| January 26, 2001, ECB Control No.:
93/95/198 (71 LCR 315)
| Between: | Sequoia
Springs West Development Corporation Claimant | | And: |
Her Majesty the Queen in Right of the Province of British Columbia as
Represented by the Minister of Transportation and Highways Respondent |
| Before: | Sharon
I. Walls, Vice Chair Lesley Eames, AACI, P.App. ,Board Member Julian K.
Greenwood, Board Member | | Appearances: | C.
Edward Hanman, Counsel For The Claimant Fran Crowhurst, Counsel for the Respondent
Catherine J. Parker, Counsel for the Board | REASONS
FOR DECISION 1.
INTRODUCTION [1] A decision on costs in this matter
was released September 1, 2000 following on a general decision on compensation
released on February 15, 2000. In the September 1, 2000 decision we determined
that the total compensation awarded to the claimant Sequoia Springs West Development
Corporation ("Sequoia Springs") was greater than 115% of the advance
payments made by the expropriating authority under section 20(1) and (12) of the
Expropriation Act, R.S.B.C. 1996, c.125 ("the Act"). As a result,
Sequoia Springs was entitled to its costs. [2] Relevant
portions of section 45 of the Act are:
| 45 | (3) | Subject
to subsections (4) to (6), a person whose interest or estate in land is expropriated
is entitled to be paid costs necessarily incurred by the person for the purpose
of asserting his or her claim for compensation or damages. | | (4) | If
the compensation awarded to an owner, other than for business losses, is greater
than 115% of the amount paid by the expropriating authority under section 20 (1)
and (12) or otherwise, the authority must pay the owner his or her costs. |
| (5) | If
the compensation awarded to an owner is 115% or less of the amount paid by the
expropriating authority under section 20 (1) and (12) or otherwise, the board
may award the owner all or part of his or her costs. | [3]
Subsequent to the September 1, 2000 decision the respondent, the Minister of Transportation
and Highways ("MoTH"), discovered that it had inadvertently omitted
inclusion of a third advance payment in the sum of $54,500 plus interest made
on November 27, 1996. This meant that the total advance payment was $1,479,500
rather than $1,425,000. With this correction, the total compensation awarded of
$1,680,000 drops to 113.6% of the advance payment from 118%. [4]
Sequoia Springs acknowledged that it had received the payment and that it was
prepared to account for this payment in its dealings with MoTH. However, it took
the position that the September 1, 2000 decision was the board's final decision
on the issue as to whether we had discretion with respect to costs and we were
therefore functus officio on this matter. MoTH brought a Notice of Motion
requesting that it be permitted to introduce the evidence of this further advance
payment. This application was heard January 10, 2001. 2.
FUNCTUS OFFICIO [5] Both parties referred us
to Chandler v. Alberta Association of Architects, [1989] 2 S.C.R. 848.
In this decision the Practice Review Board of the Alberta Association of Architects
reviewed the practice of a firm of architects and issued a report that made a
number of findings of unprofessional conduct. This was outside the statutory mandate
of the Practice Review Board and the Court of Queen's Bench quashed the Board's
findings. The Board indicated that it intended to continue the original hearing
and consider whether a further report should be prepared. The issue arose as to
whether it was functus officio. Sopinka J. speaking for the majority held
at p. 862 that the principle applies to administrative tribunals but that "its
application must be more flexible and less formalistic in respect to the decisions
of administrative tribunals which are subject to appeal only on a point of law".
In Chandler, the Board's original report was a nullity and it was permitted
to reconsider the matter and render a valid decision. [6]
A number of other cases were discussed but the most relevant was Re Grier and
Metro International Trucks Ltd. (1996), 133 D.L.R. (4th) 236 (Ont. Div. Ct.).
In this case an employment standard officer made an order with respect to vacation
pay for employees of a previous employer. There was an appeal hearing before a
referee in which an agreed statement of facts contained a mistake with respect
to the time period within which the new employee had replaced the previous employer,
making it a year and two days rather than the actual time frame of two days. The
referee reversed the employment standards officer's award of vacation pay and
her misapprehension of the time frame appeared to influence her decision. When
the mistake was pointed out the referee said that she was functus officio
and could not reconsider her decision. MacPherson J. speaking for the court relied
on Chandler. He expressly adopted the comments of Sopinka J. as to the
flexible approach to functus officio that should be applied by administrative
tribunals. At p. 243 he concludes: In the
present case, the parties made a mistake. The mistake influenced the decision
of the referee. I can see no compelling reason for concluding that the mistake
should not be corrected and the matter placed back before the referee for a new
decision which would be untainted by reliance on the incorrect fact. [7]
In our case there is an appeal, with leave, from awards by the Expropriation Compensation
Board to the Court of Appeal. Indeed, there has been both an appeal and a cross
appeal of our original decision in this matter made February 15, 2000. However,
these appeals did not include an appeal of the decision on costs, presumably because
the mistake in the advance payment requires additional evidence to correct it.
We see the facts in this case as being similar to those in Grier. On the
basis of this case we have discretion to correct this one small mistake in the
facts that was common to both parties and we exercise our discretion to make that
correction. 3. DISCRETION
AS TO COSTS [8] If the mistake in the advance payment
is corrected then the total compensation awarded is only 113.6 % of the advance
payment. Therefore under section 45(5) we have discretion with respect to costs. [9]
MoTH's main submission, if we have discretion with respect to costs, was that
it had sent a "Calderbank" settlement letter to Sequoia Springs shortly
before the compensation hearing. This letter was dated Wednesday November 11,
1998 and offered to settle the claim for $2,300,000. It reserved the right to
bring the letter to the attention of the board on the issue of costs. The settlement
offer was not accepted and the compensation hearing commenced on Monday November
16, 1998. As indicated above, final compensation awarded was $1,680,000. [10]
The issue of Calderbank settlement letters in expropriation cases was fully addressed
by this board in Baines v. British Columbia (Minister of Transportation and
Highways) (No 2) (1997), 62 L.C.R. 210. The board concluded at p. 220 in that
case: a Calderbank letter may be one factor
in assessing the reasonableness of the owner in pursuing his claim for compensation,
keeping in mind the different cost principles applicable in expropriation cases. The
board went on to consider the range of market value put forward by the two appraisers.
Since the settlement offer was less than the market value (plus agreed disturbance
damages) put forward by the claimant's appraiser the board stated it was "unable
to say that the claimant's rejection of the offer ... in the Calderbank letter
was unreasonable". [11] In the present case we note
that the market valuation set out in the claimant's appraiser's report was $2,600,000.
There were also two substantial claims for disturbance damages. We did not accept
the market valuation nor either of the claims for disturbance damages as presented.
In fact, in the original February 15, 2000 decision, we were critical of the claimant's
evidence and assumptions on a number of points. However, after considering all
the circumstances we conclude that there was some reasonable basis for the claimant
to expect to obtain more than the $2,300,000 offer to settle in the Calderbank
letter. We also note that the settlement letter was received only two working
days before the compensation hearing was scheduled to commence. Similar to the
board's finding in Baines we are "unable to say that the claimant's rejection
of the offer ... in the Calderbank letter was unreasonable". [12]
Further, we note that Sequoia Springs achieved compensation close to the minimum
percentage for obtaining full costs as a matter of right. Most importantly it
is our opinion that there were justiciable issues in this case which reasonably
warranted being brought to the board for determination. See Daflos v. School
District No. 42 (Maple Ridge-Pitt Meadows) (1999), 68 L.C.R. 167 (B.C.E.C.B.)
at 222. We conclude that the claimant is entitled to its actual reasonable legal,
appraisal, and other costs until June 28, 1999 and to its costs as prescribed
in the Tariff of Costs Regulation, B.C. Reg 189/99 after that date. |