaster, we conclude an adjustment
of 20% for raw lots that back onto Nordel Way and 10% for those raw lots that
front onto arterial roads. [184] Since we no longer have
detailed layouts, it is more difficult to say how many lots would be impacted
by the noise. However, because the commercial site would be located on Nordel
Way and the 84th Avenue connector, as well as some of the townhouse units, the
total number of single family lots that are effected would be closer to Ms. Watson's
79 than Mr. Blanchette's 112. Of course, these townhouse units adjacent to Nordel
Way would also be affected by noise. We also agree that the impact of noise from
Nordel Way and the 84th Avenue connector after the taking should be partially
offset by the impact of noise on those lots and townhouses fronting onto 84th
Avenue before the taking. (We assume that the number of single family
lots fronting onto Dunlop Road is approximately the same before and
after the taking.) Doing the best we can with the evidence available, we estimate
that the net adjustment for noise, after appropriate discounting is $375,000.
We note that this is a net adjustment that takes into account the effect of noise
on those lots and townhouses on 84th Avenue before the taking. 7.4.3.5
Servicing costs and additional engineering costs, including an overpass •
Servicing costs [185] The claimants say that the net servicing
costs applicable to the subject property with respect to the site layouts are
approximately $110,000 greater after the taking, then before, while
the respondent claims that they are approximately $890,000 less. There were also
claims for various extra items such as street lights on Nordel Way which are discussed
below. The main difference in engineering costs was that in the after
scenario, the Ministry had installed a storm sewer as part of its construction
of Nordel Way with seven or eight connections for any future development on the
subject lands. Mr. Buchan represented the claimants when this storm sewer was
constructed and ensured that it would have sufficient capacity for any anticipated
future development. There were also some sleeves or ducts installed under Nordel
Way to accommodate future installation of such services as water mains and cables. [186]
Mr. Buchan provided the engineering evidence for the claimants. He calculated
the engineering costs for his layouts before and after the taking
using some of the actual costs for the Doncaster and Harrogate subdivisions constructed
in 1986 and 1987. He estimated the expenses per metre for two different types
of roads in the Doncaster and Harrogate subdivisions and then applied these estimates
to the different types of roads in his site layouts. He assumed average pipe sizes
in this exercise. While the total cost after the taking was less, when
it was expressed per lot, the cost per lot after was more than three hundred
dollars greater than before the taking (out of total costs of approximately
$10,000 per lot). Mr. Blanchette calculated the additional servicing costs by
multiplying this extra cost per lot after the taking by the number of
Delsom lots after the taking for a claim of $218,592 (assuming no overpass). [187]
Mr. Buchan also attempted to allow for the benefit to the claimants as a result
of the Ministry installing a storm sewer under Nordel Way with connections for
any future development. Mr. Buchan calculated the cost for Mr. Elsom to install
this storm sewer in both the before and after situation. He estimated
Mr. Elsom's percentage use of this storm sewer after the taking and concluded
a net benefit of storm sewer at $108,594. He deducted this benefit from the extra
engineering costs that he thought the claimants would incur as a result of the
taking. Restricting the extra engineering costs to the $218,592 incurred with
respect to the site layouts, and deducting the benefit as a result of the storm
sewer leaves a net engineering cost of $110,000. [188]
Mr. Kruger, the engineer for the Ministry, prepared conceptual servicing plans
for the site layouts both before and after the taking. The total
servicing costs after the taking decreased approximately one million
dollars, or approximately $890,000 with respect to the share of the overall costs
allocated to the subject property. The cost per lot was approximately $11,000
per lot with the cost after being approximately $700 per lot less than
before. These costs were used by Ms. Watson in the Subdivision Residual
Approach as part of the estimate of market value for the land. This savings in
engineering costs after the taking was one of the reasons that Ms. Watson
ended up discarding the before and after approach and resorting
to the minimum valuation in section 40(3) of the Act. [189]
We recognize that having rejected portions of both appraisers' evidence, our valuation
is not based on an engineered layout. Nonetheless, in our opinion it is possible
to make some general findings on the engineering costs. [190]
We heard six days of engineering evidence. Both parties demonstrated some errors
or omissions in the other side's engineering evidence, which is not surprising
in an estimate of engineering costs for a hypothetical 150-acre subdivision. We
agree with the Ministry that a model based on conceptual servicing plans showing
all the services before and after the taking, including the storm
sewer under Nordel Way provides a better estimate than a model that assumes average
costs per metre of road for average sized pipes based on partial costs of the
Doncaster and Harrogate subdivisions plus an estimate of the cost of a developer
constructing the storm sewer and off-setting part of this cost. In the absence
of an engineered layout we cannot rely on Mr. Kruger's estimate of the decreased
engineering costs per lot after the taking. However, having accepted Mr.
Kruger's conceptual servicing approach as preferable, and recognizing the presence
of the storm sewer in Nordel Way we conclude that there would be some cost savings
in the engineering costs per lot after the taking. •
Specific engineering costs -- street lights, acoustic fencing etc. [191]
Mr. Buchan provided evidence for four extra items that the claimants asserted
would be required and should be included in the market valuation after
the taking. These were as follows:
| Street
lighting on Nordel Way | $145,800 | 81
x $1,800 | | Acoustic fencing | $396,060 | 3,220m
x $123/metre | | L 200 improvements | $
35,860 | | | 84th connector
acceleration lane | $ 24,580 | |
| |
| | | | $602,300 | |
| 20 % engineering and contingency | $120,460 |
| | | | |
| Total | $722,760 | amended
to $519,000 | The
claim for 81 street lights were for the entire length of Nordel Way and the 84th
Avenue connector. Similarly the claim for 3,220 metres of acoustic fencing was
the length to line both sides of Nordel Way and the 84th Avenue connector. During
argument, however, the claimants conceded that there was some street lighting
already installed on Nordel Way and that there were areas where acoustic fencing
could not be required. As a result they amended their claim for street lighting
to 55 lights and for acoustic fencing to 2,220 metres, which with adjusted contingency
and engineering, (mistakenly omitted in the final submissions but included in
earlier estimates of Mr. Buchan) comes to a total of $372,060. The third claim
was for the cost of improvements to the existing access road to a large portion
of the subject property known as the L-200, which was built by the Ministry at
the time of the taking. Finally there was a claim for the cost for an acceleration/deceleration
lane on the 84th Avenue connector which the claimants said would be required by
Delta. When these four claims were added together as amended and the 20% engineering
and contingency added, the total final claim was reduced to $519,000. [192]
The Ministry submitted that in 1985 no extra street lights and no acoustic fencing
would have been required. None had been required when Doncaster and Harrogate
were subdivided. Any extra costs for the L-200 should be included in the after
engineering costs and should not be claimed as a separate extra cost. There was
insufficient evidence to support a claim for an acceleration lane on the 84th
Avenue connector. As a result it was the Ministry's position that no costs for
any of these four items should be awarded. [193] The evidence
that street lights might be required is from the claimants' 1992 subdivision application
to consolidate the portions of Lots 5 and 6 that were severed by the 84th Avenue
connector and Nordel Way (in the vicinity of the Chevron gas site). We note that
the relations at this time between Mr. Elsom and Delta were strained. Dr. Collier,
the Municipal Administrator for Delta, testified that there was an ongoing debate
on the issue of street lights and whether they could be requested for a road with
limited access such as Nordel Way (except in the region of the intersection of
Nordel Way and the 84th Avenue connector). During the hearing it was established
that there were some street lights installed at the upper end of Nordel Way but
no one was clear about who had installed them and when. [194]
There was no requirement for street lights on Nordel Way with respect to applications
for subdivision for Doncaster, Harrogate, or for the subdivisions built on Lot
112 and 666. In our opinion, a hypothetical purchaser would not have considered
there was any risk for the cost of installing street lights on Nordel Way in 1985.
These items were claimed in the alternative as a disturbance damage or business
loss under section 34 or 40. A review of the wording of these sections together
with all of the evidence indicates that the likelihood of a developer of the subject
lands being required to install street lights on a road with limited access is
very uncertain. As this board stated at para 70 in Bayview Builders Supply
(1972) Ltd. v. British Columbia (Minister of Transportation and Highways),
(2001), 75 L.C.R. 95 (B.C.E.C.B.) awarding costs as disturbance damages for a
possible event that may never occur is speculative. [195]
The claim for the cost for acoustic fencing is based on some fencing being required
on Lot 112 when it was subdivided in 1991. We do not have the documentation between
Delta and the subsequent owner of that property as to the details of precisely
what was required, although we understand from Mr. Kruger's evidence that approximately
half the border with Nordel Way or 100 to 110 metres now has acoustic fencing.
No acoustic fencing was required on subdivision applications for Doncaster, Harrogate,
or for the subdivision built on Lot 666. There is also no acoustic fencing adjacent
to Marlborough College, whose grounds border Nordel Way. [196]
We do agree that a hypothetical purchaser would have had concerns about the effect
of noise from Nordel Way on the project. However, we have adjusted the market
value of those lots for the effect of noise in the after situation. There
is a risk of double compensation if the cost of acoustic fencing, the purpose
of which is to mitigate noise, is awarded when a decrease in market value for
those same lots has been awarded assuming no acoustic fencing. See Patterson
v. British Columbia (Ministry of Transportation and Highways) (1994), 53 L.C.R.
88 (B.C.E.C.B.); aff'd (1997), 62 L.C.R. 89 (B.C.C.A.) where a number of cases
involving an overlap between reduction in market value and disturbance damages
are reviewed. In most of the cases where the cost of landscaping to mitigate noise
from a highway was awarded there was no award for reduction in market value. In
one Ontario case, Adams v. Minister of Transportation and Communications
(1978), 16 L.C.R. 183 (Ont. L.C.B.); var'd 20 L.C.R. 24 (Ont. Div. Ct.), the cost
for the landscaping to mitigate the noise as a result of the taking was allowed
by the board, but then that part of the reduction in market value due to the noise
was deducted. In this case we have made an award for a reduction in market value
as a result of noise, and this sum is greater than the claimants' entire claim
for acoustic fencing (as amended). We note that we were provided with evidence
that construction of barriers would be effective in reducing the noise levels,
but we were not provided with the evidence as to the length of Nordel Way and
the 84th Avenue connector that does not have berms and might benefit from acoustic
fencing. In summary we conclude that making an award for acoustic fencing in these
circumstances would be double compensation, although we recognize that a limited
amount of acoustic fencing may be required. [197] With
respect to the costs for the acceleration lane on the 84th Avenue connector, the
only evidence that this cost might be incurred was again from the 1992 application
to consolidate portions of Lot 5 and 6 that had been severed by Nordel Way and
the 84th Avenue connector. The Approving Officer enclosed a memo from the Development
Engineer indicating that any access off the north side of the 84th Avenue connector
might require an acceleration or deceleration lane. In our opinion there
was no reason in 1985 for the hypothetical purchaser to consider the risk of this
cost. Mr. Buchan has estimated the costs to provide the acceleration lane. However,
none of the subdivision layouts, including the most recent layout that had been
submitted as part of an application in 2001, showed any access road from the north
side of the 84th Avenue connector. Accordingly it is unclear to us what purpose
an acceleration/deceleration lane on the 84th Avenue connector would have. [198]
Finally, the cost to improve the L-200 is for the road that was a replacement
access to the remainder of 84th Avenue that had been blocked off at 108th Street.
When subdivision development occurred adjacent to L-200 or to 84th Avenue, our
understanding was that the developer would face costs to upgrade both of these
roads with such things as curbs and gutters, underground services, and new sewer
pipes. It was not made obvious to us that any upgrading of the L-200 was in a
different order of magnitude than the upgrading required on 84th Avenue. In any
event it is an engineering cost that should be included in the layouts for the
after scenario. As discussed above, Mr. Kruger has provided engineering
costs based on a before and after scenario and the costs to upgrade
L-200 or its equivalent were presumably incorporated in incorporated in the after
scenario. We have accepted Mr. Kruger's general approach to engineering costs
and concluded that the servicing costs per lot would be less after the
taking. We see no reason to award any extra cost to improve the L-200. •
Overpass [199] The claimants have claimed for the cost
of constructing an overpass and have used layouts that offer an overpass as an
alternative. The respondent has submitted that an overpass would not be required.
Ms. Watson stated that she relied on Mr. Jorden's conclusion that an overpass
would not be necessary. [200] At the time of taking in
May 1985, the evidence indicated that an overpass over Nordel Way was being discussed.
As an alternative to an overpass, connection for local traffic was contemplated
by an extension of the 84th Avenue connector through to Dunlop road. The Ministry
was in favour of this option but it was opposed by local residents who preferred
a four-way intersection further east at Brooke Road and 84th Avenue. As a result
of public opposition Delta vetoed the extension of the 84th Avenue connector.
At this time Delta was on record as supporting an overpass as a means to resolve
local traffic issues. The overpass featured in the settlement negotiations between
Mr. Elsom and the respondent, with the Ministry at one time agreeing that as part
of a settlement they would fund the construction of an overpass but not the connecting
roads. However, no settlement was ever reached and the Ministry withdrew its conditional
offer to pay for an overpass. Traffic studies done a number of years later de-
emphasized the need for an overpass and there was evidence that Delta staff would
not now take any position on the overpass. The issue would be referred to Delta
council and there was evidence that existing residents would likely oppose an
overpass. [201] In our opinion the significant date in
this matter is the date of taking and what would be in the mind of a hypothetical
purchaser of the subject property after the taking. Mr. Jorden's conclusion that
an overpass would not be required was based on hindsight using evidence long
after the taking and as a result we cannot rely on it when we are considering
the effect of the risk of an overpass on the market valuation. (We note that his
conclusion would be of assistance if we were considering the overpass as an item
of disturbance damages under sections 34 or 40.) In 1985 we think that any purchaser
would have considered that the requirement of an overpass was a possibility. On
the other hand the opposition of the existing residents to the extension of the
84th Avenue connector, and to any increase in traffic in the Sunbury and Canterbury
neighbourhoods was already known. This had been the main reason why Delta had
delayed in establishing the connector route through to 84th and 88th Avenue for
so long. A review of the documents shows that in 1985 Delta was open to various
options for local traffic connections if the overpass did not get built by the
Ministry. We conclude that a potential purchaser would recognize that there was
a risk for some financial contribution to an overpass, but that there were other
options being considered. [202] The fact that the Ministry
offered to pay for an overpass as part of a settlement negotiation when no settlement
was ever achieved makes this offer irrelevant. [203] We
have found that the servicing costs for the hypothetical general layout after
the taking would be less because of the storm sewer and connections under Nordel
Way. Nonetheless, we conclude that the hypothetical purchaser after the
taking would see the risks for the subject property with respect to the potential
engineering costs, including the risk of some contribution to an overpass, as
being on balance somewhat greater than before the taking. We estimate
that a potential purchaser would allow $500,000 as a net risk factor for
engineering and servicing costs, after taking into account the benefit of the
storm sewer under Nordel Way. 7.4.4
Market Valuation After the Taking -- Conclusion [204]
As in the before valuation everything but 48 single family lots should
be deferred three years at 11%. Thus the valuation for after the taking
is as follows:
| 48 single family lots at $28,000 | | | = | $
1,344,000 448 | | single family lots at
$28,000 | = | $12,544,000 | | |
| 78 townhouses at $14,000 | = | $
1,092,000 | | | | 60,964
sq ft commercial at $10.00/sq ft | = | $
609,640 | | | | |
| | | | Subtotal | | $14,245,640 | | |
| Deferred three years | | | | $10,416,411 |
| Subtotal | | | | $11,760,411 |
| Easement Adjustment | | | | –
$ 300,000 | | Size adjustment | | | | –
$ 1,146,041 | | Noise adjustment | | | | –
$ 375,000 | | Servicing and engineering
adjustment | | | | –
$ 500,000 | | | | |
| | Total | | | | $
9,439,369 | [205]
This valuation after the taking of $9,439,400 rounded yields a value of
$69,643 per acre rounded for 135.54 acres. [206] When we
deduct the after value that we have concluded from the before
value the difference is $10,967,400 - $9,439,400 = $1,528,000 rounded. This is
more than the minimum valuation set out in the equation found in section 40(3)
of $855,000. We conclude $1,528,000 as the compensation payable to the claimants
for the market value of the lands taken and the reduction in market value to the
remainder. We note that the claim for reduced lot yield is included in this compensation
amount and nothing additional is to be paid on account of this item. 8.
MARKET VALUATION OF THE RAVINE LAND TAKEN [207] Both
parties agreed that the 1.32 hectares (3.27 acres) of ravine land that was taken
in 1985 had little or no development potential. Mr. Blanchette, the claimant's
appraiser, used five sales of comparable properties most of which were not developable
because they were heavily encumbered by rights of way. These sales ranged between
$2,167 and $5,000 per acre and Mr. Blanchette estimated a market value for the
ravine land of $4,500 per acre. Ms. Watson, the respondent's appraiser, relied
on six sales of farm property and farm property acquired for parks that ranged
in value from $6,632 to $10,744 per acre. She valued some of the land taken at
$6,000 per acre and some of it that had no access or was both encumbered with
rights of way and had steep topography at $3,000 per acre. Mr. Blanchette's total
value of the ravine land taken was $15,000 rounded (3.27 acres x $4,500 /acre
= $14,715). Ms. Watson's was $13,890. [208] These estimates
of value differ by less than $1,000 and we award $14,500. 9.
MARKET VALUATION OF THE LAND TAKEN IN THE SECOND TAKING 9.1
Claimants' position [209] The second taking by the
respondent of narrow strips bordering a portion of Nordel Way and the 84th Avenue
Connector occurred in August 1995. Mr. Blanchette relied on Mr. Buchan, the engineer
for the claimants, who calculated this taking at 0.58 hectares (1.436 acres).
Mr. Blanchette used the Direct Comparison Approach and reviewed 10 sales of developable
land in late 1994 and 1995. After adjustments for various factors Mr. Blanchette
concluded a market value of $315,000 per acre, resulting in a market value of
the land with the embankments at $411,000 after discounting for one year for re-zoning. 9.2
Respondent's position [210] The respondent's pleadings
state that the second taking gave legal effect to a "de facto" expropriation
caused by the claimants building berms outside the right of way that was taken
in 1985. In the alternative the land that was the subject of the second taking
had no value in 1995 and the respondent pleads section 40(5) of the Act. [211]
Ms. Watson stated that this further taking was 0.55 hectares (1.36 acres) to complete
the taking to the top of the cut. Her figures were based on the plan by the land
surveyor dated August 3, 1995 that provided the legal basis for the taking. This
plan and two reports in which Ms. Watson valued different parts of this taking,
were entered as exhibits only during cross-examination. In these reports Ms. Watson
valued the lands taken in the second expropriation as of September 29, 1995. She
found that the land had no market value in September 1995 because the claimants
had effectively lost all rights and use of the land ten years earlier in May 1985
when the embankments were created. Ms. Watson confirmed that she had been instructed
to assume that the lands had been effectively expropriated in 1985, at the time
of the first taking. 9.3 Board's
Analysis and Conclusion [212] As described above, the
claimants, without any consultation, constructed embankments on either side of
the right of way some months before the first taking. The claimants had been provided
with detailed plans and used these plans to dig a trench up to 20 feet deep for
Nordel Way as an attempt to mitigate the impact of the roadway on future development.
They later submitted a bill for this work to the respondent. The embankments bordered
the proposed right of way but were located outside it. The first taking eventually
occurred in accordance with the existing surveys and the Ministry commenced construction
of the Project. As early as 1986 there was evidence that Mr. Elsom wanted the
boundaries of the taking expanded as he had no wish to own the slopes of the embankment
beside Nordel Way. These embankments were seeded and there was an issue as to
who was going to cut the grass on the slopes. Although Mr. Elsom wanted the fence
to be placed at the top of the slope the Ministry installed the fence near the
boundary of the right of way at the base of the slope. The dispute about whose
responsibility it was to maintain the grass on the sides of the embankments was
ongoing. At some point Mr. Elsom moved the fence erected by the Ministry to the
top of the embankment. There was evidence that Mr. Elsom offered to transfer the
slope for $1.00. There was also evidence that as part of the settlement negotiations
the Ministry took the position that the second taking should be valued as of the
date of the first taking in 1985 when the property had effectively been lost or
expropriated from the claimants. However, no settlement was reached on this matter
and in September 1995 the narrow strips of land bordering Nordel Way that formed
part of the embankment constructed in 1985 were expropriated by the Ministry. 9.3.1
Date of valuation [213] The first issue is the date
of valuation. Counsel did not refer us to any statutory provisions or authorities
to assist us in deciding this issue. Section 32 states that the land should be
valued as if "it had been sold at the date of expropriation". The date
of expropriation is defined in section 29 to mean "the date the vesting notice
is filed in the land title office under section 23". We understand that the
vesting notice was filed in August or September 1995. [214]
Although the formal taking occurred in 1995, the land's use was altered by the
claimants' own actions, when, in anticipation of the first taking in 1985 and
the construction of the Project, they constructed the cut for Nordel Way so that
the embankments were located outside the first right of way. The correspondence
indicates that both the Ministry and Mr. Elsom contemplated that there would be
a further taking to include these embankments soon after 1985 but the matter failed
to settle and for some reason the taking was delayed until September 1995. [215]
The issue is whether the date of the second taking was in May 1985 when the respondent
alleges that the narrow strips were the subject of a de facto expropriation
or, in the alternative, was in September 1995 when the vesting notice was filed.
The facts in this case suggest that a valuation in May 1985 might be appropriate.
However, given the unambiguous wording of sections 29 and 32 of the Act, we conclude
that we must value the lands taken in the second taking as of the date that the
vesting notice was filed in the land title office, not the date that the claimants
created the embankments. We agree with the reasoning in Premanco Industries
Ltd. v. British Columbia (Minister of Environment, Lands and Parks) (2000),
71 L.C.R. 6 (B.C.E.C.B.) at para 256 where this board refused to interpret section
46(4) in a way that required a rewriting of the statutory provision. Lacking specific
evidence of the date when the vesting notice was filed, we deem the date to be
September 1, 1995. 9.3.2 Effect
of Nordel Way on market value [216] The next issue
is whether the land in the second taking was valueless in 1995 because it consisted
of embankments and berms on either side of Nordel Way. Again counsel did not refer
us to any statutory provisions with respect to this issue. We note that section
32 of the Act says that the "market value of an … interest in land is the
amount that would have been paid for it if it had been sold at the date of expropriation".
Section 33(f) of the Act provides that when "determining the market value
of the land account must not be taken of an increase or decrease in the value
of the land due to development of other land that forms part of the development
for which the expropriated land is taken (emphasis added)." [217]
In 1995 the strips of land in the second taking were worth less as a result of
development of other land, namely the land in the first taking, in the construction
of Nordel Way and the 84th Avenue connector. As a result of section 33(f), we
are to ignore this decrease in value to the land in the second taking as a result
of the development of the Project and its proximity in the course of valuing this
land. We are also to ignore the physical nature of the land taken. The embankments
were created by the claimants in the course of making the cut for the development
of Nordel Way. Before the construction work, the land was development land similar
to the rest of the subject property. Section 33(f) requires us to reject the respondent's
submission that this land that forms part of the embankments bordering Nordel
Way and the 84th Avenue connector was valueless in 1995. 9.3.3
Size of second taking [218] There is again a discrepancy
in the areas reported for this second taking. Ms. Watson's two reports on the
second taking state that the total taking was 5,799 square metres (2,163 square
metres plus 3,636 square metres) which is equivalent to 0.58 hectares or 1.43
acres, the approximate size of the second taking as estimated by Mr. Buchan. However,
in Ms. Watson's main report she states that the second taking is 0.55 hectares
(1.36 acres). While there was no discussion of this discrepancy in the evidence
or submissions, an examination of the land surveyor's plan and one of Ms. Watson's
reports on the second taking shows that one parcel of land (Lot A) was not part
of the subject land in 1985. When the area for the second taking from this lot
is deducted, the total taking from the claimants' land is 5,496 square metres
which is equivalent to 0.55 hectares or 1.36 acres as stated in Ms. Watson's main
report. But by 1995 when the land that was the subject of the second takings was
actually expropriated, Lot A was occupied by the private school on land owned
by the claimants, which is presumably why it was included in the land surveyor's
plan. We have concluded that the effective date of the taking was in 1995 and
as a result we conclude that the taking was 0.58 hectares or 1.43 acres. 9.3.4
Market valuation [219] Mr. Blanchette provided the
only evidence on market value in 1995. He provided details of 10 sales of residential
development land in North Delta and Surrey ranging from $174,292 to $683,289 per
acre. He made adjustments that he stated were primarily for location, but also
for such factors as topography, shape, size and servicing. After adjustments his
range in value per acre was between $217,865 and $341,644, and after elimination
of the two sales at either end, the range was between $298,000 and $329,000. He
concluded a value of $315,000 per acre, which for 1.436 acres provided a valuation
of the second taking of $452,340 or $411,000 after discounting for one year. [220]
We found Mr. Blanchette's descriptions of these sales lacking in detail and he
offered little justification for his adjustments. A 10% downward adjustment for
size was made for one sale, for example, while nothing was said about adjusting
five other even smaller parcels for size. A 50% downwards adjustment for servicing
was made for one sale with no indication of the servicing requirements or their
costs. Another sale was adjusted for location and physical features with no explanation
about either factor. It is of interest that he made a 25% adjustment for a hydro
easement for one of these comparables, when no adjustment had been made for easements
on the subject property in his before valuation. Mr. Blanchette's adjustments
result in a relatively tight range of estimates of value, but we were provided
with little reasoning to support them. We also note that little, if anything,
was said about the zoning or stage of subdivision approval that was in place for
any of the comparables. At the time of the second taking, the subject property
still did not have any approvals in place, (but for the Doncaster and Harrogate
subdivisions, and Lot 112 that had been sold). [221] One
of the ten comparables discussed by Mr. Blanchette was the sale of Lot 666 that
was part of the subject property. The original sale price negotiated in July 1995
was $800,000, but an inducement of $50,000 was later paid to extend the closing
until September 1996. At 4.59 acres the initial sale at $800,000 represented $174,292
per acre. Mr. Blanchette made a 25% upwards adjustment because of the topography
and the proximity of Nordel Way to several of the lots. After his adjustment this
sale yielded a price of $217,865 per acre. [222] This sale
of Lot 666 was actually part of the subject property and the sale was negotiated
at the relevant time. There was no need to make adjustments for proximity (or
lack of proximity) to commercial services and recreational amenities that Mr.
Blanchette stated were necessary for most of the comparables. We agree that this
sale needs an adjustment for the steepness of the site and proximity of Nordel
Way (which is to be ignored in the second takings). However, we note that even
with this adjustment, the sale price per acre of $217,865 is lower than any of
Mr. Blanchette's other 1995 comparables. [223] Because
the subject property still did not have any approvals in place in 1995, the price
per acre for the subject property has to be discounted in a similar manner as
for the first taking: a deferral for obtaining approvals and some adjustments
for both size and easements, although the overall adjustments would be less for
this somewhat smaller remainder in 1995. When we discount Mr. Blanchette's 1995
valuation of $315,000 per acre, based on comparables other than Lot 666, for time
to obtain approvals as well as size and easements we obtain a price of approximately
$205,000 per acre. This is within the range of the actual sale price of Lot 666
at $174,292 per acre and Mr. Blanchette's adjustment of this price for steepness
and proximity to the Project (but not for approvals or size or easements) at $218,000
per acre rounded. [224] We conclude an estimation of value
for the subject property of $210,000 per acre which provides a value for the second
taking of 1.43 acres on September 1, 1995 of $300,300. 10.
MARKET VALUATION OF THE EASEMENT FOR THE STORM SEWER [225]
There is a claim for the value of a storm sewer easement with respect to Lot 112.
The Ministry took a sewer easement in 1985. The claimant Whitechapel Estates Ltd.
sold Lot 112 to Whistler Investments in August 1991. Mr. Elsom says that he reserved
the right to claim compensation, although we were not provided with any documentation
such as the interim agreement that confirmed this arrangement. The claimants did
not provide us with a specific amount for this claim, but we assume that they
would calculate it by multiplying the area of the easement times their valuation
of the subject property in 1985 of $160,000 per acre. [226]
Counsel for the respondent conceded that compensation for this taking was payable.
The statutory right of way plan showed the taking for the sewer easement to be
0.1061 hectares (0.26 acres or 11,421 square feet). After the hearing, counsel
for the respondent made supplementary submissions in which he said that $25,012
for the storm sewer easement was appropriate compensation. This sum was based
on Ms. Watson's evaluation per lot, the number of lots subsequently developed
by the purchaser, times the ratio of the area of the storm sewer easement and
the area of Lot 112 after the taking. [227] We
have valued the subject property at $28,000 per lot. Both Mr. Blanchette and Ms.
Watson agreed that Lot 112 was 8.1 acres before the first taking for Nordel
Way and that the first taking was 0.188 acres (760.8 square metres) leaving 7.9
acres after the taking. We note that the respondent's submission includes
100% of the land value for the easement. After considering our lot valuation,
deferral for time to obtain approvals for Lot 112, and the revised size of Lot
112 after the taking for Nordel Way, we conclude that $25,000 is appropriate
compensation for the storm sewer easement. 11.
DISTURBANCE DAMAGES or BUSINESS LOSSES -- DELAY CLAIM 11.1
Claimants' position [228] Mr. Blanchette's calculation
of the loss due to delay was made by determining the cash flow from the sales
of 635 lots, with and without the taking, using a flat rate of $30,000 cash from
each lot sold. He assumed that the 1979 application based on the Hanson-Erb report
was refused because of the Project and that development of the Phase 1 Doncaster
subdivision and the Phase 2 Harrogate subdivision were not able to proceed because
of the Project until 1986, some six years later. In making his calculations Mr.
Blanchette estimated that, if there had been no taking, 170 lots would have been
sold before the taking and that the balance of 465 lots would have been
sold between 1986 and 1993. He estimated that, with the taking, the same 635 lots
could have been sold between 1986 and 1999. Both of these scenarios assume a
before situation with no Project and 635 lots. He based his cash flow analyses
on $30,000 as the price paid per raw lot without any consideration of development
costs or developer profit. He added the cash flow that had accumulated by 1985
to the present value of the two streams of cash flow after 1985, as of the date
of taking in May 1985, using a discount rate of 10% per annum, which he thought
was appropriate for 1985. The $5,486,531 difference in the present values of the
cash flows represented his estimate of the cost of delay. [229]
Counsel for the corporate claimants submitted in argument that Mr. Blanchette's
estimate of the delay may be an underestimate since it did not take into account
the lack of development from 1985 until the date of the hearing. As an alternative
to the delay claim advanced by Mr. Blanchette, the claimants submitted that a
delay claim could be based on Lofranco v. Metropolitan Toronto (1982),
25 L.C.R. 11 (Ont. L.C.B.), a case in which there was a partial taking and a temporary
construction easement on the remainder. The Ontario Board accepted that as long
as the temporary construction easement was in effect, development of the remainder
was sterilized. Compensation for the temporary easement was awarded on the basis
of the market value of the remainder invested at 10%, compounded monthly, for
the length of the temporary easement. Counsel for the corporate claimants in the
present case estimated the market value of the entire subject property after
the taking at $21,712,000 (135.7 acres x $160,000 per acre). He assumed that this
was invested at 10% for five years for an approximate value that he reported at
$10,000,000, but which was, in fact, approximately $13,000,000 or for 10 years
for an approximate value of $34,000,000, or for 15 years for an approximate value
of $68,000,000. [230] Mr. Elsom based his delay claim on
the delay of the Doncaster Phase 1 and the Harrogate Phase 2 subdivisions only.
He assumed that Doncaster was delayed for three years from June 1983 to June 1986
and that Harrogate was delayed for four years from June 1985 to July 1989. He
assumed that the value of the subject property at $160,000 per acre was halved
after the taking and using the principle in Lofranco he made a
calculation using the market value of each subdivision after the taking
that he purported to invest at 10% for the three and four year delays respectively
that provided him with a total for both subdivisions of $7,094,400. He asserted
that this sum was his claim for damages for the development freeze. 11.2
Respondent's position [231] The respondent presented
a model with a number of assumptions provided by counsel to show the effect of
delay on developer's return from the Project. Ms. Watson did the initial work
on the model but it was subsequently modified by another appraiser with particular
expertise in spread sheet computations, David Aberdeen of D.A. Aberdeen &
Associates Ltd. The final model addressed the development of the Phase 1 Doncaster
and Phase 2 Harrogate subdivisions only. It assumed a two year delay period in
the development of these two subdivisions as a result of the Project: in the first
scenario, the Doncaster subdivision started in 1983, with a one year deferral
to obtain rezoning and development approvals (no delay) and in the second scenario,
it did not start until 1985, with the same one year deferral (delay). In both
cases, it is assumed that the Project is in place and there is the same number
of lots in the Doncaster and Harrogate subdivisions that in fact were developed
after the taking. It is further assumed that the developer owned the land
with no debt, (as Mr. Elsom did) but that the servicing and subdivision costs
would be 100% financed at actual interest rates for each year provided by Ms.
Watson. The model used current dollars and assumed that the two subdivisions were
developed, with year by year servicing costs, development cost charges, and municipal
taxes provided by Ms. Watson. Absorption rates and lot sale prices were also provided
by Ms. Watson. The model assumed that the net cash from the development and sale
of these two phases would be used to repay bank loans taken out to finance the
servicing costs and other expenses and that the excess would be invested in successive
five year Guaranteed Investment Certificates until December 31, 2000. Ms. Watson
provided the relevant interest rates for the GICs. [232]
Mr. Aberdeen calculated the total returns from these two phases to December 31
2000, including interest, to be $10,882,223 assuming no delay with development
starting in 1984, and $10,307,861 assuming a two year delay with development starting
in 1986. The respondent submitted that the damages for delay should not be any
greater than the difference in these two sums of approximately $575,000. 11.3
Board's Analysis and Conclusion 11.3.1 Were the
claimants subjected to a delay as a result of the Project? [233]
The claimants state that the development of the entire subject property was delayed
by the Project commencing in 1979 when the application based on the Hanson-Erb
report was rejected by Delta. According to the claimants, but for the development
of Doncaster and Harrogate (and the sale of Lot 666 and 112), delay of the rest
of the subject property was ongoing at the date of the hearing. The respondent
states that the delay was restricted to a two year delay from 1984 until 1986
in the development of the Doncaster and Harrogate subdivisions only. [234]
In considering whether there was any delay we must review the evidence of what
in fact happened with respect to development of the subject property. While market
value is measured on an objective basis as the sale price reached between a hypothetical
purchaser and a hypothetical seller, disturbance damages are based on what financial
losses the claimants have actually suffered. As a result we use hindsight and
the actual events that have occurred in assessing these claims. The onus is on
the claimants to prove that there has been a delay that is directly attributable
to the taking or that results from the construction or use of the Project. The
Ministry is not responsible for other factors that may have caused delay in development
of the subject property. See para 165 of Sequoia Springs. [235]
We have previously described the application based on the Hanson-Erb report as
an ambitious development that included commercial development, a hotel, offices,
public service buildings, and over 150 multi-family units in addition to single
family development around the perimeter. Although one of the reasons Delta rejected
the application was that there were too many unknowns because of the projected
new bridge, Delta also stated that the application did not reflect the land uses
identified in the Draft Delta Community Plan. This application was eventually
withdrawn by the claimants. [236] In April 1983 the claimants
then applied to rezone and subdivide the 10 acre site that became the Phase 1
Doncaster subdivision. This application received first and second reading in September
1983 and, following a public hearing, received third reading on October 3, 1983.
There was evidence of a dispute between Delta and Mr. Elsom as to locating a relatively
large park space on the subject property adjacent to the proposed subdivision.
Delta told the claimants in February 1984 that there would be a postponement until
the access routes were finalized. In March 1985, the claimants requested that
the application proceed since the access routes were now known. In October 1985
there was evidence of some outstanding issues, including the park, but in the
end Delta decided to obtain the park in the next stage of development and recommend
approval at fourth reading in November 1985. These 48 lots sold between May 1986
and April 1988. [237] The claimants submitted a second
application to rezone and subdivide what became known as the Phase 2 Harrogate
subdivision in April 1986, at the same time as the 48 lots in Phase 1 were coming
on stream. The application received first and second reading in September 1986
and then was delayed for some time because of Delta's request for an agreement
on park dedication and an overall road network for the whole of the subject lands.
Final reading and approval was eventually granted in October 1987. The 63 lots
sold between May 1988 and October 1989. [238] Between 1988
and 1990 there were other applications for the subject property with respect to
the Marlborough College school site, the gas station site and five applications
for single family residential subdivisions. The only one of these that was at
least partially successful was the application to do with Marlborough College. [239]
The claimants had earlier developed the Royal York subdivision located close to
the subject property. At December 31, 1978 the claimants had an inventory of 110
unsold lots in this subdivision. These lots were sold during the next seven years
as follows: 43 lots in 1979, 24 lots in 1980, 15 lots early in 1981, 6 lots late
in 1982, 8 lots in 1983, 6 lots in 1984, and 8 lots in 1985, with the last 2 sales
not occurring until December 1985. Six of the lots that sold in 1984 and 1985
were sold on condition that the builder purchaser sold another lot in the subdivision
(with the residence) to an ultimate purchaser by a specified date. This type of
condition did not appear in interim agreements for other years. An analysis of
the sales show that the market plummeted in 1981 with average prices falling from
over $90,000 in the seven months to July 31 1981 to approximately $45,000 in the
seven months ended December 31 1982. [240] Mr. Elsom, in
cross-examination, agreed that he had provided the following answer in the family
law trial during December 1984 to a question from his counsel as to the state
of the market in December 1984: Well, my Lord,
there is no market. It - its vanished entirely in the last six months. I refer
to the fact that I had a stable of builders on the Royal York subdivision and
for various reasons now that group of builders are not proceeding with any more
purchases. Therefore, I have eight lots remaining on the Royal York subdivision.
They are 60 foot lots. They are really better than these, the view. They are standing.
The builders are not now in a position to purchase lots because they are already
stuck with their inventory from the preceding years. … Now, there may be the odd
sale to a private purchaser but in essence there is no longer any justification
to proceed with a development. Certainly, I would want to see the remaining lots
on Royal York sold. I might add, my Lord, that quite apart from my subdivision,
Royal York, there are remaining lots on quite a number of other subdivisions surrounding
the Royal York area that have lots that are unsold. So it is now a question of
doing the preparatory work and wait for the next period of building activity. [241]
First, dealing with the applications after 1988 for the school site, the gas station
site and the unsuccessful applications for single family residential development,
the evidence does not support that any failure of these applications was linked
to the Project. The Chevron application was rejected as a result of the neighbours'
opposition to a gas station in that location. While there was ongoing discussion
about an overpass in the context of several of the applications, our review of
the evidence leads us to conclude that these applications after 1988 were ultimately
rejected because of the dispute between Delta and Mr. Elsom as to the location
of a park on the subject property and the request for an overall plan. We conclude
that the rejections of the claimants' various applications after the Harrogate
subdivision were not caused by the Project. [242] Second,
from the evidence we received, the claimants made no further applications between
1991 and 2000, nor is there evidence of much time spent in attempting to move
the earlier applications forward. It was not until 2001, after the hearing had
already started, that we were told that a new overall plan had just been submitted
as part of a rezoning application. We conclude that the claimants were not delayed
in any development of the subject property after 1991 as a result of the Project. [243]
Third, with respect to the failure of the Hanson-Erb application submitted in
1979, we note that while one of the reasons given for rejecting this application
was the uncertainty related to the Project, Delta made it clear that it had other
concerns about this application. The application did not reflect uses in the draft
Delta Community Plan including two locations on the subject property designated
as open space or park. In our view, the Hanson-Erb application would have been
refused or at a minimum, been extensively modified, in the absence of the Project.
In any event, in December 1978 there were still 110 lots remaining unsold in Royal
York and Mr. Elsom testified that he proceeded cautiously in the development of
his land, investing in services only when there was a market for his serviced
lots. We do not accept that the claimants were subjected to a delay as a result
of the Project as long as they had a number of lots nearby that remained unsold. [244]
Fourth, with respect to the Doncaster and Harrogate subdivision, we do find that
the Project caused some delay. Mr. Elsom estimated a three year delay for Doncaster
from 1983, when the application was first submitted, until 1986, when the first
lots were sold. However, this period covers the entire time that was spent in
obtaining approvals and servicing of the lots. The application went through first
and second reading, then third reading and a public hearing; there were negotiations
with Delta about various issues including a park location, followed by fourth
reading and approval. After final approval the services had to be installed. The
approval process and installation of services would have taken some period of
time in the absence of the Project and accordingly we do not accept Mr. Elsom's
estimation of delay. [245] The documents referred to earlier
show that there was a gap of approximately one year between February 24, 1984
and March 6, 1985 when the Doncaster application was delayed because of the Project.
The Project may well have had other effects on this application that lengthened
the time for its approval. However, in the latter part of 1981 there was a serious
fall in the market and the sale of the final lots remaining in Royal York slowed
to a trickle. The last two lots in the Royal York subdivision did not sell until
December 1985. The very low lot sales in Royal York between 1982 and 1985 suggest
that there was no loss of sales due to the Project in this period. We note that
there was only a five month gap between December 1985 when the last Royal York
lots sold and May 1986 when the first Doncaster lots sold. Although the application
process may have been delayed for one year, or longer, the development of Doncaster
was also delayed by poor market conditions and the problems with the park (aspects
that were not the Ministry's responsibility). As a result we find that the claimants
were only in fact delayed in their development of Doncaster for some period less
than a year as a result of the Project. Since the Harrogate application followed
on the Doncaster application, we conclude that there was a delay for some period
less than a year in that application as well. 11.3.2
Financial cost of delay [246] We have accepted that
the Project caused a delay of less than one year in the Doncaster and Harrogate
applications only. [247] Since Mr. Blanchette's model assumed
that the Project caused a six years delay in development of the whole property,
we do not find it of assistance. In addition, we note that there were other flaws
in Mr. Blanchette's model for estimating disturbance damages for delay including
his use of constant 1985 dollars rather than current dollars and an overestimate
of the number of lots by using the before layout in both scenarios. [248]
We also note that Mr. Elsom's delay claim calculation appears to be fundamentally
flawed. The calculations in his submissions suggested that they were based on
a delay of the receipt of $800,000 for 3 years for Doncaster, and of $960,000
for 4 years for Harrogate. However, his actual calculations were for $800,000
a year and $960,000 a year for 3 and 4 years respectively, together with interest
at 10% compounded annually, rather than for the loss of interest on those sums
compounded annually. This led to a value that was much too high. [249]
We did find Mr. Aberdeen's model useful in measuring the effect of a delay on
the developer's return. Although Mr. Aberdeen's model yielded a loss in the developer's
return when a two year delay in the development of the Doncaster and Harrogate
subdivisions was assumed, we found a different result when we examined Mr. Aberdeen's
cash flows of the developer's returns after deducting all development costs. They
showed the following:
| No delay |
Delay | | 1985 |
$1,475,907 | | |
1986 | $1,719,076 |
$ 77,821 | | 1987 | |
$2,886,749 | | 1988 | |
$1,189,685 | | Total |
$3,194,983 | $4,154,255 |
Thus, the delay
of two years increased the net return from the property by $959,272. This is because
the lot sale prices increased during the period of the delay and the various development
costs did not increase to the same degree. [250] Similarly,
when we reviewed Ms. Watson's initial research for the entire period between 1985
and 2000, lot prices increased significantly. Between 1985 and 1994, lot prices
increased from $49,000 to $170,000, then dropped to $138,000 in 1995, and were
stable in the range of $147,500 and $155,000 between 1996 and 2000. The 347% increase
in the nine years from 1985 and 1994 is equivalent to 14.82% a year compounded
annually. The 310% increase in the fifteen years from $49,000 in 1985 to $152,000
in 2000 is equivalent to 7.84% a year compounded annually. [251]
Furthermore, when we examined the record of the actual sales of lots from Doncaster
and Harrogate we found that prices increased from an average of $55,000 a lot
in 1986 to $87,036 a lot in 1989. This increase is equivalent to 16.53% compounded
annually. [252] Mr. Aberdeen was instructed to assume the
net proceeds of sale were invested in five year Guaranteed Investment Certificates.
This means that the five year rate remained in place for the full five years and
the funds would then be reinvested for further five year periods at the then prevailing
rates. The use of a five year rate during a period when interest rates were falling
has a significant impact on the final result. If we take Mr. Aberdeen's cash flow
for each year and assume investment each year in five year GICs, at the five year
rate in effect when each year's cash flow comes on stream, the amount on hand
at December 31 1988 would be as follows:
| | No
delay | Delay | | 1985
cash flow | $1,475,907 | |
Interest on 1985 cash flow to December 31 1988
compounded at 10.5% a year | $ 515,435 | |
| 1986 cash flow |
$1,719,076 | $ 77,821 |
Interest on 1986 cash flow to December 31 1988
compounded at 9.56% a year | $ 344,398 |
$ 15,591 | | 1987 cash flow | |
$2,886,749 | Interest on 1987 cash flow
to December 31 1988 at 9.42% a year | |
$ 271,932 | | 1988 cash flow | |
$1,189,685 | | | |
| | Total at December 31 1988 |
$4,054,816 | $4,441,778 |
As can be seen,
the total cash flow from lot sales plus interest to December 31 1988 is still
greater by $386,962 with a two year delay in the development. [253]
When we reviewed Mr. Aberdeen's model we found that the only reason that there
was a greater return from a development with no delay was the rates of interest
applied to the investment and reinvestment of the cash flow from December 31 1988
to December 31 2000. The use of a five year rate in a period of generally falling
interest has the effect of applying a higher rate of return to the cash flow with
no delay. The 1985 cash flow earns 10.5% for five years and is then reinvested
for a further five years at 10.98% [higher than in 1985 due to the fact that interest
rates spiked up in 1989 and 1990 before returning to the downward pattern] and
then for a further five years at 7.06% for an overall average rate of 9.51% during
the fifteen year period. The 1987 cash flow which is received assuming a two year
delay earns 9.42% for five years, then 7.33% for the next five years and 4.71%
for the final period to December 31, 2000 for an overall average rate of 7.52%
during the thirteen year period. If the cash flow had been invested and reinvested
in one year Guaranteed Investment Certificates through to December 31, 2000 the
total return with a two year delay would be greater than in the scenario with
no delay. [254] Mr. Aberdeen's estimation of a decrease
of $575,000 in the total return to the developer assuming the two year delay flows
entirely from the methodology used to calculate the interest on the investment
of the cash flow. The increase in cash flow for Doncaster and Harrogate from $3,194,983
with no delay, to $4,154,255 with a two year delay, amounts to 30%. Since the
assumed two year delay led to an increase in compensation and the only loss is
related to an assumption in the term of the investment, we find that the model
does not support any losses accruing for delay. This result would also apply to
the shorter period of delay of less than one year that we have determined occurred
in this case. [255] We have to consider the claimants'
alternative claim for delay based on Lofranco. This case valued the construction
easement by treating the market value of the land as an investment at 10% as long
as the easement was in effect. This compensation is based on the claimant having
the interest on the market value of the land as "rent" for the period
of the easement. [256] A more directly relevant case is
the approach to estimating damages for delay in the Ontario Municipal Board decision
in Dell Holdings Ltd. v. Toronto Area Transit Operating Authority (1990),
43 L.C.R. 138. The Ontario board reviewed several measures of compensation for
the period of the delay including extra holding costs, the increase in various
development costs, the reduction in developer's profit and the deferral in receiving
the developer's profit. The Ontario board found that these various measures ranged
between $75,000 and $600,000, although it considered some measures in combination.
We note that the holding costs were calculated in the same manner as the calculation
was made in Lofranco, by assuming that the market value of the land had
been financed at 10% for the period of delay. These holding costs appear to be
mistakenly reported by the Ontario board as $86,000 when the calculation in fact
produces $860,000. As this board commented at para 167 and 168 in Sequoia
Springs, the Ontario board in Dell decided that the evidence that
they had been given on the reduction in developers profit was speculative because
it was based in part on one aspect of the development that had never been built
and might never be built. As a result it chose $500,000 for the quantum of damages,
as a round number within the range of the various calculations. Although the amount
of damages was appealed by the owner, the Ontario Divisional Court denied the
appeal of this issue saying that the board decision should not be overturned so
long as it had exercised its discretion after reviewing the evidence. See (1991),
45 L.C.R. 250. Although this case was later considered by the Ontario Court of
Appeal and the Supreme Court of Canada nothing further was said about the quantum
of damages. See (1995), 55 L.C.R. 1 (Ont C.A.); (1997), 60 L.C.R. 81 (S.C.C.). [257]
Finally in Sequoia Springs, this board considered several alternative
means of measuring damages for delay presented by the claimant's appraiser. At
para 170 it accepted the model whereby the income and expenses were deferred by
the delay and the compensation was measured as the market value of the remaining
land valued at the discount rate for the period of the delay. [258]
When we consider Mr. Aberdeen's model in the present case with the measures of
damage discussed in these three cases, we note that none of the previous cases
considered the wider picture as to what losses the owner actually suffered when
factors such as financing costs, changes in the market value of the lots, changes
in development costs, and ongoing property taxes were considered as a whole. In
each of the earlier cases only one aspect, such as the holding costs or interest
paid on the financing of the property during the period of delay or an increase
in a particular servicing cost, was dealt with in isolation. In this case, the
model showed that the sale price of the developed lots increased by more than
22% as a result of the two year delay. However, servicing and development costs
increased by only 7% so that the overall net cash return increased by 30%. Thus
the two year delay period increased the return to the developer by a compound
rate in excess of 14% a year. The model takes the financing costs, increases in
servicing costs, and the ongoing payment of property taxes into account, but the
rising market in this period, more than offsets any increase in costs. We are
satisfied that a similar situation would have prevailed had the delay period been
longer since Ms. Watson's research showed that lot prices increased by an annual
compound rate of more than 14% from 1985 to 1994 with a much lower rate of increase
in construction costs during the same period. These returns are higher than the
10% annual return used by the claimants in their estimates of loss due to delay.
We accept the model in this case as offering a more accurate indication of the
real effects of the delay and as a result we make no award under this heading. [259]
Finally, we note that the claimants' have made an additional claim for holding
costs on top of their claim for delay. They have also made a claim for the increase
in Development Cost Charges that will have to be paid as a result of the delay.
As discussed above these are different aspects of the same claim. Given that the
model supports no actual losses, these additional claims have no basis. 12.
DISTURBANCE DAMAGES -- OTHER EXPENSES 12.1 Engineering
expenses thrown away as a result of the taking [260]
The claimants have claimed $220,000 at this time for engineering expenses for
Mr. Buchan's services through Hub Engineering which were incurred as a result
of the taking and are in effect thrown away. This work was detailed in argument
as follows and in fact totalled $154,400, rounded, not $220,000:
| a | Ministry
taking | $70,700 | |
b | Phase 1 - 10% of account for Nordel Way issues |
$ 3,468 | | c |
Phase 2 - 10% of account for Nordel Way issues |
$ 3,822 | | d |
82nd Avenue, overpass and connecting road |
$37,199 | | e |
Sanitary sewer under Nordel Way | $ 7,690 |
| f |
Efforts to obtain agreement on overall plan |
$14,275 | | g |
Hester Creek ravine | $ 4,837 |
| h | Nordel Way
(112th to 120th) | $ 474 |
| i | Nordel overpass
and 82nd | $ 316 | |
j | Phase 3 | $
2,584 | | k |
108th subdivision | $ 5,867 |
| l | 108th subdivision
north of 84th | $ 3,189 | | |
| | Total | |
$154,421 | [261] Counsel for the respondent
concedes that items a, b, c, g, and i were valid disturbance damages and are payable
by the respondent. These five items total $83,143. [262]
We note that the largest item, item a, is for with work and meetings to do with
various aspects of the alignment and construction of the Project. The Ministry
has agreed that this engineering work would not have been necessary but for the
expropriation. In addition to this item and the other four items detailed above
that have been accepted by the respondent, we have reviewed the invoice for item
h and find that the $474 on this invoice is related to the Project. [263]
We have found that the failures of the various subdivision applications after
Phase 2 were unrelated to the Project. Work on attempting to have an overall plan
approved is also unrelated to the taking or the construction of the highway. The
respondent is not responsible for development work that would have been necessary
in any event of the Project. See para 114-116 of Sequoia Springs. We reject
the claims for items f, j, k, and l. [264] Item d is described
as being for the proposed overpass and connecting roads. However, the three invoices
indicate that they were for work that was related to a residential subdivision
along 82nd Avenue. Again we do not find that the engineering work for a potential
subdivision is related to the Project. We deny the claim for item d. [265]
Our review of the evidence indicates that the invoices for items e, f, i, j, k,
and l were not provided to us. We have already disallowed items f, j, k, and l.
With respect to item e, the evidence was that it was for work running a sanitary
sewer on Lot 112 in the existing rights of way to tie it into the trunk GVRD sewer.
Mr. Buchan testified that the rationale for doing the work was that if the land
was sold in a hurry, Mr. Elsom wanted the sanitary sewer in place. We find that
this work was done in anticipation of future development and would have been done
whether or not the Project was built. On the evidence provided the Ministry is
not responsible for the work claimed for item e and we reject this claim. [266]
Thus, we allow a total of $83,617 for engineering services for work made necessary
as a result of the Project. 12.2
Executive Time [267] The claimants claimed $500,000
for executive time of Mr. Elsom. Mr. Elsom suggested that he had spent approximately
20% of his time since 1979 on the expropriation claim. We were provided with a
list from his accountant of monies that had been paid to Mr. Elsom as personal
remuneration between 1979 and 1999. This salary had been paid from one or more
of his companies and varied significantly from year to year from a low of $20,000
to a high of $1,966,000. Mr. Elsom acknowledged that one factor that affected
the amount was the revenue from development that had been received that year,
but he indicated that there were other factors. [268] The
Ministry's position is that there should be no award for executive time. It referred
us to the discussion of this issue in Sequoia Springs. Mr. Elsom was vague
in providing evidence as to how his salary is determined. There was no evidence
that any of the claimants had suffered a financial loss as a result of Mr. Elsom's
time spent on the expropriation. [269] In Pay Less
Gas Co. (1972) Ltd. v. British Columbia (Minister of Transportation and Highways)
(2001), 74 L.C.R. 81 (B.C.E.C.B.), this board reviewed a number of cases to do
with executive time. The premise is that as a result of the expropriation the
claimant loses money because an executive officer has been required to deal with
matters arising from the expropriation rather than his or her regular duties.
At para 293 the test was stated to be whether there was credible evidence of a
financial loss or expense to the claimant, or a reasonable inference of a consequential
loss, as a result of the time expended by the individual. In Pay Less
the claimant's manager of real estate and development spent time finding an alternative
site for relocation of the claimant's business as a result of the expropriation.
The board decided that it was reasonable to infer some loss to the claimant for
this time spent by the manager of real estate and development and awarded $20,000. [270]
Claims for time spent in preparing a compensation claim or in attending a hearing
to give evidence are not a compensable disturbance damage. This includes time
spent meeting with counsel, meeting with expert witnesses, attending discoveries,
and reviewing documents from the claimant's own files or the authority's files
in preparation for the claim or the hearing. See E.C.E. Todd in The Law of
Expropriation and Compensation in Canada, 2nd ed. (1992), p. 290. [271]
In this case, much of the time spent by Mr. Elsom was in negotiations with the
Ministry about settlement, and later in pursuing the claim for compensation. This
is not compensable as disturbance damages. In a decision of this board, Reon
Management Services Inc. v. British Columbia (2001), 72 L.C.R. 257 (B.C.E.C.B.),
an invoice from the claimant's principal for time spent in pursuing the expropriation
claim was considered in a cost application and ultimately rejected. Mr. Elsom
also spent significant time in dealings with Delta. The respondent is not responsible
for what is the ordinary time spent by a developer in making applications to develop
or sell land. Neither is it responsible for time that was spent working on subdivisions
that have not yet been approved because of Mr. Elsom's long standing difficulties
with Delta about such issues as park and an overall plan. While the expropriation
did create some new issues of dispute, including a potential for an overpass and
maintenance of the embankments, after reviewing all of the evidence, we are not
satisfied that these issues occupied a significant portion of Mr. Elsom's time.
It is our view that the main activities on which Mr. Elsom spent time that are
properly attributable to the expropriation are the detailed negotiations that
occurred with respect to the construction of Nordel Way in an effort to minimize
the impact on his development of the remainder. This work involved his engineer,
Mr. Buchan, and Mr. Buchan's expenses submitted as engineering invoices have been
dealt with separately. We are satisfied that Mr. Elsom spent some limited time
that is directly attributable to the expropriation, although we agree with the
respondent that the claimants' evidence on this is weak. [272]
However, the measure of compensation is not how much time a claimant or a principal
may have been spent on an expropriation, but rather whether the claimants have
suffered a financial loss or can be inferred to have suffered a financial loss.
We have no evidence that any of the claimants suffered a financial loss arising
from Mr. Elsom's time spent on those aspects of the expropriation that are not
associated with pursuing a claim for compensation. Neither do we have any evidence
on which we can infer a financial loss to the claimants. While the Doncaster and
Harrogate subdivisions might have occurred somewhat sooner if Mr. Elsom had not
been spending time dealing with the construction of the Project, we have concluded
that there was no financial loss as a result of any delay in the development of
these two subdivisions. There was no evidence to support any further development
income from the subject property if Mr. Elsom had had more time available. We
note that much of the time that Mr. Elsom did spend on the subject property was
unsuccessful and did not result in any development income, a failure that we have
concluded is not attributable to the expropriation. While Mr. Elsom apparently
had other companies, we were not provided with any evidence that supported a potential
for more income to Mr. Elsom if he had had more time available (ie he had not
had to spend the time that was directly attributable to the expropriation). As
a result we make no award for this claim. 13.
SUMMARY [273] We have awarded the following compensation
with respect to the first expropriation:
| 1. |
Market value of the land taken and the reduction in market value to the remainder |
$1,528,000 | | 2. |
Market value of the ravine land |
$ 14,500 | | 3. |
Market value of the storm sewer easement |
$ 25,000 | | 4. |
Disturbance damages for delay |
nil | | 5. |
Disturbance damages for engineering services |
$ 83,617 | | 6. |
Disturbance damages for executive time | nil |
| Total | |
$1,651,117 | [274]
With respect to the second expropriation we have concluded:
| 1. |
Market value of the second taking as of September 1, 1995 |
$ 300,300 | 14.
INTEREST and COSTS [275] Mr. Goodwin, counsel for the
corporate claimants, asked that all issues related to interest and costs be adjourned
until after the release of this decision. The respondent agreed and accordingly
interest and costs are adjourned at this time. Nonetheless we make a few observations
that are relevant to these claims and may facilitate the parties in settling these
issues in whole or in part without further submissions. To the extent that the
issues do not resolve and a further hearing is necessary, none of these comments
are intended to be determinative. [276] The first taking
predated the enactment of the Act in 1987. The respondent made two payments of
$1,018,936 on July 4, 1986 and $781,064 on April 21, 1988, for a total of $1,800,000
with respect to the first expropriation. An advance payment of nil was made on
October 11, 1995 with respect to the second expropriation. Because the first taking
occurred prior to the Act coming into effect, the two payments made with respect
to the first expropriation were not made under section [20] of the Act. There
were no appraisals accompanying these two payments. An application for an order
compelling delivery of an appraisal report under section [20] of the Act was made
by the claimants in 1994 but this board decided that it did not have jurisdiction
to make such an order for an expropriation that preceded the Act. See (1994),
54 L.C.R. 306. [277] If the payments for the first expropriation
were not made under section 20 of the Act, there is an issue as to applicability
of section 46(1) and interest that is to be paid under that section. The advance
payment with respect to the second expropriation was made in 1995 and was made
under section 20. [278] There is an outstanding order of
a different panel of this board made September 15, 1995, with respect to interest.
The board granted the claimants' adjournment of the compensation hearing that
was scheduled for six weeks commencing September 25, 1995. The former Vice chair
Fiona St. Clair, who chaired the panel, stated in an oral decision: we
are … very firmly of the view that the prejudice to the claimants has been largely
self-inflicted in that these two major items [i bringing an application in advance
of the hearing as to whether Mr. Elsom's report on the valuation of the property
was admissible and ii complying with the order of the Chair made July 28, 1995
for the claimant to produce financial and tax records unless the business loss
claim was abandoned] could have been, and should have been, dealt with prior to
this time. In light of that, we are ordering as a condition of the adjournment
that there be an interest penalty pursuant to section [47], because we do view
this as an unreasonable delay in the proceedings caused by an owner. We therefore
order that the claimants be entitled to no interest between the date that hearing
was scheduled to commence [September 25, 1995] and the date that it will actually
convene [June 5, 2000]. An application for judicial
review of this decision (and another application heard on October 19, 1995 with
oral reasons provided on October 27, 1995) was eventually filed on October 10,
1996, (over a year later) alleging bias of the panel who had heard the September
15, 1995 application. After various legal proceedings Mr. Justice Macdonald heard
this application and in his decision reported at (1999), 66 L.C.R. 193 he refused
to find bias by any member of the panel after specifically dealing with their
participation in the application on September 15, 1995, granting the adjournment
and denying any interest that might be payable. [279] We
note two cases in which this board was asked to reconsider an earlier panel's
decision to deny the claimant's interest under section 47(a) from the date when
the initial compensation hearing was scheduled to commence or adjourned and when
the hearing recommenced. See Glendale Trading Ltd. v. British Columbia (Minister
of Transportation and Highways), (2000) 70 L.C.R. 235 (B.C.E.C.B.) at para
58 and Premanco at para 262. [280] We also note the recent
decision of the British Columbia Court of Appeal in Daflos v. School District
No. 42 (Maple Ridge-Pitt Meadows), unreported, 2002 BCCA 277 with respect
to additional interest under section 46(4). [281] The total
compensation payable with respect to the first expropriation is less than 115%
of the advance payments. However, this expropriation occurred before the Act came
into force and as a result it is not certain whether the provisions of the Act
with respect to costs apply. The total compensation with respect to the second
expropriation is more than 115% of the advance payment and therefore the claimants
appear to be entitled to their costs necessarily incurred to assert their claim
for compensation with respect to the second taking. These are the actual reasonable
legal, appraisal, and other costs to assert their claim for compensation with
respect to the second taking until June 28, 1999 and to their costs as prescribed
in the Tariff of Costs Regulation, B.C. Reg 189/99 after that date. THEREFORE
IT IS ORDERED THAT the Ministry of Transportation and Highways shall pay Whitechapel
Estates Ltd., Piccadilly Estates Ltd., Delsom Estates Ltd., and Norman Dennis
Elsom: 1. Compensation under section 40 of the Act for
the market value of the land that was acquired in 1985 and the reduction in market
value of the remaining land in the sum of $1,567,500. 2.
Compensation under sections 34 and 40 of the Act for business losses for engineering
expenses thrown away as a result of the taking in the amount of $83,617. 3.
Compensation under section 40 of the Act for the market value of the land that
was acquired in 1995 in the sum of $300,300. Any awards
for interest and costs are adjourned pending further submissions. |